Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli to Vajarahalli.

DAILY PROGRESS REPORT ON FABRICATION YARD DATE :13-02-2021


MS PIPELINE WORKS
Previous Day Present Day Cumulative Quantity
Plate
Sl. No. Description
Thickness Numbers Meters Numbers Meters Numbers Meters

20 1382 3455 23 57.5 1405 3512.5


1 Edge cutting (Nos)
18 290 725 0 0.0 290 725.0
20 1324 3310 30 75.0 1354 3385.0
2 Rolling (Nos)
18 290 725 0 0.0 290 725.0
20 437 3240 8 60.0 445 3300.0
3 Fit up (Meters)
18 96 720 0 0.0 96 720.0

20 433 3247.5 8 60.0 441 3307.5


4 SAW Welding (Meters)
18 96 720 0 0.0 96 720.0

20 385 2887.5 6 45.0 391 2932.5


5 Radiography test (Meters)
18 96 720 0 0.0 96 720.0

20 372 2790 8 60.0 380 2850.0


6 Hydraulic test (Meters)
18 96 720 0 0.0 96 720.0

20 178 1335 4 30.0 182 1365.0


7 Copper slag Blasting
18 0 0 0 0.0 0 0.0

20 158 1185 0 0.0 158 1185.0


8 Epoxy coating (Meters)
18 0 0 0 0.0 0 0.0

20 151 1132.5 5 37.5 156 1170.0


9 Wrapping of welded mesh (Meters)
18 0 0 0 0.0 0 0.0

20 140 1050 6 45.0 146 1095.0


10 Guniting
18 0 0 0 0.0 0 0.0

20 132 990 0 0.0 132 990.0


11 Laying
18 0 0 0 0.0 0 0.0

DAILY PROGRESS REPORT ON LAYING SITE DATE :13-02-2021


MS PIPELINE LAYING DETAILS
CHAINAGE IN MTRS LAYING DETAILS ( IN NOS)
SL.NO CONTRACTOR NAME TOTAL MTRS AS ON REMARKS
FROM TO TODAY TOTAL
YESTRDAY
1 UBEN PROJECTS 585 952.5 367.5 49 0 49 Work in Progress
2 MAHENDRA REDDY KOKU 1300 1577.5 277.5 37 0 37 Work in Progress
3 JITEESH INFRASTRUCTURE 2300 2315 15 2 0 2 Work in Progress
4 BEM ENTERPRISES 4830 4935 105 14 0 14 Work in Progress
5 RGN ENTERPRISES 5800 6025 225 30 0 30 Work in Progress

TOTAL 990 132 0 132