You are on page 1of 2

Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Haro

DAILY PROGRESS REPORT DATE:29.10.2020


MS PIPELINE WORKS

Sl No Description Previous Day Present Day


1 Edge cutting (Nos) 118.0 18.00

2 Rolling (Nos) 108.0 14.00

3 Fit up (Meters) 247.5 22.50

4 SAW Welding (Meters) 187.5 37.50

5 Radiography test (Meters) 0.0 0.00

6 Hydraulic test (Meters) 0.0 0.00

7 Epoxy coating (Meters) 0.0 0.00

8 Wrapping of welded mesh (Meters) 0.0 0.00

9 Guniting (Meters) 0.0 0.00

CIVIL WORKS

NAME OF THE STRUCTURE WORK PROGRESS STATUS

MANPOWER

Name of Contractor Supervisor Fitter Welder Cutter Grinders

1
SPML 6 3 3 7 4
2

3
er transmission main from Harohalli to Vajarahalli.
DATE:29.10.2020

Present Day Cummulative Quantity Nos


18.00 136.00 136.00

14.00 122.00 122.00

22.50 270.00 36.00

37.50 225.00 30.00

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

NAME OF THE CONTRACTOR REMARKS

Riggers Operators Helpers Total

5 3 6 37