Defective Monthly Report

Month Aug-21
Qty Weight
N° Date Spec. Shift Ton/psc Defective Type Remark
(ea) (Ton)
1 12-Aug-21 D300-12m Crane's wire 1.411 1 1.411 Fall Down Crane's wire cut off

2 17-Aug-21 9mS B 0.600 1 0.600 Fracture Fracture

3 26-Aug-21 D300-10m G.Crane 1.176 1 1.176 Fall Down Gantry Crane

4 26-Aug-21 D300-12m A 1.411 1 1.411 Bending,Cracking Pc-bar head cut off

5 27-Aug-21 D300-12m A 1.411 1 1.411 Bending,Cracking Pc-bar head cut off

6 27-Aug-21 D300-12m B 1.411 1 1.411 Bending,Cracking Pc-bar head cut off

7 29-Aug-21 D350-9m B 1.278 1 1.278 Cracking Cracking

8 27-Aug-21 D300-12m A 1.411 1 1.411 Bending,Cracking Pc-bar head cut off

10

Total 8 10.109

Returning
Qty Weight
N° Date Spec. Div Ton/psc Site Remark
(ea) (Ton)
1 D300-7m 0.823 1 0.823
03-Aug-21 Meas sokunthea Phnom Penh Site Rejecting
2 D300-9m 0.710 1 0.710

3 10-Aug-21 D350-10m Kong Pheng 1.421 1 1.421 Phnom Penh Site Rejecting

Total 3 2.954

Grand Total 11 13.063

Prepared By Checked by F.D


PHC PILE Type D300 remain at SMART CITY SITE
Date 8/1/2021

The Good Pile Remain Qty


No Spec Qty Remark
1 D300-10m 44 With Shoe
2 D300-10m 40 No Shoe
3 D300-11m 9 No Shoe
4 D300-11m 4 With Shoe
5 D300-12m 2 No Shoe
6 D300-12m 4 With Shoe
Total 103
The Pile Rejecting Qty
No Spec Qty Remark
1 D300-9m 2 With Shoe
2 D300-10m 22 With Shoe
3 D300-11m 4 No Shoe
4 D300-11m 1 With Shoe
5 D300-12m 3 No Shoe
6 D300-12m 3 With Shoe
Total 35

The Points Need to Replace and repair Qty


No Spec Qty Remain Pile Length (m) Remark
1 D300-12m 1 9.5 2nd Pile
2 D300-10m 1 8 2nd Pile
3 D300-10m 1 6 2nd Pile
4 D300-10m 1 2 2nd Pile
Total 4
PHC PILE Type D300 remain at SMART CITY SITE
Date 9/25/2021

The Good Pile Remain Qty


No Spec Qty Remark
1 D300-10m 38 No Shoe
2 D300-10m 28 With Shoe
3 D300-11m 6 No Shoe
4 D300-11m 5 With Shoe
5 D300-12m 2 No Shoe
6 D300-12m 12 With Shoe
Total 91

The Points Need to Replace and repair Qty


No Spec Qty Remain Pile Length (m) Remark
1 D300-12m 1 9.5 2nd Pile
2 D300-10m 1 8 2nd Pile
3 D300-10m 1 6 2nd Pile
4 D300-10m 1 2 2nd Pile
Total 4

Returning From Smart City


No Returning Date Spec Qty Cracking Point Remark
1 D300-8m 1 1 Posible for Other Choice
2 D300-9m 1 2 Posible for Other Choice Grade C
3 D300-10m 1 1 Posible for Other Choice
4 D300-10m 1 2 Posible for Other Choice Grade C
5 D300-10m 1 1 Posible for Other Choice
6 D300-10m 1 4 Defective
9-Jun
7 D300-10m 1 4 Defective
8 D300-10m 1 1 Posible for Other Choice
9 D300-10m 1 1 Posible for Other Choice
10 D300-11m 1 7 Defective
11 D300-11m 1 goood Reject cause surface repaired
12 D300-12m 1 1 Posible for Other Choice
1 D300-10m 1 goood Posible for Other Choice
2 D300-10m 1 6 Defective
3 D300-10m 1 1 Posible for Other Choice
4 D300-10m 1 1 Posible for Other Choice
5 D300-10m 1 1 Posible for Other Choice
6 D300-10m 1 Cracking Middle big size of Cracking / Defective
7 D300-10m 1 2 big size of Cracking / Defective
8 D300-10m 1 1 Posible for Other Choice
6-Aug
9 D300-10m 1 1 Posible for Other Choice
10 D300-10m 1 5 Defective
11 D300-10m 1 1 Posible for Other Choice
12 D300-10m 1 good Posible for Other Choice
13 D300-12m 1 10 Defective
14 D300-12m 1 2 Posible for Other Choice Grade C
15 D300-12m 1 2 Posible for Other Choice Grade C
16 D300-12m 1 2 Posible for Other Choice Grade C
Total 28
PHC PILE Type D300 remain at SMART CITY SITE
Date 9/25/2021

The Points Need to Replace and repair Qty


No Spec Qty Remain Pile Length (m)

1 1 9.5

2 1 8

3 1 6

4 1 2
5 1

6 1

7 1

8 1

Total 4
CITY SITE

Remark 20 22

2nd Pile 10.5 12.5

2nd Pile 12 14

2nd Pile 14 16

2nd Pile
2nd Pile

2nd Pile

2nd Pile

2nd Pile
PHC PILE Type D300 For SMART CITY SITE

The Points Need to Replace and repair Qty


No Spec Total Pile Length Remain Pile Length (m) Install (m) Remark
1 20 5.6 14.4
2 20 7.4 12.6
3 20 6 14
4 20 2 18
D300
5 20 5.8 14.2
6 20 2.3 17.7
7 20 2 18
8 22 22 Replace
PHC PILE Type D300 remain at SMART CITY SITE
Date 10/2/2021

Returning From Smart City


No Returning Date Spec Qty Cracking Point Remark
1 D300-8m 1 1 Posible for Other Choice
2 D300-9m 1 2 Posible for Other Choice Grade C
3 D300-10m 1 1 Posible for Other Choice
4 D300-10m 1 2 Posible for Other Choice Grade C
5 D300-10m 1 1 Posible for Other Choice
6 D300-10m 1 4 Defective
9-Jun
7 D300-10m 1 4 Defective
8 D300-10m 1 1 Posible for Other Choice
9 D300-10m 1 1 Posible for Other Choice
10 D300-11m 1 7 Defective
11 D300-11m 1 goood Reject cause surface repaired
12 D300-12m 1 1 Posible for Other Choice
1 D300-10m 1 goood Posible for Other Choice
2 D300-10m 1 6 Defective
3 D300-10m 1 1 Posible for Other Choice
4 D300-10m 1 1 Posible for Other Choice
5 D300-10m 1 1 Posible for Other Choice
6 D300-10m 1 Cracking Middle big size of Cracking / Defective
7 D300-10m 1 2 big size of Cracking / Defective
8 D300-10m 1 1 Posible for Other Choice
6-Aug
9 D300-10m 1 1 Posible for Other Choice
10 D300-10m 1 5 Defective
11 D300-10m 1 1 Posible for Other Choice
12 D300-10m 1 good Posible for Other Choice
13 D300-12m 1 10 Defective
14 D300-12m 1 2 Posible for Other Choice Grade C
15 D300-12m 1 2 Posible for Other Choice Grade C
16 D300-12m 1 2 Posible for Other Choice Grade C
Total 28
Defective Monthly Report
Month Oct-21

Returning
Qty Weight
N° Date Spec. Div Ton/psc Site Remark
(ea) (Ton)

1 D300-10m 1.176 5 5.880

Smart City Smart City Engineer Rejecting


2 30-Sep-21 D300-11m 1.293 1 1.293 Smart City
Rejecting while installing found Crack

3 D300-12m 1.411 1 1.411

Total 7 8.584

Prepared By Checked by F.D


PHC PILE Type D300 Return From SMART CITY SITE
Date 10/26/2021

Returning From Smart City


No Returning Date Spec Qty Cracking Point Remark
1 D300-8m 1 1 Posible for Other Choice
2 D300-9m 1 2 Posible for Other Choice Grade C
3 D300-10m 1 1 Posible for Other Choice
4 D300-10m 1 2 Posible for Other Choice Grade C
5 D300-10m 1 1 Posible for Other Choice
6 D300-10m 1 4 Defective
9-Jun
7 D300-10m 1 4 Defective
8 D300-10m 1 1 Posible for Other Choice
9 D300-10m 1 1 Posible for Other Choice
10 D300-11m 1 7 Defective
11 D300-11m 1 goood Reject cause surface repaired
12 D300-12m 1 1 Posible for Other Choice
1 D300-10m 1 goood Posible for Other Choice
2 D300-10m 1 6 Defective
3 D300-10m 1 1 Posible for Other Choice
4 D300-10m 1 1 Posible for Other Choice
5 D300-10m 1 1 Posible for Other Choice
6 D300-10m 1 Cracking Middle big size of Cracking / Defective
7 D300-10m 1 2 big size of Cracking / Defective
8 D300-10m 1 1 Posible for Other Choice
6-Aug
9 D300-10m 1 1 Posible for Other Choice
10 D300-10m 1 5 Defective
11 D300-10m 1 1 Posible for Other Choice
12 D300-10m 1 good Posible for Other Choice
13 D300-12m 1 10 Defective
14 D300-12m 1 2 Posible for Other Choice Grade C
15 D300-12m 1 2 Posible for Other Choice Grade C
16 D300-12m 1 2 Posible for Other Choice Grade C
Total 28