You are on page 1of 1

2

Kilwa District Council


Bills of Quantities for Routine Maintanance, Spot Improvement, and Culverts Construction along Namayuni-Namakolo
(5.5km), Chumo-Ingirito (5km) roads
Bill 1. Preliminary and general cost
item Activity Specs Unit Qty Rate Amount
item (Tshs) (Tshs)

1.03 Site establishment and removal on completion 1.06 Ls 1 5,000,000.00 5,000,000.00


1.04 Traffic/ Road diversion during construction 1.09 Ls 1 3,000,000.00 3,000,000.00
1.05 Excavation & laboratory testing. 1.10 Ps 1 1,500,000.00 1,500,000.00
1.06 Mobilization/Demobilisation of plant & Equipm 1.07 Ls 1 30,000,000.00 30,000,000.00
1.07 Provision of information panel (Project sign Board) Ls 2
1,500,000.00
3,000,000.00
1.8 HIV/AIDS Awareness campaigns Ps 1 500,000 500,000.00
Total for Bill (1) General 43,000,000.00

BILL 2: 81050: Namayuni-Namakolo (5km) road Routine Maintanance


Road Works
2.09b Site clearance by grass cutting 2.03 m2 33,480 800.00 26,784,000.00
Tree felling Nos 5 150,000.00 750,000.00
2.05a Light grading 2.4 Km 5.00 6,000,000.00 30,000,000.00
Sub Total for Routine Maintenance 57,534,000.00

Namayuni-Namakolo (0.5km) road Spot Improvement


2.09b Site clearance . 2.03 m2 9,620 800.00 7,696,000.00
2.05a Heavy grading 2.4 Km 0.50 8,000,000.00 4,000,000.00
Clear borrow area and remove overburden 2.08 m3 200 150,000.00 30,000,000.00
Cut and borow to fill gullies with selected materials
as directed by Engineer and compact in layers n.e m3 300 30,000.00
300mm thick 9,000,000.00
2.06(b) Over Hauled distance (OHD) 2.90(b) M Km 3
1,800 20,000.00 36,000,000.00
Sub Total for Spot Improvement 86,696,000.00

Drainage Works
3.01d Excavate for new Mitre drains 3.03 m3 450 4,500.00 2,025,000.00
3.02a Excavation for drainage structures 3.03 m3 24 6,000.00 144,000.00
3.02b Backfilling with selected borrow materials 3.03c m3 450 15,000.00 6,750,000.00
4.27c Concrete pipe culvert - 900mm 3.07c m 24 550,000.00 13,200,000.00
3.09b Concrete in drainage structure bedding - class 15 3.08 m3 6
280,000.00
1,680,000.00
3.09c Concrete in drainage structure -class 20 3.08 m3 22 350,000.00 7,700,000.00
2.06 Gravelling within FHD to culvert approaches 2.90 m3 60 50,000.00 3,000,000.00
2.07a Overhaul gravel 2.1 M Km
3
450 15,000.00 6,750,000.00
3.10b Reinforcement steel - high yield steel 3.08g kg 135 4,000.00 540,000.00
3.01d Excavation for inlet/outlets of culverts 3.02e m3 45 9,000.00 405,000.00
Sub Total Drainage works 42,194,000.00
Total for Bill No. 2 186,424,000.00

BILL 3: 81120: Chumo-Ingirito (5.3km) road Routine Maintanance


Road Works
2.09b Site clearance by dozzer 2.03 m2 24,200 1,000.00 24,200,000.00
Tree felling Nos 15 100,000.00 1,500,000.00
Cut to fill m3 300 150,000.00 45,000,000.00
2.05a Heavy Reshaping 2.4 Km 5.30 800,000.00 4,240,000.00
Sub Total for Routine Maintenance 74,940,000.00

Drainage Works
3.01d Excavate for new Mitre drains 3.03 m3 500 12000 6,000,000.00
Sub Total Drainage works 6,000,000.00
3
Total for Bill No. 3 80,940,000.00
SUMMARY
BILL NO. ROAD NAME AMOUNT (TSHS)
BILL NO. 1 Preliminary and General cost
43,000,000.00

BILL NO. 2 Namayuni-Namakolo


186,424,000.00
(5.5km)
BILL NO. 3 Chumo-Ingirito (5.3km)
80,940,000.00
TOTAL 310,364,000.00
GRAND TOTAL +VAT 366,229,520.00