Professional Documents
Culture Documents
Section V:
Part II (b): Conditions of Particular Application -
OPRC
The following Particular Conditions shall supplement the GC. They are to be completed by the
Employer and presented as part of the Bidding Documents. Whenever there is a conflict, the
provisions here in shall prevail over those in the GC.
Reference
Amendments of, and Supplements to, Clauses in the General Conditions (GC) of
Number of
Contract.
GC Clause
1. The site is the area: is along Addis – Chancho – Gohatsion – D/Markos – Metema
trunk road which starts at Fiche and ends at Gohatsion with total length of 75 km.
6.1.2 The Appointing Authority is: The Director General, Ethiopian Roads Authority.
6.2.3 Arbitration Proceedings for the Contracts with Contractors: All disputes arising in
connection with the present Contract shall be finally settled under the Rules of
Conciliation and Arbitration of the International Chamber of Commerce by one or
more Arbitrators appointed in accordance with said Rules.
10.1 The Start Date shall not be later than 56 days after the issuance of the Letter of
Acceptance by the Employer.
The Contractor shall carry out the Works and Services (including associated
purchases and/or subcontracting) necessary to comply with the requirements
established in the Specifications with due care and diligence in accordance with the
Contract.
11.5 Replace the Sub-Clause 11.5 with the following:
“Any Plant, Material and Services that will be incorporated in or be required for the
Works and Services and other supplies shall have their origin in an eligible Country
as defined under the FDRE procurement guidelines.”
12.1 The Contractor may subcontract the following activities: such as provision of
Labor, Minor Repair and dressing of shoulders with prior consent of the Project
Manager.
The Contractor may subcontract under his own responsibility and without prior
12.2
approval of the Employer the following Works and Services provided they do not
represent more than Twenty five (25) percentage of the Contract price: Such as
Vegetation and scrub control, Drain cleaning and construction, Grading of unpaved
surfaces and other items mentioned in specifications.
14.4 Nothing set forth in this clause, shall be deemed as relieving Contractor of any of
its obligations, including but not limited to completing all the applicable Works and
Services in a timely manner.
14.2 The Employer shall give full possession of and access to the Site not later than 56
days from the date of issue of Letter of Acceptance subject to the condition that
the date of handing over of possession of shall be the same as that of Start date.
26.1 Replace only the first paragraph of the Sub-Clause 26.1 with the following;
“The Contractor shall, throughout the execution and completion of the Works and
Services, and the remedying of any defects therein:”
32.1 The Employer’s risks specified in the GC are amended as follows:
(a) insofar as they directly affect the execution of the Works in the country
Bidding Document , Section V – Part II (b): Conditions of Particular Application - OPRC
OPRC Work: Fiche- Gohatsion Road (Km 102+700 to Km 177+700) Ethiopian Roads Authority V-4
35.1 The Contractor shall take out and maintain in effect the following insurances in the
sums and deductibles shown below:
(a) Loss of or damage to the plant and machinery - 10% of Contract price.
(b) Third party insurance – ETB 1 Million per occurrence with number of
occurrences unlimited.
(c) Worker’s compensation and other insurance - As per statutory requirement
35.7 Add new sub-clause the following:
“There shall be no obligation for the insurances in sub-clause 35.1 to include loss or
damage caused by the risks listed under Sub-Clause 32.1 subparagraphs (a) (i) to
(iv) of the Particular Conditions.”
executed.”
41.2 Delete the first paragraph of this sub-clause and replace it with the following:
“The Defect Liability Period shall be Twelve (12) months from the date of issue of
Certificate for Completion of all the Works."
42.1 The aggregate liability of the Contractor to the Employer, excluding payment
reductions defined in GC 47.1, shall not exceed the amount of 10% of Contract price.
44.1 The payment of the Contract Price will be made in the following currencies:
Ethiopian Birr.
45.1 The Advance Payment will be equivalent to 20(twenty) percept of the contract
price less day works and contingency and will be paid in Ethiopian Birr. It will be
paid to the Contractor no later than 30(thirty) days of signature of the contract.
Conditional advance payment guarantee is allowed for Local Contractor.
45.3 Advance repayment shall start in the next monthly certificate after the certified
value of Works (excluding the advance payment) exceeds 20% of Contract price.
The deduction rate shall be 30% of the total value of interim payment.
46.1 Replace the last sentence of this Sub-Clause 46.1 with the following;
“The Bill of Quantities for Works shall include, where applicable, the lump-sum
price for Maintenance Works and rates for Day works for Emergency Works.”
Should the Contractor not attend, or neglect or omit to send such representative,
then the measurement made by the Project Manager or approved by him shall be
taken to be the correct measurement of such part of the Works. For the purpose
of measuring such Permanent Works as are to be measured by records and
drawings, the Project Manager shall prepare records and drawings as the work
proceeds and the Contractor, as and when called upon to do so in writing, shall,
within 14 days, attend to examine and agree such records and drawings with the
Project Manager and shall sign the same when so agreed. If the Contractor does
not attend to examine and agree such records and drawings, they shall be taken to
be correct. If, after examination of such records and drawings, the Contractor does
not agree the same or does not sign the same as agreed, they shall nevertheless be
taken to be correct, unless the Contractor, within 14 days of such examination,
lodges with the Project Manager notice of the respects in which such records and
drawings are claimed by him to be incorrect. On receipt of such notice, the Project
Manager shall review the records and drawings and either confirm or vary them.
Price adjustment: -
48.
1) Emergency Works: - Price Adjustment not applicable.
2) Price adjustment formulae for Maintenance works
50.1. Replace “within twenty eight (28) days” by “within forty two (42) days”.
Bidding Document , Section V – Part II (b): Conditions of Particular Application - OPRC
OPRC Work: Fiche- Gohatsion Road (Km 102+700 to Km 177+700) Ethiopian Roads Authority V-8
50.2 Delete the entire content of this Sub-clause and replace it with the following:
“If an amount certified is increased in a later certificate or as a result of an award
by the Dispute Review Expert (DRE) or Arbitrator, the Contractor shall not be paid
interest upon the delayed payment as set out in this Clause.”
53.2.1 The amount of the Advance payment security is the equivalent to the advance
payment amount.
53.3.2 The form of guarantee is Unconditional Bank Guarantee for foreign Contractors
and Conditional Bank Guarantee /Insurance Bond for local Contractors as set forth
in Procurement Directive by Federal Democratic Republic of Ethiopia.
59.2.2(c) The condition of persistent failure to execute the Contract fulfilled if and when the
total amount of payment reductions and liquidated damages applied under the
61 Replace Clause 61: “Use of Provisional Sum for Emergency Works” with Clause 61:
Use of Days Works items for Emergency Works”
62 Delete the entire Sub-Clause 62 including the heading and replace with the
following:
Clause 62: Use of Days Works items for Contingencies
The use of the Day Works items to cover for Contingencies will be done under the
control and initiative of the Project Manager in accordance with the conditions of
the Contract
63.1.1 The Employer has the right to propose a change in or from the assignments to the
Contractor as per Contract: Yes