Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli to Vajarahalli.

DAILY PROGRESS REPORT ON FABRICATION YARD DATE :11-02-2021


MS PIPELINE WORKS
Previous Day Present Day Cumulative Quantity
Plate
Sl. No. Description
Thickness Numbers Meters Numbers Meters Numbers Meters

20 1328 3320 24 60.0 1352 3380.0


1 Edge cutting (Nos)
18 290 725 0 0.0 290 725.0
20 1282 3205 12 30.0 1294 3235.0
2 Rolling (Nos)
18 290 725 0 0.0 290 725.0
20 427 3165 2 15.0 429 3180.0
3 Fit up (Meters)
18 96 720 0 0.0 96 720.0

20 420 3150 5 37.5 425 3187.5


4 SAW Welding (Meters)
18 96 720 0 0.0 96 720.0

20 380 2850 5 37.5 385 2887.5


5 Radiography test (Meters)
18 96 720 0 0.0 96 720.0

20 365 2737.5 2 15.0 367 2752.5


6 Hydraulic test (Meters)
18 96 720 0 0.0 96 720.0

20 168 1260 5 37.5 173 1297.5


7 Copper slag Blasting
18 0 0 0 0.0 0 0.0

20 153 1147.5 0 0.0 153 1147.5


8 Epoxy coating (Meters)
18 0 0 0 0.0 0 0.0

20 151 1132.5 0 0.0 151 1132.5


9 Wrapping of welded mesh (Meters)
18 0 0 0 0.0 0 0.0

20 135 1012.5 5 37.5 140 1050.0


10 Guniting
18 0 0 0 0.0 0 0.0

20 121 907.5 6 45.0 127 952.5


11 Laying
18 0 0 0 0.0 0 0.0

DAILY PROGRESS REPORT ON LAYING SITE DATE :11-02-2021


MS PIPELINE LAYING DETAILS
CHAINAGE IN MTRS LAYING DETAILS ( IN NOS)
SL.NO CONTRACTOR NAME TOTAL MTRS AS ON REMARKS
FROM TO TODAY TOTAL
YESTRDAY
1 UBEN PROJECTS 585 952.5 367.5 49 0 49 Work in Progress
2 MAHENDRA REDDY KOKU 1300 1577.5 277.5 35 2 37 Work in Progress
3 BEM ENTERPRISES 4830 4920 90 10 2 12 Work in Progress
4 RGN ENTERPRISES 5800 6017.5 217.5 27 2 29 Work in Progress

TOTAL 952.5 121 6 127

SPML ONTB BWSSB