Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli to Vajarahalli.

DAILY PROGRESS REPORT ON FABRICATION YARD DATE :14-02-2021


MS PIPELINE WORKS
Previous Day Present Day Cumulative Quantity
Plate
Sl. No. Description
Thickness Numbers Meters Numbers Meters Numbers Meters

20 1405 3512.5 0 0.0 1405 3512.5


1 Edge cutting (Nos)
18 290 725 0 0.0 290 725.0
20 1354 3385 0 0.0 1354 3385.0
2 Rolling (Nos)
18 290 725 0 0.0 290 725.0
20 445 3300 2 15.0 447 3315.0
3 Fit up (Meters)
18 96 720 0 0.0 96 720.0

20 441 3307.5 3 22.5 444 3330.0


4 SAW Welding (Meters)
18 96 720 0 0.0 96 720.0

20 391 2932.5 0 0.0 391 2932.5


5 Radiography test (Meters)
18 96 720 0 0.0 96 720.0

20 380 2850 3 22.5 383 2872.5


6 Hydraulic test (Meters)
18 96 720 0 0.0 96 720.0

20 182 1365 3 22.5 185 1387.5


7 Copper slag Blasting
18 0 0 0 0.0 0 0.0

20 158 1185 10 75.0 168 1260.0


8 Epoxy coating (Meters)
18 0 0 0 0.0 0 0.0

20 156 1170 3 22.5 159 1192.5


9 Wrapping of welded mesh (Meters)
18 0 0 0 0.0 0 0.0

20 146 1095 3 22.5 149 1117.5


10 Guniting
18 0 0 0 0.0 0 0.0

20 132 990 3 22.5 135 1012.5


11 Laying
18 0 0 0 0.0 0 0.0

DAILY PROGRESS REPORT ON LAYING SITE DATE :14-02-2021


MS PIPELINE LAYING DETAILS
CHAINAGE IN MTRS LAYING DETAILS ( IN NOS)
SL.NO CONTRACTOR NAME TOTAL MTRS AS ON REMARKS
FROM TO TODAY TOTAL
YESTRDAY
1 UBEN PROJECTS 585 960 375 49 1 50 Work in Progress
2 MAHENDRA REDDY KOKU 1300 1577.5 277.5 37 0 37 Work in Progress
3 JITEESH INFRASTRUCTURE 2300 2322.5 22.5 2 1 3 Work in Progress
4 BEM ENTERPRISES 4830 4942.5 112.5 14 1 15 Work in Progress
5 RGN ENTERPRISES 5800 6025 225 30 0 30 Work in Progress

TOTAL 1012.5 132 3 135

SPML ONTB BWSSB