DISCREPATION Basic Salary Social Security Contributions & Over time cost Sum of totaa labor cost per day
Item no
Pay Per Holly Day Sick Leave Annual Leave Over time Total Monthly
types of labor Total Daily Expense
Monthly Expense
0% 0% 0% 0%
1 Surveyor 6000 0 0 0 0 6000.00 250.00
2 Site Engineer 6500 0 0 0 0 6500.00 270.83
3 Project Manager 6800 0 0 0 0 6800.00 283.33
4 Accountant 6500 0 0 0 0 6500.00 270.83
5 Foreman 6000 0 0 0 0 6000.00 250.00
6 Daily Labor 4800 0 0 0 0 4800.00 200.00
7 cobble stone paver 8400 0 0 0 0 8400.00 350.00
8 Mason 7200 0 0 0 0 7200.00 300.00
9 Compactor operator 4800 0 0 0 0 4800.00 200.00
10 Loader operator 7200 0 0 0 0 7200.00 300.00
11 Backloader operator 7200 0 0 0 0 7200.00 300.00
12 Grader operator 8400 0 0 0 0 8400.00 350.00
13 Truck Driver 7200 0 0 0 0 7200.00 300.00
14 Grease Boy 4800 0 0 0 0 4800.00 200.00
15 Plasterer 7200 0 0 0 0 7200.00 300.00
16 mixer operator 4800 0 0 0 0 4800.00 200.00
17 Carpenter 7200 0 0 0 0 7200.00 300.00
18 Bar Bender I 7200 0 0 0 0 7200.00 300.00
19 Bar Bender II 4800 0 0 0 0 4800.00 200.00
20 vibrator operator 4800 0 0 0 0 4800.00 200.00
Selected borrowed fill material m3 Chiro 107.14 3.00 47.619 142.86 0.00 0.00 0.00 0.00 250.00
red ash m3 Adama 285.71 236.10 1.815 428.57 1.00 1.00 0.00 0.07 716.35
Cobblestone Pcs Modjo 1.20 250.80 0.003 0.71 0.00 0.00 0.20 0.24 2.15
Curb Stone Pcs Modjo 7.80 250.80 0.010 2.50 0.00 0.00 0.10 0.78 11.08
Aggregate ( 00 ) m3 Chiro 600.00 3.00 47.619 142.86 0.00 0.00 0.00 0.00 742.86
Cement Qts Chiro 580.00 1.00 10.000 10.00 5.00 5.00 0.01 6.96 606.96
Sand m3 Mieso 208.33 26.00 4.808 125.00 0.00 0.00 0.00 0.00 333.33
Aggregate ( 02 ) m3 Chiro 600.00 3.00 47.619 142.86 0.00 0.00 0.00 0.00 742.86
Masonary stone m3 Mieso 375.00 26.00 9.615 250.00 0.00 0.00 0.00 0.00 625.00
Basaltic stone (hard core) m3 Mieso 333.33 26.00 9.615 250.00 0.00 0.00 0.00 0.00 583.33
Form work pcs Chiro 280.00 1.00 5.000 5.00 1.00 1.00 0.00 0.00 287.00
dia 12mm Berga Chiro 960.00 1.00 12.000 12.00 3.00 3.00 0.00 0.00 978.00
dia 14mm Berga Chiro 1100.00 1.00 15.000 15.00 5.00 5.00 0.00 0.00 1,125.00
Nails 7-12cm Kgs Chiro 56.00 1.00 0.400 0.40 0.20 0.20 0.00 0.00 56.80
Dia 10-12 mm Eucalyptus wood ml Chiro 20.00 1.00 0.833 0.83 0.63 0.63 0.00 0.00 22.08
Water m3 Chiro 30.00 0.10 50.000 0.00 0.00 0.00 0.00 0.00 30.00
1 Backhoe loader 1.00 Cat 424b 92hp Used Owned Lease Rental Chiro town 8000
2 Plate compactor 1.00 Jenoil Koria 105kg Used Owned Lease Rental Chiro town 500
3 Roller Compactor 1.00 CB15 8Ton Used Owned Lease Rental Chiro town 2800
4 Vibrator 1.00 Saravana 2hp Used Owned Lease Rental Chiro town 350
5 Dump Truck 2.00 Sinotruck 16m3 Used Owned Lease Rental Chiro town 4800
6 concrete mixer 1.00 Lombardini 250lit. Used Owned Lease Rental Chiro town 1000
7 Grader 1.00 140H (caterpilar) 125-500HP Used Owned Lease Rental Chiro town 12000
9 Hand Tools 22.00 Based On Work Based On Work Used Owned Lease Rental Chiro town 15
Fix center line of the road by putting pegs at 20m interval including setting of
horizontal and vertical curves. Set out also cross-section of the road at 20cm
1.1 intervals or less as convenient, if terrain is very ragged, by placing pegs on ml 292 36.43 10,637.56 0 2,044.00 4,964.00 638.25 531.88 2,246.68 1,595.63 212.75
center, two sides and drainage lines of the road as well as following design
patterns of the cobble stone.
excavate the top 15-20cm top soil to remove the soil with grass and organic layer
of the soil which is very weak, compressible and not required for road
2.1 m2 3,580.7 29.62 106,061.07 0 17,903.65 71,600.00 6,363.66 5,303.05 2,769.48 15,909.16 2,121.22
construction. The excavated material will be deposited at a place directed by the
engineer.
trachytic semi dressed stone masonry bedded in cement mortar (1:3) mix price
2.2 shall include cement mortar bed not exceding 120cm (to be corrected by trench m3 142.11 237.00 33,678.89 0 7,105.50 15,632.10 2,020.73 1,683.94 6,563.03 5,051.83 673.58
excavation)
2.3 m3 510.00 380.31 193,958.10 127,500.00 16,830.00 10,200.00 11,637.49 9,697.91 14,213.55 29,093.72 3,879.16
backfill of selected material outside the site, if directed by the site engineer.
2.4 m3 858.25 294.37 252,643.05 0 12,873.75 71,517.97 15,158.58 12,632.15 135,407.73 37,896.46 5,052.86
cart away surplus excavated material deposited 1km away from the site.
compaction by hand of sub grade to the required density by sprinkling water
2.5 m2 10742.18 44.29 475,770.93 0 85,937.44 236,327.96 28,546.26 23,788.55 91,655.31 71,365.64 9,515.42
over it in every layer ( 3 layer)
25cm thick basaltic stone hardcore, consolidated and blinded with crushed stone
2.6 m2 2.00 218.91 437.82 291.66 40.00 2.80 26.27 21.89 46.44 65.67 8.76
supply, spread to level and compact 10cm base course, red ash from quarry site,
3.1 m2 3580.725 67.28 240,911.18 177,331.82 25,065.08 42,968.70 4,818.22 12,045.56 (26,136.43) 36,136.68 4,818.22
keeping the design slope so as to enable cobble stone paving following the slope.
supply, spread to level and compact 5-7cm base course, fine crushed aggregate
3.2 (00mm) from stone crusher site, keeping the design slope so as to enable cobble m2 3580.725 64.00 229,166.40 160,237.44 35,807.25 64,453.05 13,749.98 11,458.32 (61,122.98) 34,374.96 4,583.33
stone paving following the slope
Supply and lay out to the required level 10*10*10 cm shaped cobblestones made
of hard rock as per the layout, design and slope for the main body of the road
4.1 m2 3580.725 406.08 1,454,060.81 769,855.88 125,325.38 82,356.68 87,243.65 72,703.04 287,494.98 218,109.12 29,081.22
and 15*10*10cm shaped edge cobblestones following the design pattern of the
cobblestones road pavement.
5. CONCRETE WORK - - - - -
Project Owner Chiro Town Municipality 25 Oct 2021 1 Nov 2021 8 Nov 2021 15 Nov 2021 22 Nov 2021 29 Nov 2021 6 Dec 2021 13 Dec 2021 20 Dec 2021 27 Dec 2021
25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2
Ammount of Work
ITEM No TASK DESCRIPTION Unit Quantity Rate Amount Birr % Cummulative of work PREDECESSOR START END DAYS % DONE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
in percent(%)
c Agreement and Advance payment process b Sat 10/30/21 Sun 10/31/21 2 100%
1. Setting out
Fix center line of the road by putting pegs at 20m interval including setting of horizontal and
vertical curves. Set out also cross-section of the road at 20cm intervals or less as convenient, if
1.1 terrain is very ragged, by placing pegs on center, two sides and drainage lines of the road as
ml 292.00 36.43 10,637.56 0.22 0.22 d Tue 11/02/21 Wed 11/03/21 2 100%
well as following design patterns of the cobble stone.
excavate the top 15-20cm top soil to remove the soil with grass and organic layer of the soil
2.1 which is very weak, compressible and not required for road construction. The excavated m2 3,580.73 29.62 106,061.07 2.16 2.38 1.10 Thu 11/04/21 Fri 11/05/21 2 100%
material will be deposited at a place directed by the engineer.
trachytic semi dressed stone masonry bedded in cement mortar (1:3) mix price shall include
2.2 cement mortar bed not exceding 120cm (to be corrected by trench excavation)
m3 142.11 237.00 33,678.89 0.69 3.07 2.10 Sat 11/06/21 Sun 11/07/21 2 100%
2.3 m3 510.00 380.31 193,958.10 3.96 7.03 5.20 Sat 11/27/21 Wed 12/01/21 5 100%
backfill of selected material outside the site, if directed by the site engineer.
2.4 m3 858.25 294.37 252,643.05 5.16 12.18 2.20 Sun 11/07/21 Tue 11/09/21 3 100%
cart away surplus excavated material deposited 1km away from the site.
compaction by hand of sub grade to the required density by sprinkling water over it in every
2.5 layer ( 3 layer)
m2 10,742.18 44.29 475,770.93 9.71 21.89 7.10 Wed 12/01/21 Sun 12/05/21 5 100%
2.6 25cm thick basaltic stone hardcore, consolidated and blinded with crushed stone m2 2.00 218.91 437.82 0.01 21.90 6.10 Tue 11/16/21 Tue 11/16/21 1 100%
supply, spread to level and compact 10cm base course, red ash from quarry site, keeping the
3.1 design slope so as to enable cobble stone paving following the slope.
m2 3,580.73 67.28 240,911.18 4.92 26.81 2.50 Sat 12/04/21 Sat 12/18/21 15 100%
supply, spread to level and compact 5-7cm base course, fine crushed aggregate (00mm) from
3.2 stone crusher site, keeping the design slope so as to enable cobble stone paving following the m2 3,580.73 64.00 229,166.40 4.68 31.49 3.10 Thu 12/09/21 Tue 12/28/21 20 100%
slope
Supply and lay out to the required level 10*10*10 cm shaped cobblestones made of hard rock
4.1 as per the layout, design and slope for the main body of the road and 15*10*10cm shaped m2 3,580.73 406.08 1,454,060.81 29.67 61.16 3.20 Thu 12/09/21 Tue 12/28/21 20 100%
edge cobblestones following the design pattern of the cobblestones road pavement.
supply and fix 15*45cm shaped cobblestones, 30 to 50 cm long each, place between pavement
and sidewalk (ditch). Along both side of the road with cement mortar base of 1:4 mix and
5.1 backed with C-15 concrete for support, as shown in the design and fill joint with cement
ml 104.40 346.48 36,172.51 0.74 61.90 2.40 Tue 11/16/21 Tue 11/23/21 8 100%
mortar of 1:4 mix
5. CONCRETE WORK
5.2 Reinforced concrete quality C-20 a) b/n masonry and curb stone m3 326.55 3,703.52 1,209,384.46 24.68 87.18 5.40 Fri 11/12/21 Sat 11/27/21 16 100%
5.3 Reinforced concrete quality C-25 Slab culverts m3 1.00 4,058.81 4,058.81 0.08 87.27 5.60 Sun 11/21/21 Sun 11/21/21 1 100%
5.4 form work m2 656.30 562.41 369,109.68 7.53 94.80 4.10 Wed 11/10/21 Fri 11/19/21 10 100%
5.6 dia 12mm kg 62.94 103.08 6,487.55 0.13 94.93 5.70 Fri 11/19/21 Fri 11/19/21 1 100%
5.7 dia 14mm kg 84.48 111.91 9,454.03 0.19 95.12 5.40 Fri 11/19/21 Fri 11/19/21 1 100%
6. MASONRY WORK
7. FINISHING
7.1 Apply pointing to stone masonry foundation wall below ground level in mortar 1:3 m2 46.50 92.94 4,321.71 0.09 100.00 2.30 Wed 12/01/21 Wed 12/01/21 1 100%
The whole project 4,900,727.81 100.00 100.00 Mon 10/25/21 Tue 12/28/21 64 100%
Roller compactor
Plate Compactor
Backhoe Loader
dump track
Vibrator
Loader
Grader
Mixer
TASK DESCRIPTION PREDECESSOR START END DAYS
ITEM
No
a Contract Award - Mon 10/25/21 Fri 10/29/21 5
1. Setting out
Fix center line of the road by putting pegs at 20m interval including setting of horizontal and vertical curves. Set out also
1.1 cross-section of the road at 20cm intervals or less as convenient, if terrain is very ragged, by placing pegs on center, two d Tue 11/02/21 Wed 11/03/21 2
sides and drainage lines of the road as well as following design patterns of the cobble stone.
B. Excavation and Earth work
2. Top soil Excavation
excavate the top 15-20cm top soil to remove the soil with grass and organic layer of the soil which is very weak,
2.1 compressible and not required for road construction. The excavated material will be deposited at a place directed by the 1.1 Thu 11/04/21 Fri 11/05/21 2 1
engineer.
2.2
trachytic semi dressed stone masonry bedded in cement mortar (1:3) mix price shall include cement mortar bed not exceding 2.1 Sat 11/06/21 Sun 11/07/21 2 1
120cm (To be Corrected by Trench Excavation)
3.1
supply, spread to level and compact 10cm base course, red ash from quarry site, keeping the design slope so as to enable 2.5 Sat 12/04/21 Sat 12/18/21 15 1
cobble stone paving following the slope.
3.2
supply, spread to level and compact 5-7cm base course, fine crushed aggregate (00mm) from stone crusher site, keeping the 3.1 Thu 12/09/21 Tue 12/28/21 20 1
design slope so as to enable cobble stone paving following the slope
4. Cobble Stone Paving and Filling Voids by Crushed Aggregate
Supply and lay out to the required level 10*10*10 cm shaped cobblestones made of hard rock as per the layout, design and
4.1 slope for the main body of the road and 15*10*10cm shaped edge cobblestones following the design pattern of the 3.2 Thu 12/09/21 Tue 12/28/21 20 1
cobblestones road pavement.
5.Curb Stone Paving
supply and fix 15*45cm shaped cobblestones, 30 to 50 cm long each, place between pavement and sidewalk (ditch). Along
5.1 both side of the road with cement mortar base of 1:4 mix and backed with C-15 concrete for support, as shown in the design 2.4 Tue 11/16/21 Tue 11/23/21 8
and fill joint with cement mortar of 1:4 mix
5. CONCRETE WORK
5.1
C-5 lean concrete with minimum cement content of 150kg/m3 a) under 2.6 Tue 11/09/21 Fri 11/12/21 4 1
masonry Retaining wall and curb stone
5.2 Reinforced concrete quality C-20 a) b/n masonry and curb stone 5.4 Fri 11/12/21 Sat 11/27/21 16 1 1
5.3 Reinforced concrete quality C-25 Slab culverts 5.6 Sun 11/21/21 Sun 11/21/21 1 1 1
5.4 form work 4.1 Wed 11/10/21 Fri 11/19/21 10
5.6 dia 12mm 5.7 Fri 11/19/21 Fri 11/19/21 1
5.7 dia 14mm 5.4 Fri 11/19/21 Fri 11/19/21 1
6. MASONRY WORK
6.1 trachytic semi dressed stone masonry bedded in a)B.N.G.L 5.1 Thu 11/11/21 Mon 11/15/21 5
7. FINISHING
7.1 Apply pointing to stone masonry foundation wall below ground level in mortar 1:3 2.3 Wed 12/01/21 Wed 12/01/21 1
Name Mengstagegnew Mebrate
In the Capacity of General Manager
Signed----------------------------------------------------------------------
authorized to sign the bid for and on behalf of Olbane General Construction PLC
Dated on October 2021, Chiro, Oromia region
Karoora Humna Namaa Yeeroo fi Dhaabbii
Project: Cobble Stone Road Construction Man Power (Workmanship) Schedule
Backloader operator
Compactor operator
Project Owner Chiro Town Municipality
Vibrator operator
Loader operator
Grader operator
Mixer Operator
Site Engineer
Bar Bender II
Bar Bender I
Truck Driver
Grease Boy
Daily Labor
Carpenter
Surveyor
Plasterer
Forman
Mason
ITEM
TASK DESCRIPTION PREDECESSOR START END DAYS
No
1. Setting out
Fix center line of the road by putting pegs at 20m interval including setting of
horizontal and vertical curves. Set out also cross-section of the road at 20cm
1.1 intervals or less as convenient, if terrain is very ragged, by placing pegs on d Tue 11/02/21 Wed 11/03/21 2 1 1 2
center, two sides and drainage lines of the road as well as following design
patterns of the cobble stone.
B. Excavation and Earth work
2. Top soil Excavation
excavate the top 15-20cm top soil to remove the soil with grass and organic
layer of the soil which is very weak, compressible and not required for road
2.1 1.1 Thu 11/04/21 Fri 11/05/21 2 1 1 2 1
construction. The excavated material will be deposited at a place directed by
the engineer.
trachytic semi dressed stone masonry bedded in cement mortar (1:3) mix
2.2 2.1 Sat 11/06/21 Sun 11/07/21 2 1 2 5 1
price shall include cement mortar bed not exceding 120cm
2.3 5.2 Sat 11/27/21 Wed 12/01/21 5 2 10 1 1
backfill of selected material outside the site, if directed by the site engineer.
2.4 cart away surplus excavated material deposited 1km away from the site. 2.2 Sun 11/07/21 Tue 11/09/21 3 1 2 6 1 2
compaction by hand of sub grade to the required density by sprinkling water
2.5 7.1 Wed 12/01/21 Sun 12/05/21 5 1 2 6 1
over it in every layer ( 3 layer)
25cm thick basaltic stone hardcore, consolidated and blinded with crushed
2.6 6.1 Tue 11/16/21 Tue 11/16/21 1 1 1 1
stone
3. Lying of Fine Sand Aggregate Base Course
supply, spread to level and compact 10cm base course, red ash from quarry
3.1 site, keeping the design slope so as to enable cobble stone paving following 2.5 Sat 12/04/21 Sat 12/18/21 15 1 1 2 16 1
the slope.
supply, spread to level and compact 5-7cm base course, fine crushed
3.2 aggregate (00mm) from stone crusher site, keeping the design slope so as to 3.1 Thu 12/09/21 Tue 12/28/21 20 1 2 15 1
enable cobble stone paving following the slope
4. Cobble Stone Paving and Filling Voids by Crushed Aggregate
Supply and lay out to the required level 10*10*10 cm shaped cobblestones
made of hard rock as per the layout, design and slope for the main body of
4.1 3.2 Thu 12/09/21 Tue 12/28/21 20 1 2 16 6 1
the road and 15*10*10cm shaped edge cobblestones following the design
pattern of the cobblestones road pavement.
5.Curb Stone Paving
Project Start Date 10/25/2021 (Monday)
Backloader operator
Compactor operator
Project Owner Chiro Town Municipality
Vibrator operator
Loader operator
Grader operator
Mixer Operator
Site Engineer
Bar Bender II
Bar Bender I
Truck Driver
Grease Boy
Daily Labor
Carpenter
Surveyor
Plasterer
Forman
Mason
ITEM
TASK DESCRIPTION PREDECESSOR START END DAYS
No
2 2 3
* * * * * * *
* * * * * *
* *
* * *
* * *
* * *
Gantt Chart Template Pro
The following link is a blog post that talks specifically about the
Pro version for Excel Online.
Simple Color-Coding
The Pro version includes a column for specifying the color of bars in the chart. For example,
you could change the color based on urgency or task lead.
Be sure to read the Getting Started Tips below. Watching the video demos for Gantt Chart Template
Pro may also help you see how to use the spreadsheet.
Please read the license agreement in the TermsOfUse worksheet to learn how you may or may not
use and share this spreadsheet.
• [Bracketed Text] is meant to be edited, like the project title and task descriptions.
• Some of the labels include cell comments to provide extra information.
• To adjust the range of dates shown in the Gantt chart, change the Display Week number.
• The Project Start Date is used to define the first week shown in the gantt chart.
• Insert new tasks using one of the methods listed below.
• Define the task start date and duration (days) by editing the light green cells.
• If you see "#####" in a cell, widen the column to display the cell contents.
• Backup your file regularly to avoid losing data! Excel files get corrupted occasionally.
METHOD 1 (recommended)
• Insert a new blank row by right-clicking on the row number and selecting Insert.
• With the new blank row selected, press Ctrl+d to copy the formulas and formatting down from the row
above OR use the row drag handle to copy the formulas and formatting down.
METHOD 2
• Copy a row from the set of template rows at the bottom of the worksheet.
• Right-click on the row where you want to insert the new task and select Insert Copied Cells.
Method 2 will work, but Excel will split/fracture/duplicate conditional formatting rules rather than
merging the rules. This can cause inefficiencies in very large and heavily modified files.
Help improve Excel by voting on a suggestion to fix this problem.
Using the Template Rows and Choosing a WBS Level
The set of template rows at the bottom of the Gantt Chart worksheet provide examples of different
ways to format and define tasks for different WBS levels.
Each different WBS level uses a different formula in the WBS column.
You can either copy/paste/insert these template rows via Method 2 as explained above, OR you can
just copy/paste the desired WBS cell when you want to change the WBS level.
If you leave a blank cell above a WBS number, the numbering will reset to 1.x.x. The formulas are
meant for convenience, but you can manually enter the WBS numbers if you want to.
You can indent the task description for sub-tasks by entering leading spaces or using the Indent
feature in Excel.
FAQs
Q: How do I enter the Work Days instead of Calendar Days?
Entering work days instead of calendar days is a feature of the Pro version. There is nothing in the free
version preventing you from entering your own formulas, though.
Q: How do I calculate Calendar Days after entering the Start and End Dates?
You can calculate the duration in calendar days (including both start and end dates) using the formula
=enddate-startdate+1
Q: How do I create a summary row that shows the MIN and MAX dates for all sub-tasks?
In the Start column, use the formula =MIN(range_of_start_dates)
In the End column, use the formula =MAX(range_of_end_dates)
In the Days column, use the formula =end_date-start_date+1
Example: Let's say you have 3 sub tasks that are 10 days, 12 days, and 14 days long, respectively. If
the first subtask is 50% complete and the others are 25% complete, you could calculate the overall
percent complete for the group as: =(10*50%+12*25%+14*25%)/(10+12+14).
Input Cell
Terms of Use
Gantt Chart Template, by Vertex42.com
https://www.vertex42.com/ExcelTemplates/excel-gantt-chart.html
You may download the spreadsheet template, make archival copies, and customize
the template only for your personal use or use within your company or
organization and not for resale or public sharing.
You may not remove or alter any Vertex42 logo, trademark, copyright, disclaimer,
brand, terms of use, attribution, or other proprietary notices or marks within the
template.
The template and any file, document, or other work including or derived from the
template may NOT be sold, distributed, published to an online gallery, hosted on a
website, or placed on any server in a way that makes it available to the general
public.
Limited Private Sharing and Other Allowed Uses: See the complete license
agreement to learn more about how you may or may not use this template.