208+000)
2. Present Status
Highway (Cumulative length achieved in Km. till 5th Feb 2018)
a) Earthwork up to subgrade top 7.38 Km.
b) GSB 4.20 Km.
c) WMM 3.02 Km.
Structure (Completed in Nos.) (Total Culverts as per Scope = 29 Nos.)
In 4 Lane 4 Nos. Completed Physical Progress = 5.10%
a) Culverts
In 2 lane 3 Nos. Completed
(Total Minor Bridges as per Scope = 6
c) Minor Bridge Financial Progress = 4.36 %
Nos.)
Works Not Yet Started
d) Major Bridge (Total Major Bridges as per Scope = 1
No.)
Works Not Yet Started
3. Revised Work programme submitted by the Contractor on 18th Jan ‘2018 during the visit of NLPM to the site.
Target as per Revised Work Programme (In Cr.) Achieved (In Cr.) Remarks
Jan 2018 10.26 0.32 Progress achieved up to 31st Jan 2018
Feb 2018 34.20 - Earthwork is in progress.
Month Mar 2018 36.24 - The progress will be monitor closely
April 2018 28.54 - month wise and shall be intimated to
the NHIDCL Authority
Other Details
SL DESCRIPTION TARGET ACHIEVED REMARKS
No. (As on 5th Feb 2018)
4. Site Laboratory Functional w.e.f 1st Nov,2017
Laboratory Equipments related to 1st week of Not Available till date Contractor reassures to purchase
Bitumen Tests Dec’ 2017 necessary equipment within 10 days.
5. Machineries
31st Dec’ Installation is in
a) Commissioning of HMP Plant is yet to be commissioned.
2018 progress.
- Functional w.e.f. 1st
b) WMM plant
Week of Nov’ 2017
- Operational in the
c) Batching Plant
base camp location.
I. Mobile Crusher Operational w.e.f 1st
-
Unit Nov’ 2017
d) Crusher
Plant Not yet brought to the
II. Jaw Crusher Dec,2017 Not yet mobilized.
site.
6. Man Power
Description Remarks
The Contractor is yet to Mobilize an experience M.E, S.E
The Contractor has not taken proper action in mobilizing a
& Planning Engineer.
working team with experienced and qualified Key and Sub
The CV of B.E has been submitted to the TL office for
Key professionals
approval, but he has not mobilized at site.