IMPROVEMENT AND MAINTENANCE OF 49.01 KM RURAL ROADS IN MANNAR DISTRICT IN THE NORTHERN PROVINCE ‐ PACKAGE 3
CONTRACT PACKAGE : RDA/ADB/IROAD‐2(NP)/NCB/MN‐03
Item Pay Item Work Description Unit Qty Rate Amount Period to be Used Date Reference if Any Remarks
1B.1.6b.18 120.6(2) Supply and maintain Vehicle Type 2 Mth 3.00 200,000.00 600,000.00 1/Aug/22 ‐ 31/Oct/22
1B.1.7.25 120.8(3) CAD Operator Mth 3.00 75,000.00 225,000.00 1/Aug/22 ‐ 31/Oct/22
3.1.6 301(16) Preparation of subgrade in cut areas Cu.m 1,200.00 30.00 36,000.00
3.2.10 301A(5) Channel excavation, unsuitable soil Cu.m 1,500.00 660.00 990,000.00
Tentative surplus qty in final
3.4.18 304(2)a Embankment construction using borrow, Type I Cu.m 500.00 5,240.00 2,620,000.00 measurement drawings which is to be
finalized
3.4.19 304(2)b Embankment construction using borrow, Type II Cu.m 250.00 5,240.00 1,310,000.00
3.4.20 304(3) Trimming, level and compaction of original ground Sq.m 1,200.00 52.00 62,400.00
3.4.22 304(6) Embankment construction using rockfill Cu.m 100.00 6,803.00 680,300.00
Item Pay Item Work Description Unit Qty Rate Amount Period to be Used Date Reference if Any Remarks
4.4.11 506(1) Asphalt concrete in Wearing Course 50 mm thick Sq.m 350.00 1,771.00 619,850.00
10.2 122(2) Maintenance of road during year two 489.98 12,000.00 5,879,760.00
10.3 122(3) Maintenance of road during year three 489.98 10,000.00 4,899,800.00
3 Cost of health care and sanitary items for COVID-19 1,608,355.00 Refer attachment 3
……………………………………………….. ………………………………………………..
Prepared By Submitted By
Quantity Surveyor Contractor's Representative
CNTIC ‐ RR JV CNTIC ‐ RR JV
Attachment 01
SECOND INTEGRATED ROAD INVESTMENT PROGRAM - REHABILITATION /IMPROVEMENT AND MAINTENANCE OF 49.01 KM RURAL ROADS IN
MANNAR DISTRICT IN THE NOTHERN PROVINCE - PACKAGE 3
Extended
Boq Item Total Cost For
Description prelimineries Per Extended Period
Nos Extensions
Month
SECOND INTEGRATED ROAD INVESTMENT PROGRAM ‐ REHABILITATION /IMPROVEMENT AND MAINTENANCE OF 49.01 KM RURAL ROADS IN MANNAR DISTRICT IN THE
NOTHERN PROVINCE ‐ PACKAGE 3
Cost of providing facilities for the Engineer beyond the provisioned contract duration following the EOT granted
Duration
BOQ Item Description Period Monthly Cost Amount(Rs) Remarks
(months)