MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
ROUGHING-IN WORKS
I. GENERAL REQUIREMENTS
1.1) Mobilization & Demobilization of workers & tools 1.00 lot 100,000.00
1.2) Temporary Site Enclosure 1.00 lot 60,000.00
1.3) Cleaning and Hauling of Construction Debris 1.00 lot 200,000.00
1.4) Renovations Permit & Licenses lot
1.5) Others
1.5.1) Supervision 1.00 lot 170,000.00
1.5.2) Electrical & Water Consumptions 1.00 lot 60,000.00
1.5.3) Others (Please specify) lot
sub-total
MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
b) Second Floor to Roof Beam kls
3.1.2) Steel Wide Flange Beam kls
a) Second Floor kls
W10 x 33lbs kls
W10 x 45lbs kls
W8 x 48lbs kls
W8 x 35lbs kls
W8 x 28lbs kls
W8 x 67lbs kls
W12 x 53lbs kls
W8 x 18lbs kls
W6 x 9lbs kls
b) Roof Framing kls
W8 x 21lbs kls
W8 x 28lbs kls
c) Steel Tubular Trelliss kls
d) Anchor Bolt, Base Plates & Stiffener Plates lots
e) 16mm thk. End Wall Plate, Use Hillti RE 500 lots
WITH 6 - M20 has Rods
3.2) Other Consummables & Accessories
3.2.1) Steel Decking lot
3.2.2) # 16 G.I Tie Wire lot
3.2.3) Consummables lot
3.2.4) Others (Pls. Specify) lot
sub-total
V. CONCRETE WORKS
5.1) Column Footing 6.10 cu.m.
5.2) Concrete Pedestal 1.68 cu.m.
5.3) Wall Footing 5.32 cu.m.
5.4) B.I. Pipe column to be filled with concrte cu.m.
5.5) Trench Drain cu.m.
5.6) Ground Water Reservoir cu.m.
5.7) Reinforce Concrete Stairs cu.m.
5.8) Slab (Ready Mix Concrete)
a) Ground Floor cu.m.
b) Second Floor cu.m.
c) Canopy Slab cu.m.
d) Concrete Ledge cu.m.
e) Carport / Driveway / Walkway cu.m.
f) Concrete Ledge cu.m.
5.9) Septic Tank cu.m.
5.10) Grease Trap cu.m.
5.11) Electrical Post cu.m.
5.12) Area Drain / Catch Basin cu.m.
5.13) Others (Pls. Specify)
sub-total
MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
100mm thk M2 Wall Panel 65.22 sq.m
6.1.2) Second Floor to Roof Beam
150mm thk M2 Wall Panel 53.03 sq.m
100mm thk M2 Wall Panel 44.98 sq.m
6.1.3) Area Drain / Catch Basin sq.m
6.1.4) Septic Tank sq.m
6.1.5) Others (Pls. Specify)
sub-total
6.2) Plastering
6.2.1) Ground Floor to Second Floor sq.m
6.2.2) Second Floor to Roof Beam sq.m
6.2.3) Area Drain / Catch Basin sq.m
6.2.4) Septic Tank sq.m
6.2.5) Others (Pls. Specify)
sub-total
MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
8.2) Cold and Hot Water Lines
a) PAP or XLPE(Multi Layered Pipes - by Unitec)
a.1) 50mm diameter 2.50 lm
a.2) 38mm diameter 3.50 lm
a.3) 31mm diameter 110.45 lm
a.4) 25mm diameter 48.00 lm
a.5) 18mm diameter 137.00 lm
a.6) 12mm diameter 69.50 lm
b) Gate Valve
b.1) 50mm diameter 2.00 pcs
b.2) 31mm diameter 9.00 pcs
b.3) 25mm diameter 1.00 pcs
b.4) 18mm diameter 30.00 pcs
b.5) 12mm diameter 5.00 pcs
c) Fittings
c.1) 31mm diameter pcs
c.2) 25mm diameter pcs
c.3) 18mm diameter pcs
c.4) 12mm diameter pcs
d) Hose Bibb with Gate Valve
d.1) 18mm diameter 17.00 pcs
e) Water Meter set
f) Tapping to Existing Water Lines 1.00 lot
g) Hangers and Supports 1.00 lot
8.3) Testing and Commissioning 1.00 lot
8.4) Others (Please Specify)
sub-total
MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
Labor & Materials
FINISHING WORKS
I ARCHITECTURAL WORKS
1.1) Painting Works
1.1.1) Wall
a) Ground Floor
a.1) Exterior Wall sq.m.
a.2) Interior Wall sq.m.
b) Second Floor
b.1) Exterior Wall sq.m.
b.2) Interior Wall sq.m.
1.1.2) Ceiling Works
a) Ground Floor sq.m.
b) Second Floor sq.m.
1.1.3) Door Jambs & Door (Varnish Finish) sets
1.1.4) Fascia Board lm
1.1.5) Windows & Door Openings sq.m.
1.1.6) Baseboard lm
1.1.7) Stair Railings lm
1.1.8) Steel Tubular Trellis lm
1.1.9) Concrete Ledge sq.m.
1.1.10) Sliding Gate & Pedestrian Gate lot
1.1.11) Others (Pls. Specify)
sub-total
MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
2.15) Refrigerator Outlet pcs
2.16) Freezer Outlet pc
2.17) Booster Pump pcs
2.18) Motorized Sliding Gate Supply pc
2.19) Smoke Detector Supply pcs
2.20) Telephone / Intercom pcs
2.21) LAN pcs
2.22) CCTV pcs
2.23) Others (Pls. Specify)
sub-total
MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
5.1.19) Auxillary Kitchen sq.m.
5.1.20) Outdoor Area sq.m.
5.1.21) Walkway 1 sq.m.
5.1.22) Others (Please Specify) sq.m.
VII. WATERPROOFING
7.1) All T&B's (Second Floor)
Mapelastic / Barralastic waterproofing with Fiber Mesh on sq.m.
corners. Shower Walls must be 1.80m high to be waterproof
7.2) Concrete Ledge & Roof Slab
Mapelastic / Barralastic waterproofing with sq.m.
Fiber Mesh on corners
7.3) Canopy Roof
Mapelastic / Barralastic waterproofing with sq.m.
Fiber Mesh on corners
7.4) Others (Pls. Specify)
sub-total
MATERIALS LABOR
ITEM NO. DESCRIPTION QUANTITY UNIT
UNIT COST TOTAL UNIT COST TOTAL
GRAND TOTAL AMOUNT (Roughing-in & Finishing Works)
Labor & Materials
Prepared by: