PROJECT STATUS REPORT


PROJECT SUMMARY

REPORT DATE PROJECT NAME PREPARED BY


22/12/2022 Sun Drying bed Maintenance Work at Seeb Stone for Trading
Rusayl STP

Progress still 22nd December 2022

PROJECT OVERVIEW

TASK % DONE NOTES


Cleaning of sludge drying bed 100 Cleaning of sludge drying bed and underground drain path
TASK % DONE NOTES
Demolished and Disposal 100 Dismantling and cleaning of existing damaged sludge drying bed
works

Page 2
TASK % DONE NOTES
Repair of cracked and 100 Dismantling and cleaning of existing damaged sludge drying bed
damage concrete walls

Page 3
TASK % DONE NOTES
Cleaning of Underground Drain 100 Removal of existing sewage and cleaning of underground pipeline
Pipe

Page 4
TASK % DONE NOTES
Covered underground waste pipes 100 Covered underground waste pipes (Using of Permeable materials)

BIFORE FILLING

AFTER FILLING

Page 5
TASK % DONE NOTES
Construct of sludge drying bed 75  Solid Block work in cement and sand 1: 5
boundary wall & painting work  15mm thick Plastering to wall in cement and sand 1:5 finished
smooth internally
 Using of approved type epoxy paint to specified color externally

Page 6
Page 7
PAINTING WORK

Page 8

TASK % DONE NOTES


Work Completion 100  Completing of the Drying bed partition