Professional Documents
Culture Documents
DISCREPATION Basic Salary Social Security Contributions & Over time cost Sum of totaa labor cost per day
Item no
Pay Per Holly Day Sick Leave Annual Leave Over time Total Monthly
types of labor Total Daily Expense
Monthly Expense
0% 0% 0% 0%
1 Surveyor 6000 0 0 0 0 6000.00 250.00
2 Site Engineer 6500 0 0 0 0 6500.00 270.83
3 Project Manager 6800 0 0 0 0 6800.00 283.33
4 Accountant 6500 0 0 0 0 6500.00 270.83
5 Foreman 6000 0 0 0 0 6000.00 250.00
6 Daily Labor 4800 0 0 0 0 4800.00 200.00
7 cobble stone paver 8400 0 0 0 0 8400.00 350.00
8 Mason 7200 0 0 0 0 7200.00 300.00
9 Compactor operator 4800 0 0 0 0 4800.00 200.00
10 Loader operator 7200 0 0 0 0 7200.00 300.00
12 Grader operator 8400 0 0 0 0 8400.00 350.00
13 Truck Driver 7200 0 0 0 0 7200.00 300.00
14 Grease Boy 4800 0 0 0 0 4800.00 200.00
15 Plasterer 7200 0 0 0 0 7200.00 300.00
16 mixer operator 4800 0 0 0 0 4800.00 200.00
17 Carpenter 7200 0 0 0 0 7200.00 300.00
20 vibrator operator 4800 0 0 0 0 4800.00 200.00
red ash m3 Adama 185.56 285.71 1.000 285.71 1.00 1.00 0.01 1.86 475.13
Cobblestone Pcs Modjo 1.20 250.80 0.003 0.71 0.00 0.00 0.20 0.24 2.15
Curb Stone Pcs Modjo 7.80 250.80 0.010 2.50 0.00 0.00 0.10 0.78 11.08
Aggregate ( 00 ) m3 Chiro 600.00 3.00 27.000 81.00 0.00 0.00 0.02 12.00 693.00
Cement Qts Chiro 580.00 1.00 10.000 10.00 5.00 5.00 0.01 6.96 606.96
Sand m3 Mieso 208.33 26.00 4.808 125.00 0.00 0.00 0.00 0.00 333.33
Aggregate ( 02 ) m3 Chiro 600.00 3.00 47.619 142.86 0.00 0.00 0.00 0.00 742.86
Masonary stone m3 Mieso 375.00 26.00 9.615 250.00 0.00 0.00 0.00 0.00 625.00
Form work pcs Chiro 280.00 1.00 5.000 5.00 1.00 1.00 0.00 0.00 287.00
Nails 7-12cm Kgs Chiro 56.00 1.00 0.400 0.40 0.20 0.20 0.00 0.00 56.80
Dia 10-12 mm Eucalyptus wood ml Chiro 20.00 1.00 0.833 0.83 0.63 0.63 0.00 0.00 22.08
Water m3 Chiro 30.00 0.10 50.000 0.00 0.00 0.00 0.00 0.00 30.00
2 Plate compactor 1.00 Jenoil Koria 105kg Used Owned Lease Rental Chiro town 500
3 Roller Compactor 1.00 CB15 8Ton Used Owned Lease Rental Chiro town 2800
4 Vibrator 1.00 Saravana 2hp Used Owned Lease Rental Chiro town 350
5 Dump Truck 2.00 Sinotruck 16m3 Used Owned Lease Rental Chiro town 4800
6 Loader 1.00 Dosan 130HP Used Owned Lease Rental Chiro town 1000
7 concrete mixer 1.00 Lombardini 250lit. Used Owned Lease Rental Chiro town 1000
8 Grader 1.00 140H (caterpilar) 125-500HP Used Owned Lease Rental Chiro town 12000
9 Water Truck(Shower Truck) 1.00 Sinotruck 16m3 Used Owned Lease Rental Chiro town 4800
10 Hand Tools Based On Work Based On Work Based On Work Used Owned Lease Rental Chiro town 15
Contract
over head cost
Man power Equipment Amount to be
contract amount WORK ITEM Material Expenses and Other Related profit cost
Expenses Expenses Executed
Expenses
before VAT
Before VAT 100% Setting out 0 1,800.00 3,380.00 1,970.13 4,916.94 12,313.34
3,319,176.41100% site clearance work 0 4,166.68 43,940.00 16,018.50 33,988.11 100,115.60
With VAT 100% cart away work 0 7,378.05 81,120.00 31,839.06 74,677.13 198,994.12
3,817,052.87100% compaction of sub grade 1600 14,074.92 75,114.00 20,472.61 14,133.21 475,770.93
20% formwork 22,028.72 11,199.60 1,652.15 8,811.49 10,278.40 55,071.79
20% C-25 Concrete Curb work 34,094.00 18,480.00 2,640.00 5,455.04 4,317.08 34,094.00
20% curb stone work 79,200.00 6,160.00 6,720.00 22,292.72 22,170.21 139,329.52
20% base course, red ash 23,468.56 6,373.00 1,600.00 6,219.90 435.43 38,874.38
20% base course, fine crushed
25,974.79 6,373.00 1,600.00 4,807.30 36,979.20
aggregate (00mm) -2,515.48
20% cobble stone paving 147,339.00 21,062.96 1,600.00 30,502.29 29,436.11 234,633.02
Contract
Man power Equipment Amount to be
contract amount WORK ITEM Material Expenses over head cost profit cost
Expenses Expenses Executed
before VAT
Contract
Man power Equipment Amount to be
contract amount WORK ITEM Material Expenses over head cost profit cost
Expenses Expenses Executed
before VAT
Before VAT 40% formwork 44,057.43 22,399.20 3,304.31 17,622.97 10,278.40 110,143.59
40% C-25 Concrete Curb work 36,960.00 5,280.00 5,040.00 10,910.08 4,317.08
3,319,176.41 68,188.01
With VAT 40% curb stone work 158,400.00 12,320.00 13,440.00 44,585.45 22,170.21 278,659.04
3,817,052.8740% base course, red ash 46,937.12 12,746.01 3,200.00 12,439.80 435.43 77,748.77
CONTRACTOR:-OLBANE GENERAL CONSTRUCTION PLC Direct cost Indirect cost Tax Duties
1. Setting out
1.1
Fix center line of the road by putting pegs at 20m interval including setting of horizontal and vertical curves. Set out also cross-section of the road at 20m intervals or less as ml 338.00 36.43 12,313.34 1,800.00 3,380.00 738.80 1,231.33 4,916.94 1,847.00 246.27
convenient, if terrain is very ragged, by placing pegs on center, two sides and drainage lines of the road as well as following design patterns of the cobble stone.
excavate the top 20-25 cm top soil to remove the soil with grass and organic layer of the soil which is very weak, compressible and not required for road construction. The
2.1 m2 3,380.00 29.62 100,115.60 4,166.68 43,940.00 6,006.94 10,011.56 33,988.11 15,017.34 2,002.31
excavated material will be deposited at a place directed by the engineer.
2.2 cart away surplus excavated material deposited 1km away from the site. m3 676.00 294.37 198,994.12 7,378.05 81,120.00 11,939.65 19,899.41 74,677.13 29,849.12 3,979.88
3.1 compaction of sub grade to the required density by sprinkling water over it as directed by the engineer m2 2,889.00 44.29 127,953.81 1,600.00 14,074.92 75,114.00 7,677.23 12,795.38 14,133.21 19,193.07 2,559.08
4.1 supply, spread to level and compact 10cm base course, red ash from quarry site, keeping the design slope so as to enable cobble stone paving following the slope. m2 2,889.00 67.28 194,371.92 117,342.80 31,865.02 8,000.00 11,662.32 19,437.19 2,177.15 29,155.79 3,887.44
4.2
supply, spread to level and compact 5-7cm base course, fine crushed aggregate (00mm) from stone crusher site, keeping the design slope so as to enable cobble stone paving m2 2,889.00 64.00 184,896.00 129,873.97 31,865.02 8,000.00 11,093.76 12,942.72 (12,577.39) 27,734.40 3,697.92
following the slope
c. Cobble Stone Paving and Filling Voids by Crushed Aggregate - - - - -
5.1
Supply and lay out to the required level 10*10*10 cm shaped cobblestones made of hard rock as per the layout, design and slope for the main body of the road and 15*10*10cm m2 2,889.00 406.08 1,173,165.12 736,695.00 105,314.82 8,000.00 70,389.91 82,121.56 147,180.53 175,974.77 23,463.30
shaped edge cobblestones following the design pattern of the cobblestones road pavement.
Supply, Fill and Compact the 10mm spaces or voids between the cobblestones with fine crushed aggregate to prevent the movement of the stones due to traffic and make the
6.1 m2 2,889.00 64.00 184,896.00 129,873.97 31,865.02 13,400.00 11,093.76 18,489.60 (23,524.27) 27,734.40 3,697.92
pavement stiff. The surface should be cleaned afterwards. This work depend on the guidance of the site Engineer.
supply and fix 15*45cm shaped cobblestones, 30m interval ,place between pavement and sidewalk (ditch). Along both side of the road with cement mortar base of 1:4 mix and
7.1 m3 220.00 3,166.58 696,647.60 396,000.00 30,800.00 33,600.00 41,798.86 69,664.76 110,851.03 104,497.14 13,932.95
backed with C-15 concrete 5cm thick on the external sides of the road. for support, as shown in the design and fill joint with cement mortar of 1:4 mix
7.2 C-25 Concrete mixing ratio 1:2:3 m3 42.00 4,058.81 170,470.02 92,400.00 13,200.00 12,600.00 10,228.20 17,047.00 21,585.42 25,570.50 3,409.40
7.3 form work for cobel concrete m2 559.98 491.73 275,358.97 110,143.59 55,998.00 8,260.77 16,521.54 27,535.90 51,392.00 41,303.84 5,507.18
Total 3,319,182.50 1,713,929.33 328,327.53 295,414.77 199,150.95 291,176.42 424,799.86 497,877.37 66,383.65
Project Owner Chiro Town Municipality 29 Nov 2021 6 Dec 2021 13 Dec 2021 20 Dec 2021 27 Dec 2021 3 Jan 2022 10 Jan 2022
29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
c Agreement and Advance payment process b Tue 12/07/21 Wed 12/08/21 2 100%
excavate the top 20-25 cm top soil to remove the soil with grass and organic layer of the soil which is very weak, compressible and not
2.1 m2 3,380.00 29.62 100,115.60 3.02 3.39 1.10 Mon 12/13/21 Tue 12/14/21 2 100%
required for road construction. The excavated material will be deposited at a place directed by the engineer.
2.2 cart away surplus excavated material deposited 1km away from the site. m3 676.00 294.37 198,994.12 6.00 9.38 2.10 Tue 12/14/21 Thu 12/16/21 3 100%
3.1 compaction of sub grade to the required density by sprinkling water over it as directed by the engineer m2 2,889.00 44.29 127,953.81 3.85 13.24 2.20 Thu 12/16/21 Thu 12/16/21 1 100%
supply, spread to level and compact 10cm base course, red ash from quarry site, keeping the design slope so as to enable cobble stone
4.1 m2 2,889.00 67.28 194,371.92 5.86 19.09 7.20 Tue 12/28/21 Mon 1/10/22 14 100%
paving following the slope.
supply, spread to level and compact 5-7cm base course, fine crushed aggregate (00mm) from stone crusher site, keeping the design
4.2 m2 2,889.00 64.00 184,896.00 5.57 24.66 4.10 Fri 12/31/21 Sun 1/16/22 17 100%
slope so as to enable cobble stone paving following the slope
c. Cobble Stone Paving and Filling Voids by Crushed Aggregate -
Supply and lay out to the required level 10*10*10 cm shaped cobblestones made of hard rock as per the layout, design and slope for the
5.1 m2 2,889.00 406.08 1,173,165.12 35.35 60.01 4.20 Fri 12/31/21 Sun 1/16/22 17 100%
main body of the road and 15*10*10cm shaped edge cobblestones following the design pattern of the cobblestones road pavement.
6. Filling Voids by Crushed Fine Aggregate and Finishing -
Supply, Fill and Compact the 10mm spaces or voids between the cobblestones with fine crushed aggregate to prevent the movement of
6.1 the stones due to traffic and make the pavement stiff. The surface should be cleaned afterwards. This work depend on the guidance of m2 2,889.00 64.00 184,896.00 5.57 65.58 5.10 Fri 12/31/21 Sun 1/16/22 17 100%
supply and fix 15*45cm shaped cobblestones, 30m interval ,place between pavement and sidewalk (ditch). Along both side of the road
7.1 with cement mortar base of 1:4 mix and backed with C-15 concrete 5cm thick on the external sides of the road. for support, as shown in m3 220.00 3,166.58 696,647.60 20.99 86.57 3.10 Fri 12/17/21 Sat 1/01/22 16 100%
the design and fill joint with cement mortar of 1:4 mix
7.2 C-25 Concrete mixing ratio 1:2:3 m3 42.00 4,058.81 170,470.02 5.14 91.70 7.30 Thu 12/23/21 Tue 12/28/21 6 100%
7.3 form work for cobble concrete m2 559.98 491.73 275,358.97 8.30 100.00 7.10 Mon 12/20/21 Mon 12/27/21 8 100%
The whole project 3,319,176.41 100 100 Thu 12/02/21 Sun 1/16/22 45 100%
Roller compactor
Plate Compactor
Backhoe Loader
dump track
Vibrator
Loader
Grader
Mixer
TASK DESCRIPTION PREDECESSOR START END DAYS
ITEM
No
supply, spread to level and compact 5-7cm base course, fine crushed aggregate (00mm) from stone
4.2 4.10 Fri 12/31/21 Sun 1/16/22 17 1
crusher site, keeping the design slope so as to enable cobble stone paving following the slope
Supply and lay out to the required level 10*10*10 cm shaped cobblestones made of hard rock as
5.1 per the layout, design and slope for the main body of the road and 15*10*10cm shaped edge 4.20 Fri 12/31/21 Sun 1/16/22 17 1
cobblestones following the design pattern of the cobblestones road pavement.
Supply, Fill and Compact the 10mm spaces or voids between the cobblestones with fine crushed
6.1 aggregate to prevent the movement of the stones due to traffic and make the pavement stiff. The 5.10 Fri 12/31/21 Sun 1/16/22 17 1
surface should be cleaned afterwards. This work depend on the guidance of the site Engineer.
7.3 form work for cobble concrete 7.10 Mon 12/20/21 Mon 12/27/21 8
Compactor operator
Project Owner Chiro Town Municipality
Vibrator operator
Project Manager
Loader operator
Grader operator
Mixer Operator
Site Engineer
Truck Driver
cobble stone paver
Accountant
Daily Labor
Carpenter
Surveyor
Forman
Mason
ITEM
TASK DESCRIPTION PREDECESSOR START END DAYS
No
excavate the top 20-25 cm top soil to remove the soil with grass
and organic layer of the soil which is very weak, compressible
2.1 1.10 Mon 12/13/21 Tue 12/14/21 2 1 1 1 1 2 1
and not required for road construction. The excavated material
will be deposited at a place directed by the engineer.
Supply, Fill and Compact the 10mm spaces or voids between the
cobblestones with fine crushed aggregate to prevent the
6.1 movement of the stones due to traffic and make the pavement 5.10 Fri 12/31/21 Sun 1/16/22 17 1 1 1 2 10 1
stiff. The surface should be cleaned afterwards. This work
depend on the guidance of the site Engineer.
2 2 3
* * * * * * *
* * * * * *
* *
* * *
* * *
* * *
Gantt Chart Template Pro
The following link is a blog post that talks specifically about the
Pro version for Excel Online.
Simple Color-Coding
The Pro version includes a column for specifying the color of bars in the chart. For example,
you could change the color based on urgency or task lead.
Be sure to read the Getting Started Tips below. Watching the video demos for Gantt Chart Template
Pro may also help you see how to use the spreadsheet.
Please read the license agreement in the TermsOfUse worksheet to learn how you may or may not
use and share this spreadsheet.
• [Bracketed Text] is meant to be edited, like the project title and task descriptions.
• Some of the labels include cell comments to provide extra information.
• To adjust the range of dates shown in the Gantt chart, change the Display Week number.
• The Project Start Date is used to define the first week shown in the gantt chart.
• Insert new tasks using one of the methods listed below.
• Define the task start date and duration (days) by editing the light green cells.
• If you see "#####" in a cell, widen the column to display the cell contents.
• Backup your file regularly to avoid losing data! Excel files get corrupted occasionally.
METHOD 1 (recommended)
• Insert a new blank row by right-clicking on the row number and selecting Insert.
• With the new blank row selected, press Ctrl+d to copy the formulas and formatting down from the row
above OR use the row drag handle to copy the formulas and formatting down.
METHOD 2
• Copy a row from the set of template rows at the bottom of the worksheet.
• Right-click on the row where you want to insert the new task and select Insert Copied Cells.
Method 2 will work, but Excel will split/fracture/duplicate conditional formatting rules rather than
merging the rules. This can cause inefficiencies in very large and heavily modified files.
Help improve Excel by voting on a suggestion to fix this problem.
Using the Template Rows and Choosing a WBS Level
The set of template rows at the bottom of the Gantt Chart worksheet provide examples of different
ways to format and define tasks for different WBS levels.
Each different WBS level uses a different formula in the WBS column.
You can either copy/paste/insert these template rows via Method 2 as explained above, OR you can
just copy/paste the desired WBS cell when you want to change the WBS level.
If you leave a blank cell above a WBS number, the numbering will reset to 1.x.x. The formulas are
meant for convenience, but you can manually enter the WBS numbers if you want to.
You can indent the task description for sub-tasks by entering leading spaces or using the Indent
feature in Excel.
FAQs
Q: How do I enter the Work Days instead of Calendar Days?
Entering work days instead of calendar days is a feature of the Pro version. There is nothing in the free
version preventing you from entering your own formulas, though.
Q: How do I calculate Calendar Days after entering the Start and End Dates?
You can calculate the duration in calendar days (including both start and end dates) using the formula
=enddate-startdate+1
Q: How do I create a summary row that shows the MIN and MAX dates for all sub-tasks?
In the Start column, use the formula =MIN(range_of_start_dates)
In the End column, use the formula =MAX(range_of_end_dates)
In the Days column, use the formula =end_date-start_date+1
Example: Let's say you have 3 sub tasks that are 10 days, 12 days, and 14 days long, respectively. If
the first subtask is 50% complete and the others are 25% complete, you could calculate the overall
percent complete for the group as: =(10*50%+12*25%+14*25%)/(10+12+14).
Input Cell
Terms of Use
Gantt Chart Template, by Vertex42.com
https://www.vertex42.com/ExcelTemplates/excel-gantt-chart.html
You may download the spreadsheet template, make archival copies, and customize
the template only for your personal use or use within your company or
organization and not for resale or public sharing.
You may not remove or alter any Vertex42 logo, trademark, copyright, disclaimer,
brand, terms of use, attribution, or other proprietary notices or marks within the
template.
The template and any file, document, or other work including or derived from the
template may NOT be sold, distributed, published to an online gallery, hosted on a
website, or placed on any server in a way that makes it available to the general
public.
Limited Private Sharing and Other Allowed Uses: See the complete license
agreement to learn more about how you may or may not use this template.