Professional Documents
Culture Documents
Particulars
7,500,000.00 150,000,000.00
I. Civil Works
A. Contracts 7,050,000.00 117,500,000.00
B. Administration (FAW) 10,000,000.00
II. IDP 150,000.00 2,250,000.00
III. Construction Survey 75,000.00 1,500,000.00
IV. Parcellary Survey 1,500,000.00
V. ROW Acquisition, Property/Plant Damages 5,000,000.00
VI. Procurement of Equipment & Vehicle 3,000,000.00
VII. Field Support, Supervision & Monitoring 225,000.00 4,500,000.00
VIII. Consultancy Services 2,500,000.00
IX. Taxes (for FAP's only)
X. Contingencies (5-10% as needed) 2,250,000.00
TOTAL
1. New Projects
a. Line Projects, NIP's
b. Extension/Expansion Areas
c. Small Irrigation Projects
2. Rehab/Restoration/Repair
a. RREIS-NIS/CIS
3. Others
a. CARP-IC
b. BUB
c. EGPIP
AL PROJECT COST
Particulars
20,000,000.00 150,000,000.00
13,400,000.00 125,800,000.00
5,000,000.00 10,000,000.00
300,000.00 1,500,000.00
200,000.00 1,500,000.00
200,000.00 1,500,000.00
2,500,000.00
600,000.00 4,500,000.00
1,200,000.00
300,000.00 1,500,000.00
PROGRAM OF WORKS
BASIC ATTACHMENT
General Project Lay-out & Schematic Diagram including the Project Plan
3 Attachment "A" - which is color-coded to show the programmed activities as reflected in
the Geo-Tagged Pictures (GPS) and Work/Contract Packaging as reflected
in the Geo-Tagged Pictures (GPS)
CONTRACT PACKAGING
BASIC ATTACHMENT
I. GENERAL INFORMATION
1 Project Location 6 Overall Project Cost (P'000) Original Revised
a. Region 02 a. GOP
b. Province CAGAYAN b. Loan Proceeds
City/Municipality Solana c. Others (Equity, etc.)
District I TOTAL - -
2 Service Area/ 7 Physical Target (Overall)
Designed Area a. New Area (Ha.)
3 Source of Water b. Restored Area (Ha.)
a. Drainage Area c. Repair Works (specific for rehab.)
b. Dependable Flow c.1. Earth Canal (km.)
4 Type of Irrigation 5 Point of Diversion c.2. Lined Canal (km.)
a. Run-Off the River Latitude Longtitude c.3. Structures (units)
b. Reservoir c.4. Coconet slope Protection (sq.m.)
c. Pump Type c.5. Concrete Service Road (km.)
d. Ground Water Pump c.6. Earth Service Road (km.)
e. Others (Sprinkler/Drip) c.7. Other Repair Works (Pls. specify) -
c.8. Rehab Area (Ha.) (Attribution) -
d. Other Activities: (Pls. specify) -
8 Overall Implementation Schedule
Original Revised
a. Physical Starting Date
b. Completion Date
3 CONSTRUCTION SURVEY -
4 PARCELLARY SURVEY - -
ROW ACQUISITION, PLANT/PROPERTY
5 DAMAGES - - BENAJMIN N. RIVERA
10 CONTINGENCIES - - FRANCIS C. YU
1 GOP
720,514.37 - 720,514.37
ANTONIO C. LARA
2 LOAN PROCEEDS
Regional Irrigation Manager
###
"SIGNATORIES SHALL END UP
AT THE LEVEL OF IMO
MANAGER EXCEPT FOR NEW
PROJECTS"
BICUD SWIS
MANPOWER REQUIREMENT, EQUIPMENT REQUIREMENT, MATERIAL REQUIREMENT & CASH REQUIREMENT
CY 2017 PROGRAM OF WORKS
Attachment "C" 1 of 3
APRIL MAY JUNE 2ND QUANTER TOTAL
PARTICULAR DESCRIPTION P.C. L.P. P.C. L.P. P.C. L.P. P.C. L.P.
F.O. C.O. F.O. C.O. F.O. C.O. F.O. C.O. F.O. C.O. F.O. C.O. F.O. C.O. F.O.
I. MANPOWER REQUIREMENT NUMBER OF PERSONNEL
1 Monthly Personnel 1
2 Daily Personnel 1
3 Contractual 15
II. EQUIPMENT REQUIREMENT
1 Dozer 1
2 Backhoe 1
3 Loader 1
4 etc…
III. MATERIAL REQUIREMENT
DIRECT COST
I. Civil Works
A. Contract Works
Attachment "D"
WORK TO BE DONE
ACTIVITY
UNIT QUANTITY UNIT COST ESTIMATED COST
I. DIRECT COST
A. STRUCTURE EXCATION
a. Common Earth Excavation cu.m. 134.85 134.70 18,164.03
B. CONCRETE WORKS
a. Class "A" Concrete cu.m. 12.41 8,117.70 100,724.42
b. Reinforcing Steel Bars kgs 836.02 84.00 70,226.09
c. Gravel Blanket cu.m. 2.08 585.00 1,214.46
d. CHB Wall sq.m. 108.80 989.8 107,690.24
C. CHB Canal Lining
a. 4" CHB sq.m. 56.00 989.80 55,428.80
b. Class "A" Concrete cu.m. 7.00 8,117.70 56,823.90
c. Reinforcing Steel Bars kg. 540.09 84.00 45,367.30
d. Gravel Blanket cu.m. 7.00 585.00 4095.00
D. Canal Structures
a. Gravel Blanket cu.m. 0.11 585.00 61.43
b. Class "A" Concrete cu.m. 1.56 8117.70 12663.61
c. 46cm ø RCP pcs. 12.00 2972.60 35671.20
E. Miscellaneous Metal Works and Materials
a. 2"x 2" Mesh Wire (4'x 8') pcs. 23.00 1,000.00 23,000.00
b. GI Pipe Post
1. 1 1/4" ø pipe lin.m. 188.00 506.00 95,128.00
3. 3" ø pipe lin.m. 36.00 700.00 25,200.00
c. flat bar pcs. 66.00 500.00 33,000.00
F. SPOT LIGHT pcs. 6.00 2,500.00 15,000.00
G. Paint L.S. 12,000.00 12,000.00
H. Wirings and Switches L.S. 9,055.89 9,055.89
Sub-Total 720,514.37
TOTAL PROJECT COST (NEP) 720,514.37
Approved by:
FRANCIS C. YU
Acting Manager
(Name of Project)
DETAILED BREAKDOWN
OVER-ALL PROGRAM OF WORKS
WORK TO BE DONE
TOTAL PROJECT COST
CY 2016 FUTURE YEARS
Amount QTY Unit Cost Amount QTY Unit Cost Amount
- - - -
- - - -
139,560.00 1,200.00 116.30 139,560.00
346,920.00 2,800.00 123.90 346,920.00
- - - -
158,015.00 850.00 185.90 158,015.00
- - - -
1,575,240.00 1,200.00 1,312.70 1,575,240.00
- - - -
573,912.50 125.00 4,591.30 573,912.50
5,406,765.00 650.00 8,318.10 5,406,765.00
- - - -
2,037,000.00 35,000.00 58.20 2,037,000.00
383,250.00 35,000.00 10.95 383,250.00
18,230,250.00 2,500.00 7,292.10 18,230,250.00
1,042,764.80 224.00 4,655.20 1,042,764.80
169,450.20 138.00 1,227.90 169,450.20
544,495.00 350.00 1,555.70 544,495.00
304,878.00 245.00 1,244.40 304,878.00
15,427,880.00 5,200.00 2,966.90 15,427,880.00
2,384,800.00 1,000.00 2,384.80 2,384,800.00
- - - -
66,456.00 65.00 1,022.40 66,456.00
5,053.50 15.00 336.90 5,053.50
14,150.00 125.00 113.20 14,150.00
- - - -
34,502.00 2.00 17,251.00 34,502.00
1,074,640.00 140.00 7,676.00 1,074,640.00
100,626.50 65.00 1,548.10 100,626.50
18,182.00 1.00 18,182.00 18,182.00
14,615.00 185.00 79.00 14,615.00
- - - -
887,680.00 2.00 443,840.00 887,680.00
2,803,200.00 3.00 934,400.00 2,803,200.00
805,920.00 3.00 268,640.00 805,920.00
946,080.00 3.00 315,360.00 946,080.00
105,120.00 3.00 35,040.00 105,120.00
700,800.00 3.00 233,600.00 700,800.00
525,600.00 3.00 175,200.00 525,600.00
58,400.00 1.00 58,400.00 58,400.00
140,160.00 1.00 140,160.00 140,160.00
268,640.00 1.00 268,640.00 268,640.00
- - - -
19,964.00 2.00 9,982.00 19,964.00
59,892.00 3.00 19,964.00 59,892.00
119,784.00 3.00 39,928.00 119,784.00
39,927.00 3.00 13,309.00 39,927.00
49,911.00 3.00 16,637.00 49,911.00
49,911.00 3.00 16,637.00 49,911.00
39,923.00 1.00 39,923.00 39,923.00
13,309.30 1.00 13,309.30 13,309.30
19,964.00 1.00 19,964.00 19,964.00
- - - -
7,708,800.00 1,200.00 6,424.00 7,708,800.00
267,360.00 1,200.00 222.80 267,360.00
- - - -
1,216,875.00 2,500.00 486.75 1,216,875.00
41,500.00 1,000.00 41.50 41,500.00
73,872,875.80 - 73,872,875.80
- - - -
- - - -
148,680.00 1,200.00 123.90 148,680.00
31,101.00 210.00 148.10 31,101.00
- - - -
60,417.50 325.00 185.90 60,417.50
- - - -
1,115,795.00 850.00 1,312.70 1,115,795.00
- - - -
390,260.50 85.00 4,591.30 390,260.50
3,733,505.10 387.00 9,647.30 3,733,505.10
- - - -
1,076,700.00 18,500.00 58.20 1,076,700.00
202,575.00 18,500.00 10.95 202,575.00
209,484.00 45.00 4,655.20 209,484.00
56,005.20 36.00 1,555.70 56,005.20
111,996.00 90.00 1,244.40 111,996.00
- - - -
116,248.50 45.00 2,583.30 116,248.50
1,900,525.00 550.00 3,455.50 1,900,525.00
186,562.80 36.00 5,182.30 186,562.80
35,275.00 850.00 41.50 35,275.00
11,225,130.60 - 11,225,130.60
-
1,035,000.00 75,000.00 13.80 1,035,000.00
5,205,600.00 6,000.00 867.60 5,205,600.00
6,240,600.00 - 6,240,600.00
-
1,318,500.00 10,000.00 131.85 1,318,500.00
1,053,500.00 10,000.00 105.35 1,053,500.00
2,372,000.00 - 2,372,000.00
-
700,800.00 5.00 140,160.00 700,800.00
1,022,000.00 25.00 40,880.00 1,022,000.00
1,722,800.00 - 1,722,800.00
120,969,136.05 - 120,969,136.05
- - - -
- - - -
140,314.81 2,200.00 63.78 140,314.81
- - - -
2,785,579.74 250.00 11,142.32 2,785,579.74
- - - -
444,743.13 8,750.00 50.83 444,743.13
139,223.44 8,750.00 15.91 139,223.44
101,523.53 15.00 6,768.24 101,523.53
59,764.59 35.00 1,707.56 59,764.59
- - - -
113,231.76 36.00 3,145.33 113,231.76
1,033,654.45 250.00 4,134.62 1,033,654.45
69,131.31 8.00 8,641.41 69,131.31
279,375.00 1,500.00 186.25 279,375.00
5,166,541.76 - 5,166,541.76
- - - -
- - - -
188,298.75 674.00 279.38 188,298.75
- - - -
668,539.14 60.00 11,142.32 668,539.14
- - - -
91,490.02 1,800.00 50.83 91,490.02
28,640.25 1,800.00 15.91 28,640.25
50,761.76 7.50 6,768.24 50,761.76
17,075.60 10.00 1,707.56 17,075.60
- - - -
50,587.38 25.00 2,023.50 50,587.38
- - - -
8,769.75 5.00 1,753.95 8,769.75
87,697.50 25.00 3,507.90 87,697.50
22,350.00 120.00 186.25 22,350.00
1,214,210.15 - 1,214,210.15
6,380,751.91 - 6,380,751.91
127,349,887.96 - 127,349,887.96
42,135.12 lump sum lump sum 42,135.12 42,135.12
28,437.30 lump sum lump sum 28,437.30 28,437.30
- lump sum lump sum - -
- lump sum lump sum - -
85,308.10 lump sum lump sum 85,308.10 85,308.10
- lump sum lump sum - -
- lump sum lump sum - -
127,505,768.48 127,505,768.48
PROGRAM OF WORK DATA
ACTIVITY
UNIT Qty
I. DIRECT COST
A. STRUCTURE EXCATION
a. Common Earth Excavation cu.m. 134.85
B. CONCRETE WORKS
a. Class "A" Concrete cu.m. 12.41
b. Reinforcing Steel Bars kgs 836.02
c. Gravel Blanket cu.m. 2.08
d. CHB Wall sq.m. 108.80
C. CHB Canal Lining
a. 4" CHB sq.m. 56.00
b. Class "A" Concrete cu.m. 7.00
c. Reinforcing Steel Bars kg. 540.09
d. Gravel Blanket cu.m. 7.00
D. Canal Structures
a. Gravel Blanket cu.m. 0.11
b. Class "A" Concrete cu.m. 1.56
c. 46cm ø RCP pcs. 12.00
E. Miscellaneous Metal Works and Materials
a. 2"x 2" Steel Matting (4'x 8') pcs. 23.00
b. GI Pipe Post
1. 1 1/4" ø pipe x 6m S40 lin.m. 188.00
2. 3" ø pipe x 6m S40 lin.m. 36.00
c. flat bar pcs. 66.00
F. SPOT LIGHT pcs. 6.00
G. Paint L.S.
H. Wirings and Switches L.S.
TOTAL
PROGRAM OF WORK DATA QTY. ACCOMP.
PERCENT WT. PREVIOUS
UNIT COST AMOUNT THIS PERIOD TO DATE
5,685.42 0.79
-
100,740.66 13.98
70,225.68 9.75
1,216.80 0.17
107,690.24 14.95
-
27,714.40 3.85
28,411.95 3.94
22,683.78 3.15
2,047.50 0.28
-
-
-
-
-
20,000.00 2.78
-
95,128.00 13.20
25,200.00 3.50
20,000.00 2.78
-
-
-
526,744.43 73.11
MASTERLIST OF WORKS TO BE DONE
BICUD SWIS
Lallo, Cagayan
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
300.00 /day x - hrs./trip
Labor Cost = = - /bag
8 hr/day x 1 bag/trip
SUMMARY
Page 35
B. Lumber
AHD = 5.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 5.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = - kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 300.00 /day = 1,500.00 /day
Base Cost = 55.00 /bd.ft.
Capacity of Truck = 4,000 bd.ft./trip
Capability of five (5) Laborers
Loading = 4,000 bd.ft./trip
Unloading = 4,000 bd.ft./trip
a. Hauling from Source To Dump Site
Cycle Time
with load = 5.00 kms. / / 35.00 km./hr. = 0.14 hrs./trip
T-I
without load = 5.00 kms. / / 45.00 km./hr. = 0.11 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 20.00 km./hr. = - hrs./trip
T-IV
without load = - kms. / / 25.00 km./hr. = - hrs./trip
Loading = 4000 bd.ft./trip / / 4000 bd.ft./trip = 1.00 hrs./trip
Unloading = 4000 bd.ft./trip / / 4000 bd.ft./trip = 1.00 hrs./trip
total time = 2.25 hrs./trip
920.00 /hr. x 2.25 hrs./trip
Equipment Cost = = 0.52 /bd.ft.
4000 bd.ft./trip
1,500.00 /day x 2.25 hrs./trip
Labor Cost = = 0.11 /bd.ft.
8 hr/day x 4000 bd.ft./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 300.00 /day
Capability : 25 bd.ft./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
300.00 /day x - hrs./trip
Labor Cost = = - /bd.ft.
8 hr/day x 25 bd.ft./trip
SUMMARY
Page 36
SUMMARY
SUMMARY
Page 37
E. Sand and Gravel
1 Quarrying
Utilized : 160 HP Dozer
Production : 65 cu. m./hr.
Rental : 2,257.00 /hr. (incl. Fuel & operator)
Equipment
2,257.00 /hr
Cost = = 34.72 /cu. m
65 /cu. m./hr.
2 Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)
Equipment
1,746.00 /hr
Cost = = 31.75 /cu. m
55 /cu. m./hr.
3 Hauling
AHD = 5.00 kms. Tuguegarao, Cagayan Speed (kph)
with Load w/o Load
Type of Road : Type I = 5.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = - kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilize Dump Truck (6W)
Capacity : 4.00 cu.m./trip
truck rental = 877.00 /hr.
Quarry Pit Fee : 120.00 /cu.m.
4 Screening of Aggregates
Capability
Sand = 6.00 cu. m./day
Gravel = 4.00 cu. m./day
1 -Laborers @ 300.00 /day
300.00 / day
Sand = = 50.00 /m3
6.00 m3/day
300.00 / day
Gravel = = 75.00 /m3
4.00 m3/day
SUMMARY
SAND GRAVEL
1 Quarry Pit Fee = 120.00 /m3 = 120.00 /m3
2 Quarrying = 34.72 /m3 = 34.72 /m3
3 Loading = 31.75 /m3 = 31.75 /m3
4 Hauling = 81.26 /m3 = 81.26 /m3
5 Screening = 50.00 /m3 = 75.00 /m3
Total = 317.73 /m3 342.73 /m3
Plus: 12% VAT = 38.13 /m3 41.13 /m3
2% Excise Tax = 6.35 /m3 6.85 /m3
TOTAL COST = 362.21 /m3 = 390.71 /m3
say 362.20 /m3 say 390.70 /m3
Page 38
F. 4" CHB
AHD = 5.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 5.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = - kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 300.00 /day = 1,500.00 /day
Base Cost = 12.00 /pc.
Capacity of Truck = 600 pc./trip
Capability of five (5) Laborers
Loading = 600 pc./hr
Unloading = 600 pc./hr
G. GI Pipes (2"Ø)
AHD = 5.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 5.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = - kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 300.00 /day = 1,500.00 /day
Base Cost :
GI Pipes = 250.00 /lin.m.
Capacity of Truck = 2,000 lin.m./trip
Capability of five (5) Laborers
Loading = 2,000 lin.m./trip
Unloading = 2,000 lin.m./trip
a. Hauling from Source To Dump Site
Cycle Time
with load = 5.00 kms. / / 35.00 km./hr. = 0.14 hrs./trip
T-I
without load = 5.00 kms. / / 45.00 km./hr. = 0.11 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 20.00 km./hr. = - hrs./trip
T-IV
without load = - kms. / / 25.00 km./hr. = - hrs./trip
Loading = 2000 lin.m./trip / / 2000 lin.m./trip = 1.00 hrs./trip
Unloading = 2000 lin.m./trip / / 2000 lin.m./trip = 1.00 hrs./trip
total time = 2.25 hrs./trip
920.00 /hr. x 2.25 hrs./trip
Equipment Cost = = 1.04 /lin.m.
2000 lin.m./trip
1,500.00 /day x 2.25 hrs./trip
Labor Cost = = 0.21 /lin.m.
8 hr/day x 2000 lin.m./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 300.00 /day
Capability : 30 lin.m./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
300.00 /day x - hrs./trip
Labor Cost = = - /lin.m.
8 hr/day x 30 lin.m./trip
SUMMARY
GI Pipes
1 Base Cost = 250.00
2 Hauling
a. Equipment Cost = 1.04
b. Labor Cost = 0.21
Total Hauling Cost = 1.25
12% VAT for Hauling Cost = 0.15
TOTAL COST = 251.40
say 251.40
Page 39
H. GI Pipes (3/4"Ø)
AHD = 5.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 5.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = - kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 300.00 /day = 1,500.00 /day
Base Cost :
GI Pipes = 160.00 /lin.m.
PVC Pipes = /lin.m.
Capacity of Truck = 2,000 lin.m./trip
Capability of five (5) Laborers
Loading = 2,000 lin.m./trip
Unloading = 2,000 lin.m./trip
a. Hauling from Source To Dump Site
Cycle Time
with load = 5.00 kms. / / 35.00 km./hr. = 0.14 hrs./trip
T-I
without load = 5.00 kms. / / 45.00 km./hr. = 0.11 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 20.00 km./hr. = - hrs./trip
T-IV
without load = - kms. / / 25.00 km./hr. = - hrs./trip
Loading = 2000 lin.m./trip / / 2000 lin.m./trip = 1.00 hrs./trip
Unloading = 2000 lin.m./trip / / 2000 lin.m./trip = 1.00 hrs./trip
total time = 2.25 hrs./trip
920.00 /hr. x 2.25 hrs./trip
Equipment Cost = = 1.04 /lin.m.
2000 lin.m./trip
1,500.00 /day x 2.25 hrs./trip
Labor Cost = = 0.21 /lin.m.
8 hr/day x 2000 lin.m./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 300.00 /day
Capability : 30 lin.m./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
300.00 /day x - hrs./trip
Labor Cost = = - /lin.m.
8 hr/day x 30 lin.m./trip
SUMMARY
GI Pipes
1 Base Cost = 160.00
2 Hauling
a. Equipment Cost = 1.04
b. Labor Cost = 0.21
Total Hauling Cost = 1.25
12% VAT for Hauling Cost = 0.15
TOTAL COST = 161.40
say 161.40
RECAPITULATION
Page 40
IV. ITEM OF WORK
A. CONCRETING WORKS
1. Class "A" Concrete
a. Materials
Cement = 9.00 bags /m3 x 286.40 / bag = 2,577.60 /m3
Sand = 0.45 m3 /m3 x 362.20 /m3 = 162.99 /m3
Gravel = 0.90 m3 /m3 x 390.70 /m3 = 351.63 /m3
F. Lumber = 2.00 bd. ft./m 3
x 55.70 /bd. ft. = 111.40 /m3
Plywood = 1.00 pc./m3 x 861.20 /pc. = 861.20 /m3
Tie Wire = 0.50 kgs. /m2 x 90.40 /kg. = 45.20 /m2
CWN = 1.00 kgs. /m3 x 90.40 /kg. = 90.40 /m3
Material Cost . . . . . = 4,200.42 /m3
b. Labor
b.1 Fabrication, Placing & Dismantling of Forms
Capability = 3.50 cu. m./day
2 -Carpenters @ 450.00 /day = 900.00 /day
4 -Laborers @ 300.00 /day = 1,200.00 /day
2,100.00 /day
2,100.00 / day
Cost = = 600.00 /m3
3.50 m3/day
3,850.00 / day
Cost = = 1,100.00 /m3
3.50 m3/day
c. Equipment Utilization
Utilized : 1 - Bagger Mixer
Rental = 172.00 /hr. (incl. fuel & operator)
9.00 bags /m3 x 10.00 min./bag
Time of Mixer/day = = 1.50 hrs./m3
60.00 min./hr.
SUMMARY
12%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 4,200.42 - 4,200.42 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 1,700.00 204.00 1,904.00 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = 258.00 30.96 288.96 /m3
TOTAL DIRECT COST = 6,158.42 234.96 6,393.38 /m3
Plus: 25% OCM & Profit = 1,539.61 184.75 1,724.36 /m3
UNIT COST = 7,698.03 419.71 8,117.74 /m3
say 8,117.70 /m3
750.00 /day
Cost = = 9.38 /kg.
80.00 kgs./day kgs.
Plus: 25% OCM & Profit = 2.34 /kg.
12% VAT (Labor) = 1.13 /kg.
12% VAT (OCM & Profit) = 0.28 /kg.
UNIT COST = 13.13 /kg.
say 13.10 /kg.
Page 41
C. GRAVEL BLANKET
1. Materials
Gravel = 1.00 cu.m./cu.m. x 390.70 /cu.m. = 390.70 /m3
Material Cost . . . . . = 390.70 /m3
2. Labor
Capability = 5.00 cu. m./day
1 -Laborers @ 300.00 /day = 300.00 /day
300.00 /day
300.00 / day
Cost = = 60.00 /m3
5.00 m3/day
SUMMARY
12%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 390.70 - 390.70 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 60.00 7.20 67.20 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = - - - /m3
TOTAL DIRECT COST = 450.70 7.20 457.90 /m3
Plus: 25% OCM & Profit = 112.68 13.52 126.20 /m3
UNIT COST = 563.38 584.10 /m3
say 585.00 /m3
b. Labor
b.1 Laying
Capability = 14.00 sq. m./day
1 -Mason @ 450.00 /day = 450.00 /day
2 -Laborers @ 300.00 /day = 600.00 /day
1,050.00 /day
b.2 Plastering
Capability = 12.00 sq. m./day
1 -Mason @ 450.00 /day = 450.00 /day
1 -Laborers @ 300.00 /day = 300.00 /day
750.00 /day
SUMMARY
12%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 622.88 - 622.88 /m2
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 137.50 16.50 154.00 /m2
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = - - - /m2
TOTAL DIRECT COST = 760.38 16.50 776.88 /m2
Plus: 25% OCM & Profit = 190.09 22.81 212.91 /m2
UNIT COST = 950.47 989.78 /m2
say 989.80 /m2
Page 42
E. Fabrication & Installation of Reinforced Concrete Pipes (RCP)
1. 46 cm Æ
1. Fabrication
a. Materials
Cement = 1.22 bags/pc. x 286.40 /bag = 349.41 /pc.
Sand = 0.05 cu. m./pc. x 362.20 /cu. m = 18.11 /pc.
Gravel = 0.10 cu. m./pc. x 390.70 /cu. m = 39.07 /pc.
GI Sheet = 0.19 lin. ft./pc x 65.50 /lin. ft. = 12.45 /pc.
RSB = 7.72 kg./pc x 55.40 /kg. = 427.69 /pc.
Lumber = 0.36 bd. ft./pc x 55.70 /bd. ft. = 20.05 /pc.
CWN = 0.20 kg./pc x 90.40 /kg. = 18.08 /pc.
Material Cost . . . . . . P 884.85 /pc.
b. Labor
Capability = 11 pcs./day
1 - Foreman @ 550.00 /day = 550.00 /day
1 - Carpenter/Stlma @ 450.00 /day = 450.00 /day
1 - Mason @ 450.00 /day = 450.00 /day
12 - Laborers @ 300.00 /day = 3,600.00 /day
5,050.00 /day
5,050.00 /day
Cost = = 459.09 /pc.
11 pcs./day
c. Equipment
Utilized : 1 - Bagger Mixer
Rental = 172.00 /hr. (incl. fuel & operator)
Time of Mixer/day = 1.22 bags/pc. x 10 min./bag = 0.20 hr./pc.
60 min./hr.
b. Labor
Capability = 14 pcs./day
1 - Foreman @ 550.00 /day = 550.00 /day
1 - Carpenter/Stlma @ 450.00 /day = 450.00 /day
1 - Mason @ 450.00 /day = 450.00 /day
12 - Laborers @ 300.00 /day = 3,600.00 /day
5,050.00 /day
5,050.00 /day
Cost = = 360.71 /pc.
14 pcs./day
c. Equipment
Utilized : 1 - Bagger Mixer
Rental = 172.00 /hr. (incl. fuel & operator)
SUMMARY
12%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 1,373.32 - 1,373.32 /pc.
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 819.81 98.38 918.18 /pc.
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = 47.87 5.74 53.62 /pc.
TOTAL DIRECT COST = 2,240.99 104.12 2,345.11 /pc.
Plus: 25% Indirect Cost = 560.25 67.23 627.48 /pc.
UNIT COST = 2,801.24 2,972.59 /pc.
say 2,972.60 /pc.
D. MISCELLANEOUS METAL WORKS AND MATERIALS
1. 2"ø GI Pipe Post
a. Materials
2" Ø GI Pipe Sch. 40 = 251.40 /lin.m.
1,050.00 / day
Cost = = 131.25 /lin.m.
8.00 lin.m./day
SUMMARY
12%VAT TOTAL
a. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 251.40 - 251.40 /lin.m.
b. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 131.25 15.75 147.00 /lin.m.
TOTAL DIRECT COST = 382.65 15.75 398.40 /lin.m.
Plus: 25% Indirect Cost = 95.66 11.48 107.14 /lin.m.
UNIT COST = 478.31 27.23 505.54 /lin.m.
say 506.00 /lin.m.
2. 3/4"ø GI Pipe Post
a. Materials
3/4" Ø GI Pipe Sch. 40 = 161.40 /lin.m.
1,050.00 / day
Cost = = 131.25 /lin.m.
8.00 lin.m./day
SUMMARY
12%VAT TOTAL
a. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 161.40 - 161.40 /lin.m.
b. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 131.25 15.75 147.00 /lin.m.
TOTAL DIRECT COST = 292.65 15.75 308.40 /lin.m.
Plus: 25% Indirect Cost = 73.16 8.78 81.94 /lin.m.
UNIT COST = 365.81 24.53 390.34 /lin.m.
say 391.00 /lin.m.
Page 43
DERIVATION OF UNIT COST
(ABC/EPC/UCD)
PROPOSED TENNIS COURT PERIMETER FENCE
I. DAILY RATES TO BE USED
2,886.00 /hr.
Cost = = 96.20 /m3
30 m3/hr
Plus: 25% OCM & Profit = 24.05 /m3
12% VAT (Equipment) = 11.54 /m3
12% VAT (OCM & Profit) = 2.89 /m3
UNIT COST = 134.68 /m3
say 134.70 /m3
Page 44
DERIVATION OF UNIT COST
(FORCE ACCOUNT WORKS)
2. Form Lumber
Hauling from Source to Dumpsite
AHD = 18.35 kms. Speed (kph)
with Load
Type of Road : Type I = 16.00 kms. 35.00
: Type II = 2.00 kms. 25.00
: Type III = - kms. 30.00
: Type IV = - kms. 20.00
: Type V (Manual Hauling) = 0.35 kms. 2.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x 558.75 /day = 2,793.75
Base Cost = 55.00 /bd.ft.
Capacity of Truck = 4000 bd.ft./trip
Capability of five (5) Laborers
Loading = 4000 bd.ft/hr
Unloading = 4000 bd.ft/hr
a. Hauling from Source To Dump Site
Cycle Time
with load = 16.00 kms. / 35.00 km./hr. = 0.46
T-I
without load = 16.00 kms. / 45.00 km./hr. = 0.36
with load = 2.00 kms. / 25.00 km./hr. = 0.08
T-II
without load = 2.00 kms. / 35.00 km./hr. = 0.06
with load = - kms. / 30.00 km./hr. = -
T-III
without load = - kms. / 35.00 km./hr. = -
with load = - kms. / 20.00 km./hr. = -
T-IV
without load = - kms. / 25.00 km./hr. = -
Loading = 4000 bd.ft./trip / 4000 bd.ft/hr = 1.00
Unloading = 4000 bd.ft./trip / 4000 bd.ft/hr = 1.00
total time = 2.95
LABOR COST:
809.97 /day x 2.95 hrs/trip
Driver = = 0.07 /bd.ft.
8 hrs/day x 4,000.00 bd.ft./trip
2,793.75 /day x 2.95 hrs/trip
5 - Laborer = = 0.26 /bd.ft.
8 hrs/day x 4000 bd.ft./trip
Labor Cost = 0.33 /bd.ft.
EQUIPMENT:
35.00 lit/hr x 0.95 hrs/trip x 35 /liter
Fuel = = 0.29
4000 bd.ft./trip
121.69 /hr. x 2.95 hrs/trip
Depreciation = = 0.09
4000 bd.ft./trip
182.54 /hr. x 2.95 hrs/trip
Spare Parts = = 0.13
4000 bd.ft./trip
note: Time for Loading & Unloading and Manual Hauling were excluded from the fuel consumption.
Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 558.75 /day
Capability : 25 bd.ft./trip
Cycle Time
with load = 0.35 kms. / 2.00 km./hr. = 0.18
T-V
without load = 0.35 kms. / 5.00 km./hr. = 0.07
total time = 0.25
558.75 /day x 0.25 hrs/trip
Manual Hauling = = 0.68 /bd.ft.
8 hrs/day x 25 bd.ft./trip
SUMMARY:
Base Cost = 55.00 /bd.ft.
Labor Cost = 1.02 /bd.ft.
Fuel Cost = 0.29 /bd.ft.
Depreciation = 0.09 /bd.ft.
Spare Parts = 0.13 /bd.ft.
TOTAL = 56.53 /bd.ft.
5. Plain GI Sheet
Hauling from Quarry Site to Dumpsite
AHD = 18.35 kms. Speed (kph)
with Load
Type of Road : Type I = 16.00 kms. 35.00
: Type II = 2.00 kms. 25.00
: Type III = - kms. 30.00
: Type IV = - kms. 20.00
: Type V (Manual Hauling) = 0.35 kms. 2.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x 558.75 /day = 2,793.75
Base Cost = 65.00 /lin.m.
Capacity of Truck = 6000 lin.m./trip
Capability of five (5) Laborers
Loading = 6000 lin.m./hr.
Unloading = 6000 lin.m./hr.
a. Hauling from Source To Dump Site
Cycle Time
with load = 16.00 kms. / 35.00 km./hr. = 0.46
T-I
without load = 16.00 kms. / 45.00 km./hr. = 0.36
with load = 2.00 kms. / 25.00 km./hr. = 0.08
T-II
without load = 2.00 kms. / 35.00 km./hr. = 0.06
with load = - kms. / 30.00 km./hr. = -
T-III
without load = - kms. / 35.00 km./hr. = -
with load = - kms. / 20.00 km./hr. = -
T-IV
without load = - kms. / 25.00 km./hr. = -
Loading = 6000 lin.m./trip / 6000 lin.m./hr. = 1.00
Unloading = 6000 lin.m./trip / 6000 lin.m./hr. = 1.00
total time = 2.95
LABOR COST:
809.97 /day x 2.95 hrs/trip
Driver = = 0.05 /lin.m.
8 hrs/day x 6,000.00 lin.m./trip
2,793.75 /day x 2.95 hrs/trip
5 - Laborer = = 0.17 /lin.m.
8 hrs/day x 6000 lin.m./trip
Labor Cost = 0.22 /lin.m.
EQUIPMENT:
35.00 lit/hr x 0.95 hrs/trip x 35 /liter
Fuel = = 0.19
6000 lin.m./trip
121.69 /hr. x 2.95 hrs/trip
Depreciation = = 0.06
6000 lin.m./trip
182.54 /hr. x 2.95 hrs/trip
Spare Parts = = 0.09
6000 lin.m./trip
note: Time for Loading & Unloading and Manual Hauling were excluded from the fuel consumption.
Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 558.75 /day
Capability : 25 lin.m./day
Cycle Time
with load = 0.35 kms. / 2.00 km./hr. = 0.18
T-V
without load = 0.35 kms. / 5.00 km./hr. = 0.07
total time = 0.25
558.75 /day x 0.25 hrs/trip
Manual Hauling = = 0.68 /lin.m.
8 hrs/day x 25 lin.m./day
SUMMARY:
Base Cost = 65.00 /lin.m.
Labor Cost = 0.91 /lin.m.
Fuel Cost = 0.19 /lin.m.
Depreciation = 0.06 /lin.m.
Spare Parts = 0.09 /lin.m.
TOTAL = 66.25 /lin.m.
b. Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 2.09 /cu.m.
8 hrs/day x 55 cu. m./hr.
558.75 /day
Laborer = = 1.27 /cu.m.
8 hrs/day x 55 cu. m./hr.
Labor Cost = 3.36 /cu.m.
EQUIPMENT:
9.00 lit/hr x 35 /liter
Fuel = = 5.73 /cu.m.
55 cu. m./hr.
293.64 /hr.
Depreciation = = 5.34 /cu.m.
55 cu. m./hr.
440.45 /hr.
Spare Parts = = 8.01 /cu.m.
55 cu. m./hr.
c. Hauling
c.1. Hauling from Quarry Site to Dumpsite
AHD = 18.35 kms. Speed (kph)
with Load
Type of Road : Type I = 16.00 kms. 35.00
: Type II = 2.00 kms. 25.00
: Type III = - kms. 30.00
: Type IV = - kms. 20.00
: Type V (Manual Hauling) = 0.35 kms. 2.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 342.25 /hr.
Labor per day = 5 - Laborers x 558.75 /day = 2,793.75
Base Cost = 120.00 /cu.m.
Capacity of Truck = 4 cu.m./trip
Capability of five (5) Laborers
Cycle Time
with load = 16.00 kms. / 35.00 km./hr. = 0.46
T-I
without load = 16.00 kms. / 45.00 km./hr. = 0.36
with load = 2.00 kms. / 25.00 km./hr. = 0.08
T-II
without load = 2.00 kms. / 35.00 km./hr. = 0.06
with load = - kms. / 30.00 km./hr. = -
T-III
without load = - kms. / 35.00 km./hr. = -
with load = - kms. / 20.00 km./hr. = -
T-IV
without load = - kms. / 25.00 km./hr. = -
Loading, Unloading, Maneuvering, delays, etc. = 0.12
total time = 1.07
LABOR COST:
809.97 /day x 1.07 hrs/trip
Driver = = 26.99 /cu.m.
8 hrs/day x 4.00 cu.m./trip
2,793.75 /day x 1.07 hrs/trip
5 - Laborer = = 93.11 /cu.m.
8 hrs/day x 4 cu.m./trip
Labor Cost = 120.11 /cu.m.
EQUIPMENT:
15.00 lit/hr x 0.95 hrs/trip x 35 /liter
Fuel = = 124.67
4 cu.m./trip
136.90 /hr. x 1.07 hrs/trip
Depreciation = = 36.50
4 cu.m./trip
205.35 /hr. x 1.07 hrs/trip
Spare Parts = = 54.75
Spare Parts = = 54.75
4 cu.m./trip
7. Boulders
a. Quarrying (Manual)
utilize : 1 laborer
Capabilities = 2 cu.m./day
558.75 /day
Cost = = 279.38 /cu.m.
2.00 cu.m./day
b. Loading (Manual)
utilize : 5 laborer
Capabilities = 3 cu.m./hr.
2,793.75 /day
Cost = = 116.41 /cu.m.
3.00 cu.m./hr. x 8 hrs./day
c. Hauling
c.1. Hauling from Quarry Site to Dumpsite
AHD = 18.15 kms. Speed (kph)
with Load
Type of Road : Type I = 16.00 kms. 35.00
: Type II = 2.00 kms. 25.00
: Type III = - kms. 30.00
: Type IV = - kms. 20.00
: Type V (Manual Hauling) = 0.15 kms. 2.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x 558.75 /day = 2,793.75
Base Cost = 150.00 /cu.m.
Capacity of Truck = 4 cu.m./trip
Capability of five (5) Laborers
Cycle Time
with load = 16.00 kms. / 35.00 km./hr. = 0.46
T-I
without load = 16.00 kms. / 45.00 km./hr. = 0.36
with load = 2.00 kms. / 25.00 km./hr. = 0.08
T-II
without load = 2.00 kms. / 35.00 km./hr. = 0.06
with load = - kms. / 30.00 km./hr. = -
T-III
without load = - kms. / 35.00 km./hr. = -
with load = - kms. / 20.00 km./hr. = -
T-IV
without load = - kms. / 25.00 km./hr. = -
Loading, Unloading, Maneuvering, delays, etc. = 0.12
total time = 1.07
LABOR COST:
809.97 /day x 1.07 hrs/trip
Driver = = 26.99 /cu.m.
8 hrs/day x 4.00 cu.m./trip
2,793.75 /day x 1.07 hrs/trip
5 - Laborer = = 93.11 /cu.m.
8 hrs/day x 4 cu.m./trip
Labor Cost = 120.11 /cu.m.
EQUIPMENT:
35.00 lit/hr x 0.95 hrs/trip x 35 /liter
Fuel = = 290.89
4 cu.m./trip
121.69 /hr. x 1.07 hrs/trip
Depreciation = = 32.45
4 cu.m./trip
182.54 /hr. x 1.07 hrs/trip
Spare Parts = = 48.67
4 cu.m./trip
d. Unloading (Manual)
utilize : 5 laborer
Capabilities = 4 cu.m./hr.
2,793.75 /day
Cost = = 87.30 /cu.m.
4.00 cu.m./hr. x 8 hrs./day
SUMMARY:
Base Cost = 150.00 /cu.m.
Labor Cost = 847.65 /cu.m.
Fuel Cost = 290.89 /cu.m.
Depreciation = 32.45 /cu.m.
Spare Parts = 48.67 /cu.m.
TOTAL = 1,369.65 /cu.m.
SUMMARY:
Gabion Mattress
Base Cost = 2,500.00 /pc. = 2,800.00 /pc.
Labor Cost = 11.23 /pc. = 11.23 /pc.
Fuel Cost = 4.65 /pc. = 4.65 /pc.
Depreciation = 1.49 /pc. = 1.49 /pc.
Spare Parts = 2.24 /pc. = 2.24 /pc.
TOTAL = 2,519.62 /pc. = 2,819.62 /pc.
SUMMARY:
Coconet Vetiver Grass
Base Cost = 85.00 /sq.m. = 75.00 /sq.m.
Labor Cost = 0.79 /sq.m. = 0.79 /sq.m.
Fuel Cost = 0.19 /sq.m. = 0.19 /sq.m.
Depreciation = 0.06 /sq.m. = 0.06 /sq.m.
Spare Parts = 0.09 /sq.m. = 0.09 /sq.m.
TOTAL = 86.13 /sq.m. = 76.13 /sq.m.
SUMMARY:
2" GI Pipe 2" PVC Pipe
Base Cost = 250.00 /lin.m. = - /lin.m.
Labor Cost = 1.26 /lin.m. = 1.26 /lin.m.
Fuel Cost = 0.58 /lin.m. = 0.58 /lin.m.
Depreciation = 0.19 /lin.m. = 0.19 /lin.m.
Spare Parts = 0.28 /lin.m. = 0.28 /lin.m.
TOTAL = 252.31 /lin.m. = 2.31 /lin.m.
SUMMARY
b. Labor
b.1 Fabrication, Placing and Dismantling of Forms (Formworks)
Crew: 2 - Carpenter and 4 - Laborer
Capability = 3.5 cu.m./day
b.2 Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 8 - Laborers
Capability = 3.5 cu.m./day
LABOR
Position Rate /day Formworks Concreting Works
No. Cost No. Cost
Foreman 983.55 - 1.00 983.55
Carpenter 714.15 2.00 1,428.30 -
Mason 714.15 - 2.00 1,428.30
Steelman 714.15 - -
LE Operator 921.12 - 1.00 921.12
Laborer 558.75 4.00 2,235.00 8.00 4,470.00
Total Cost 3,663.30 7,802.97
Unit Cost 1,046.66 2,229.42
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
9.00 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.5
60 min./hr.
Fuel = 1.26 lit./hr. x 1.5 hr./cu.m. x 35 /liter = 66.15
Depreciation = 39.66 /hr. x 1.5 hr./cu.m. x = 59.48
Spare Parts = 59.48 /hr. x 1.5 hr./cu.m. x = 89.23
SUMMARY
a. Materials = 4,129.00 /cu.m.
b. Labor = 4,696.51 /cu.m.
c. Depreciation = 125.20 /cu.m.
d. Spare Parts = 187.80 /cu.m.
e. Fuel = 311.13 /cu.m.
UNIT COST = 9,449.65 /cu.m.
2. Class "A" Reinforced Concrete (211 kscm for Flume & Bridges incl. Pump House)
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 9.00 2,484.00 206.71 14.24 21.36 69.81
Sand 0.45 54.00 381.15 16.43 24.64 56.10
Gravel 0.90 108.00 804.20 32.85 49.28 112.20
Form Lumber 30.00 1,650.00 30.50 2.69 4.04 8.73
Plywood 1.50 1,275.00 33.64 2.15 3.23 6.98
CW Nails 1.20 108.00 0.94 0.07 0.10 0.09
Tie Wire 2.50 250.00 1.95 0.14 0.21 0.18
TOTAL 5,929.00 1,459.09 68.57 102.86 254.09
b. Labor
b.1 Fabrication, Placing and Dismantling of Forms (Formworks)
Crew: 2 - Carpenter and 4 - Laborer
Capability = 3.5 cu.m./day
b.2 Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 8 - Laborers
Capability = 3.5 cu.m./day
LABOR
Position Rate /day Formworks Concreting Works
No. Cost No. Cost
Foreman 983.55 - 1.00 983.55
Carpenter 714.15 2.00 1,428.30 -
Mason 714.15 - 2.00 1,428.30
Steelman 714.15 - -
LE Operator 921.12 - 1.00 921.12
Laborer 558.75 4.00 2,235.00 8.00 4,470.00
Total Cost 3,663.30 7,802.97
Unit Cost 1,046.66 2,229.42
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
9.00 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.5
60 min./hr.
Fuel = 1.26 lit./hr. x 1.5 hr./cu.m. x 35 /liter = 66.15
Depreciation = 39.66 /hr. x 1.5 hr./cu.m. x = 59.48
Spare Parts = 59.48 /hr. x 1.5 hr./cu.m. x = 89.23
SUMMARY
a. Materials = 5,929.00 /cu.m.
b. Labor = 4,735.17 /cu.m.
c. Depreciation = 128.05 /cu.m.
d. Spare Parts = 192.08 /cu.m.
e. Fuel = 320.24 /cu.m.
UNIT COST = 11,304.54 /cu.m.
3. Class "A" Reinforced Concrete (211 kscm for Siphon/Box Culvert & Other Structures)
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 9.00 2,484.00 206.71 14.24 21.36 69.81
Sand 0.45 54.00 381.15 16.43 24.64 56.10
Gravel 0.90 108.00 804.20 32.85 49.28 112.20
Form Lumber 25.00 1,375.00 25.42 2.24 3.37 7.27
Plywood 1.25 1,062.50 28.03 1.79 2.69 5.82
CW Nails 1.20 108.00 0.94 0.07 0.10 0.09
Tie Wire 2.00 200.00 1.56 0.11 0.17 0.14
TOTAL 5,391.50 1,448.01 67.73 101.60 251.43
b. Labor
b.1 Fabrication, Placing and Dismantling of Forms (Formworks)
Crew: 2 - Carpenter and 4 - Laborer
Capability = 3.5 cu.m./day
b.2 Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 8 - Laborers
Capability = 3.5 cu.m./day
LABOR
Position Rate /day Formworks Concreting Works
No. Cost No. Cost
Foreman 983.55 - 1.00 983.55
Carpenter 714.15 2.00 1,428.30 -
Mason 714.15 - 2.00 1,428.30
Steelman 714.15 - -
LE Operator 921.12 - 1.00 921.12
Laborer 558.75 4.00 2,235.00 8.00 4,470.00
Total Cost 3,663.30 7,802.97
Unit Cost 1,046.66 2,229.42
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
9.00 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.5
60 min./hr.
Fuel = 1.26 lit./hr. x 1.5 hr./cu.m. x 35 /liter = 66.15
Depreciation = 39.66 /hr. x 1.5 hr./cu.m. x = 59.48
Spare Parts = 59.48 /hr. x 1.5 hr./cu.m. x = 89.23
SUMMARY
a. Materials = 5,391.50 /cu.m.
b. Labor = 4,724.09 /cu.m.
c. Depreciation = 127.22 /cu.m.
d. Spare Parts = 190.83 /cu.m.
e. Fuel = 317.58 /cu.m.
UNIT COST = 10,751.21 /cu.m.
b. Labor
b.1 Fabrication, Placing and Dismantling of Forms (Formworks)
Crew: 2 - Carpenter and 4 - Laborer
Capability = 5 cu.m./day
b.2 Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 8 - Laborers
Capability = 5 cu.m./day
LABOR
Position Rate /day Formworks Concreting Works
No. Cost No. Cost
Foreman 983.55 - 1.00 983.55
Carpenter 714.15 2.00 1,428.30 -
Mason 714.15 - 2.00 1,428.30
Steelman 714.15 - -
LE Operator 921.12 - 1.00 921.12
Laborer 558.75 4.00 2,235.00 8.00 4,470.00
Total Cost 3,663.30 7,802.97
Unit Cost 732.66 1,560.59
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
7.00 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.17
60 min./hr.
Fuel = 1.26 lit./hr. x 1.17 hr./cu.m. x 35 /liter = 51.45
Depreciation = 39.66 /hr. x 1.17 hr./cu.m. x = 46.27
Spare Parts = 59.48 /hr. x 1.17 hr./cu.m. x = 69.40
SUMMARY
a. Materials = 2,409.50 /cu.m.
b. Labor = 3,776.36 /cu.m.
c. Depreciation = 112.55 /cu.m.
d. Spare Parts = 168.83 /cu.m.
e. Fuel = 294.22 /cu.m.
UNIT COST = 6,761.47 /cu.m.
b. Labor
b.1 Fabrication, Placing and Dismantling of Forms (Formworks)
Crew: 1 - Carpenter and 1 - Laborer
Capability = 4.5 cu.m./day
b.2 Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 8 - Laborers
Capability = 4.5 cu.m./day
LABOR
Position Rate /day Formworks Concreting Works
No. Cost No. Cost
Foreman 983.55 - 1.00 983.55
Carpenter 714.15 1.00 714.15 -
Mason 714.15 - 2.00 1,428.30
Steelman 714.15 - -
LE Operator 921.12 - 1.00 921.12
Laborer 558.75 1.00 558.75 8.00 4,470.00
Total Cost 1,272.90 7,802.97
Unit Cost 282.87 1,733.99
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
7.50 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.25
60 min./hr.
Fuel = 1.26 lit./hr. x 1.25 hr./cu.m. x 35 /liter = 55.13
Depreciation = 39.66 /hr. x 1.25 hr./cu.m. x = 49.57
Spare Parts = 59.48 /hr. x 1.25 hr./cu.m. x = 74.36
SUMMARY
a. Materials = 2,540.30 /cu.m.
b. Labor = 3,458.77 /cu.m.
c. Depreciation = 114.46 /cu.m.
d. Spare Parts = 171.69 /cu.m.
e. Fuel = 294.30 /cu.m.
UNIT COST = 6,579.51 /cu.m.
6. Lean concrete
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 5.00 1,380.00 114.84 7.91 11.86 38.79
Sand 0.50 60.00 423.50 18.25 27.38 62.33
Gravel 1.00 120.00 893.56 36.50 54.75 124.67
TOTAL 1,560.00 1,431.90 62.66 93.99 225.79
b. Labor
b.1 Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 8 - Laborers
Capability = 4.5 cu.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter 714.15 -
Mason 714.15 2.00 1,428.30
Steelman 714.15 -
LE Operator 921.12 1.00 921.12
Laborer 558.75 8.00 4,470.00
Total Cost 7,802.97
Unit Cost 1,733.99
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
5.00 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 0.83
60 min./hr.
Fuel = 1.26 lit./hr. x 0.83 hr./cu.m. x 35 /liter = 36.75
Depreciation = 39.66 /hr. x 0.83 hr./cu.m. x = 33.05
Spare Parts = 59.48 /hr. x 0.83 hr./cu.m. x = 49.57
SUMMARY
a. Materials = 1,560.00 /cu.m.
b. Labor = 3,165.89 /cu.m.
c. Depreciation = 95.71 /cu.m.
d. Spare Parts = 143.56 /cu.m.
e. Fuel = 262.54 /cu.m.
UNIT COST = 5,227.69 /cu.m.
SUMMARY
a. Materials = 55.00 /cu.m.
b. Labor = 0.78 /cu.m.
c. Depreciation = 0.06 /cu.m.
d. Spare Parts = 0.09 /cu.m.
e. Fuel = 0.07 /cu.m.
UNIT COST = 55.99 /cu.m.
SUMMARY
a. Materials = - /cu.m.
b. Labor = 15.91 /cu.m.
c. Depreciation = - /cu.m.
d. Spare Parts = - /cu.m.
e. Fuel = - /cu.m.
UNIT COST = 15.91 /cu.m.
C. RUBBLE MASONRY
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 4.50 1,242.00 103.35 7.12 10.68 34.91
Sand 0.23 27.00 190.57 8.21 12.32 28.05
Gravel 0.45 54.00 402.10 16.43 24.64 56.10
Plywood 2.45 2,082.50 54.95 3.52 5.28 11.40
Form Lumber 5.00 275.00 5.08 0.45 0.67 1.45
CW Nails 0.25 22.50 0.20 0.01 0.02 0.02
Boulder 0.95 142.50 805.26 30.82 46.24 276.34
TOTAL 3,845.50 1,561.52 66.56 99.84 408.28
b. Labor
Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 10 - Laborers
Capability = 5 cu.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter 714.15 -
Mason 714.15 2.00 1,428.30
Steelman 714.15 -
LE Operator 921.12 1.00 921.12
Laborer 558.75 10.00 5,587.50
Total Cost 8,920.47
Unit Cost 1,784.09
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
4.50 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 0.75
60 min./hr.
Fuel = 1.26 lit./hr. x 0.75 hr./cu.m. x 35 /liter = 33.08
Depreciation = 39.66 /hr. x 0.75 hr./cu.m. x = 29.74
Spare Parts = 59.48 /hr. x 0.75 hr./cu.m. x = 44.61
SUMMARY
a. Materials = 3,845.50 /cu.m.
b. Labor = 3,345.61 /cu.m.
c. Depreciation = 96.30 /cu.m.
d. Spare Parts = 144.46 /cu.m.
e. Fuel = 441.35 /cu.m.
UNIT COST = 7,873.22 /cu.m.
D. GROUTED RIPRAP
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 4.20 1,159.20 96.46 6.64 9.97 32.58
Sand 0.35 42.00 296.45 12.78 19.16 43.63
Gravel 0.05 6.00 44.68 1.83 2.74 6.23
Boulder 1.00 150.00 847.65 32.45 48.67 290.89
TOTAL 1,357.20 1,285.24 53.69 80.54 373.34
b. Labor
Concreting and Curing (Concreting Works)
Crew: 1 - Foreman, 2 - Mason, 1 - LE Operator & 10 - Laborers
Capability = 3.5 cu.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter 714.15 -
Mason 714.15 2.00 1,428.30
Steelman 714.15 -
LE Operator 921.12 1.00 921.12
Laborer 558.75 10.00 5,587.50
Total Cost 8,920.47
Unit Cost 2,548.71
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
4.20 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 0.7
60 min./hr.
Fuel = 1.26 lit./hr. x 0.7 hr./cu.m. x 35 /liter = 30.87
Depreciation = 39.66 /hr. x 0.7 hr./cu.m. x = 27.76
Spare Parts = 59.48 /hr. x 0.7 hr./cu.m. x = 41.64
SUMMARY
a. Materials = 1,357.20 /cu.m.
b. Labor = 3,833.94 /cu.m.
c. Depreciation = 81.45 /cu.m.
d. Spare Parts = 122.17 /cu.m.
e. Fuel = 404.21 /cu.m.
UNIT COST = 5,798.97 /cu.m.
E. BOULDER RIPRAP
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Gravel 0.10 12.00 89.36 3.65 5.48 12.47
Boulder 1.00 150.00 847.65 32.45 48.67 290.89
TOTAL 162.00 937.00 36.10 54.14 303.36
b. Labor
Laying of Boulders
Crew: 1 - Laborer
Capability = 1.5 cu.m./day
LABOR
Position Rate /day
No. Cost
Laborer 558.75 1.00 558.75
Total Cost 558.75
Unit Cost 372.50
SUMMARY
a. Materials = 162.00 /cu.m.
b. Labor = 1,309.50 /cu.m.
c. Depreciation = 36.10 /cu.m.
d. Spare Parts = 54.14 /cu.m.
e. Fuel = 303.36 /cu.m.
UNIT COST = 1,865.10 /cu.m.
F. FILTER DRAIN
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Sand 0.65 78.00 550.55 23.73 35.59 81.03
Gravel 0.35 42.00 312.75 12.78 19.16 43.63
TOTAL 120.00 863.30 36.50 54.75 124.67
b. Labor
Laying of Aggregates
Crew: 1 - Laborer
Capability = 5 cu.m./day
LABOR
Position Rate /day
No. Cost
Laborer 558.75 1.00 558.75
Total Cost 558.75
Unit Cost 111.75
SUMMARY
a. Materials = 120.00 /cu.m.
b. Labor = 975.05 /cu.m.
c. Depreciation = 36.50 /cu.m.
d. Spare Parts = 54.75 /cu.m.
e. Fuel = 124.67 /cu.m.
UNIT COST = 1,310.97 /cu.m.
G. GRAVEL BLANKET
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Gravel 1.00 120.00 893.56 36.50 54.75 124.67
TOTAL 120.00 893.56 36.50 54.75 124.67
b. Labor
Laying of Aggregates
Crew: 1 - Laborer
Capability = 5 cu.m./day
LABOR
Position Rate /day
No. Cost
Laborer 558.75 1.00 558.75
Total Cost 558.75
Unit Cost 111.75
SUMMARY
a. Materials = 120.00 /cu.m.
b. Labor = 1,005.31 /cu.m.
c. Depreciation = 36.50 /cu.m.
d. Spare Parts = 54.75 /cu.m.
e. Fuel = 124.67 /cu.m.
UNIT COST = 1,341.23 /cu.m.
b. Labor
b.1. Laying of CHB
Crew: 1 - Mason, 2 - Laborers
Capability = 14 cu.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 0.00 0.00
Carpenter 714.15 0.00 -
Mason 714.15 1.00 714.15
Steelman 714.15 0.00 -
LE Operator 921.12 0.00 0.00
Laborer 558.75 2.00 1,117.50
Total Cost 1,831.65
Unit Cost 130.83
b.2. Plastering
Crew: 1 - Mason, 1 - Laborers
Capability = 12 cu.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 0.00 0.00
Carpenter 714.15 0.00 -
Mason 714.15 1.00 714.15
Steelman 714.15 0.00 -
LE Operator 921.12 0.00 0.00
Laborer 558.75 1.00 558.75
Total Cost 1,272.90
Unit Cost 106.08
SUMMARY
a. Materials = 539.72 /cu.m.
b. Labor = 391.31 /cu.m.
c. Depreciation = 27.92 /cu.m.
d. Spare Parts = 24.18 /cu.m.
e. Fuel = 41.96 /cu.m.
UNIT COST = 1,025.09 /cu.m.
a.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 15 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 607.79
a.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
0.58 bag/pc x 10 min./bag
Time of Mixer/cu.m. = = 0.10
60 min./hr.
Fuel = 1.26 lit./hr. x 0.10 hr./pc. x 35 /liter = 4.26
Depreciation = 39.66 /hr. x 0.10 hr./pc. x = 3.83
Spare Parts = 59.48 /hr. x 0.10 hr./pc. x = 5.75
b. Installation
b.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 0.21 57.96 4.82 0.33 0.50 1.63
Sand 0.01 1.20 8.47 0.37 0.55 1.25
Gravel 0.02 2.40 17.87 0.73 1.10 2.49
RSB - - - - - -
Form Lumber 2.00 110.00 2.03 0.18 0.27 0.58
Tie Wire - - - - - -
CWN 0.20 18.00 0.16 0.01 0.02 0.01
TOTAL 189.56 33.35 1.62 2.43 5.97
b.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 16 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 569.80
b.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
0.21 bag/pc. x 10 min./bag
Time of Mixer/cu.m. = = 0.04
60 min./hr.
Fuel = 1.26 lit./hr. x 0.04 hr./pc. x 35 /liter = 1.54
Depreciation = 39.66 /hr. x 0.04 hr./pc. x = 1.39
Spare Parts = 59.48 /hr. x 0.04 hr./pc. x = 2.08
SUMMARY
a. Materials = 678.44 /pc.
b. Labor = 1,290.44 /pc.
c. Depreciation = 10.66 /pc.
d. Spare Parts = 15.97 /pc.
e. Fuel = 25.46 /pc.
UNIT COST = 2,020.97 /pc.
2. 46 cm Æ
a. Fabrication
a.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 1.22 336.72 28.02 1.93 2.89 9.46
Sand 0.05 6.00 42.35 1.83 2.74 6.23
Gravel 0.10 12.00 89.36 3.65 5.48 12.47
Pl. GI Sheet 0.19 12.35 0.17 0.04 0.01 0.02
RSB 7.72 424.60 6.03 0.44 0.66 0.55
Form Lumber 0.36 19.80 0.37 0.03 0.05 0.10
CW Nails 0.20 18.00 0.16 0.01 0.02 0.01
TOTAL 829.47 166.45 7.93 11.84 28.85
a.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 11 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 828.80
a.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
1.22 bag/pc x 10 min./bag
Time of Mixer/cu.m. = = 0.20
60 min./hr.
Fuel = 1.26 lit./hr. x 0.20 hr./pc. x 35 /liter = 8.97
Depreciation = 39.66 /hr. x 0.20 hr./pc. x = 8.06
Spare Parts = 59.48 /hr. x 0.20 hr./pc. x = 12.10
b. Installation
b.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 0.45 124.20 10.34 0.71 1.07 3.49
Sand 0.02 2.40 16.94 0.73 1.10 2.49
Gravel 0.04 4.80 35.74 1.46 2.19 4.99
RSB 3.65 200.75 2.85 0.21 0.31 0.26
Form Lumber 2.00 110.00 2.03 0.18 0.27 0.58
Tie Wire 0.05 5.00 0.04 0.00 0.00 0.00
CWN 0.20 18.00 0.16 0.01 0.02 0.01
TOTAL 465.15 68.10 3.30 4.96 11.83
b.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 14 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 651.20
b.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
0.45 bag/pc. x 10 min./bag
Time of Mixer/cu.m. = = 0.08
60 min./hr.
Fuel = 1.26 lit./hr. x 0.08 hr./pc. x 35 /liter = 3.31
Depreciation = 39.66 /hr. x 0.08 hr./pc. x = 2.97
Spare Parts = 59.48 /hr. x 0.08 hr./pc. x = 4.46
SUMMARY
a. Materials = 1,294.62 /pc.
b. Labor = 1,714.56 /pc.
c. Depreciation = 22.27 /pc.
d. Spare Parts = 33.36 /pc.
e. Fuel = 52.96 /pc.
UNIT COST = 3,117.75 /pc.
3. 61 cm Æ
a. Fabrication
a.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 1.82 502.32 41.80 2.88 4.32 14.12
Sand 0.08 9.60 67.76 2.92 4.38 9.97
Gravel 0.15 18.00 134.03 5.48 8.21 18.70
Pl. GI Sheet 0.24 15.60 0.22 0.05 0.01 0.02
RSB 9.77 537.35 7.63 0.56 0.83 0.70
Form Lumber 0.48 26.40 0.49 0.04 0.06 0.14
CW Nails 0.30 27.00 0.23 0.02 0.03 0.02
TOTAL 1,136.27 252.17 11.94 17.85 43.67
a.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 9 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 1,012.98
a.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
1.82 bag/pc x 10 min./bag
Time of Mixer/cu.m. = = 0.30
60 min./hr.
Fuel = 1.26 lit./hr. x 0.30 hr./pc. x 35 /liter = 13.38
Depreciation = 39.66 /hr. x 0.30 hr./pc. x = 12.03
Spare Parts = 59.48 /hr. x 0.30 hr./pc. x = 18.04
b. Installation
b.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 0.72 198.72 16.54 1.14 1.71 5.59
Sand 0.03 3.60 25.41 1.10 1.64 3.74
Gravel 0.06 7.20 53.61 2.19 3.29 7.48
RSB 4.52 248.60 3.53 0.26 0.39 0.32
Form Lumber 3.00 165.00 3.05 0.27 0.40 0.87
Tie Wire 0.10 10.00 0.08 0.01 0.01 0.01
CWN 0.10 9.00 0.08 0.01 0.01 0.01
TOTAL 642.12 102.30 4.96 7.44 18.02
b.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 12 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 759.74
b.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
0.72 bag/pc. x 10 min./bag
Time of Mixer/cu.m. = = 0.12
Time of Mixer/cu.m. = = 0.12
60 min./hr.
Fuel = 1.26 lit./hr. x 0.12 hr./pc. x 35 /liter = 5.29
Depreciation = 39.66 /hr. x 0.12 hr./pc. x = 4.76
Spare Parts = 59.48 /hr. x 0.12 hr./pc. x = 7.14
SUMMARY
a. Materials = 1,778.39 /pc.
b. Labor = 2,127.18 /pc.
c. Depreciation = 33.69 /pc.
d. Spare Parts = 50.47 /pc.
e. Fuel = 80.36 /pc.
UNIT COST = 4,070.09 /pc.
4. 76 cm Æ
a. Fabrication
a.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 2.52 695.52 57.88 3.99 5.98 19.55
Sand 0.11 13.20 93.17 4.02 6.02 13.71
Gravel 0.21 25.20 187.65 7.67 11.50 26.18
Pl. GI Sheet 0.30 19.50 0.27 0.06 0.02 0.03
RSB 23.22 1,277.10 18.14 1.32 1.98 1.66
Form Lumber 0.60 33.00 0.61 0.05 0.08 0.17
CW Nails 0.40 36.00 0.31 0.02 0.03 0.03
TOTAL 2,099.52 358.03 17.12 25.62 61.33
a.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 6 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 1,519.48
a.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
2.52 bag/pc x 10 min./bag
Time of Mixer/cu.m. = = 0.42
60 min./hr.
Fuel = 1.26 lit./hr. x 0.42 hr./pc. x 35 /liter = 18.52
Depreciation = 39.66 /hr. x 0.42 hr./pc. x = 16.66
Spare Parts = 59.48 /hr. x 0.42 hr./pc. x = 24.98
b. Installation
b.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 0.93 256.68 21.36 1.47 2.21 7.21
Sand 0.04 4.80 33.88 1.46 2.19 4.99
Gravel 0.08 9.60 71.48 2.92 4.38 9.97
RSB 5.26 289.30 4.11 0.30 0.45 0.38
Form Lumber 3.00 165.00 3.05 0.27 0.40 0.87
Tie Wire 0.08 8.00 0.06 0.00 0.01 0.01
CWN 0.30 27.00 0.23 0.02 0.03 0.02
TOTAL 760.38 134.18 6.44 9.66 23.45
b.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 10 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 911.69
b.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
0.93 bag/pc. x 10 min./bag
Time of Mixer/cu.m. = = 0.16
60 min./hr.
Fuel = 1.26 lit./hr. x 0.16 hr./pc. x 35 /liter = 6.84
Depreciation = 39.66 /hr. x 0.16 hr./pc. x = 6.15
Spare Parts = 59.48 /hr. x 0.16 hr./pc. x = 9.22
SUMMARY
a. Materials = 2,859.90 /pc.
b. Labor = 2,923.37 /pc.
c. Depreciation = 46.37 /pc.
d. Spare Parts = 69.48 /pc.
e. Fuel = 110.14 /pc.
UNIT COST = 6,009.25 /pc.
5. 91 cm Æ
a. Fabrication
a.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 3.33 919.08 76.48 5.27 7.90 25.83
Sand 0.14 16.80 118.58 5.11 7.67 17.45
Gravel 0.28 33.60 250.20 10.22 15.33 34.91
Pl. GI Sheet 0.34 22.10 0.31 0.07 0.02 0.03
RSB 50.43 2,773.65 39.39 2.87 4.31 3.60
Form Lumber 0.72 39.60 0.73 0.06 0.10 0.21
CW Nails 0.50 45.00 0.39 0.03 0.04 0.04
TOTAL 3,849.83 486.08 23.63 35.36 82.07
a.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 5 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 1,823.37
a.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
3.33 bag/pc x 10 min./bag
Time of Mixer/cu.m. = = 0.56
60 min./hr.
Fuel = 1.26 lit./hr. x 0.56 hr./pc. x 35 /liter = 24.48
Depreciation = 39.66 /hr. x 0.56 hr./pc. x = 22.01
Spare Parts = 59.48 /hr. x 0.56 hr./pc. x = 33.01
b. Installation
b.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 1.11 306.36 25.49 1.76 2.63 8.61
Sand 0.05 6.00 42.35 1.83 2.74 6.23
Gravel 0.10 12.00 89.36 3.65 5.48 12.47
RSB 6.01 330.55 4.69 0.34 0.51 0.43
Form Lumber 4.00 220.00 4.07 0.36 0.54 1.16
Tie Wire 0.09 9.00 0.07 0.01 0.01 0.01
CWN 0.40 36.00 0.31 0.02 0.03 0.03
TOTAL 919.91 166.34 7.96 11.94 28.94
b.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 8 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 1,139.61
b.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
1.11 bag/pc. x 10 min./bag
Time of Mixer/cu.m. = = 0.19
60 min./hr.
Fuel = 1.26 lit./hr. x 0.19 hr./pc. x 35 /liter = 8.16
Depreciation = 39.66 /hr. x 0.19 hr./pc. x = 7.34
Spare Parts = 59.48 /hr. x 0.19 hr./pc. x = 11.00
SUMMARY
a. Materials = 4,769.74 /pc.
b. Labor = 3,615.40 /pc.
c. Depreciation = 60.93 /pc.
d. Spare Parts = 91.32 /pc.
e. Fuel = 143.64 /pc.
UNIT COST = 8,681.04 /pc.
6. 122 cm Æ
a. Fabrication
a.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 4.28 1,181.28 98.30 6.77 10.16 33.20
Sand 0.18 21.60 152.46 6.57 9.86 22.44
Gravel 0.36 43.20 321.68 13.14 19.71 44.88
Pl. GI Sheet 0.40 26.00 0.36 0.08 0.02 0.04
RSB 60.84 3,346.20 47.52 3.46 5.20 4.35
Form Lumber 0.84 46.20 0.85 0.08 0.11 0.24
CW Nails 0.60 54.00 0.47 0.03 0.05 0.04
TOTAL 4,718.48 621.65 30.13 45.11 105.19
a.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 3 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 3,038.95
a.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
4.28 bag/pc x 10 min./bag
Time of Mixer/cu.m. = = 0.71
60 min./hr.
Fuel = 1.26 lit./hr. x 0.71 hr./pc. x 35 /liter = 31.46
Depreciation = 39.66 /hr. x 0.71 hr./pc. x = 28.29
Spare Parts = 59.48 /hr. x 0.71 hr./pc. x = 42.43
b. Installation
b.1. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per cubic meter
Cement 1.32 364.32 30.32 2.09 3.13 10.24
Sand 0.06 7.20 50.82 2.19 3.29 7.48
Gravel 0.12 14.40 107.23 4.38 6.57 14.96
RSB 6.79 373.45 5.30 0.39 0.58 0.49
Form Lumber 4.00 220.00 4.07 0.36 0.54 1.16
Tie Wire 0.10 10.00 0.08 0.01 0.01 0.01
CWN 0.40 36.00 0.31 0.02 0.03 0.03
TOTAL 1,025.37 198.13 9.43 14.15 34.36
b.2. Labor
Crew: 1 - Foreman, 2 - Mason & 12 - Laborers
Capability = 6 pcs./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter/Steelman 714.15 1.00 714.15
Mason 714.15 1.00 714.15
LE Operator 921.12 0.00 0.00
Laborer 558.75 12.00 6,705.00
Total Cost 9,116.85
Unit Cost 1,519.48
b.3. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
1.32 bag/pc. x 10 min./bag
Time of Mixer/cu.m. = = 0.22
60 min./hr.
Fuel = 1.26 lit./hr. x 0.22 hr./pc. x 35 /liter = 9.70
Depreciation = 39.66 /hr. x 0.22 hr./pc. x = 8.72
Spare Parts = 59.48 /hr. x 0.22 hr./pc. x = 13.09
SUMMARY
a. Materials = 5,743.85 /pc.
b. Labor = 5,378.20 /pc.
c. Depreciation = 76.58 /pc.
d. Spare Parts = 114.77 /pc.
e. Fuel = 180.71 /pc.
UNIT COST = 11,494.11 /pc.
b. Labor
b.1. Laying of CHB
Crew: 1 - Foreman & 4 - Laborers
Capability = 12 cu.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter 714.15 0.00 -
Mason 714.15 0.00 0.00
Steelman 714.15 0.00 -
LE Operator 921.12 0.00 0.00
Laborer 558.75 4.00 2,235.00
Total Cost 3,218.55
Unit Cost 268.21
SUMMARY
a. Materials = 1,430.00 /cu.m.
b. Labor = 1,121.71 /cu.m.
c. Depreciation = 34.79 /cu.m.
d. Spare Parts = 49.44 /cu.m.
e. Fuel = 292.03 /cu.m.
UNIT COST = 2,927.97 /cu.m.
b. Labor
b.1. Laying of CHB
Crew: 1 - Foreman & 4 - Laborers
Capability = 12 cu.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter 714.15 0.00 -
Mason 714.15 0.00 0.00
Steelman 714.15 0.00 -
LE Operator 921.12 0.00 0.00
Laborer 558.75 4.00 2,235.00
Total Cost 3,218.55
Unit Cost 268.21
SUMMARY
a. Materials = 964.00 /cu.m.
b. Labor = 1,119.24 /cu.m.
c. Depreciation = 33.77 /cu.m.
d. Spare Parts = 49.11 /cu.m.
e. Fuel = 290.96 /cu.m.
UNIT COST = 2,457.08 /cu.m.
L. SLOPE PROTECTION
1. Erosion Control Net
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per square meter
Coconet CGN 40 1.000 85.00 0.79 0.19 0.06 0.09
Bamboo Pegs 3.000 5.00 - - - -
TOTAL 90.00 0.79 0.19 0.06 0.09
b. Labor
b.1. Laying of CHB
Crew: 1 - Foreman & 8 - Laborers
Capability = 400 sq.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter 714.15 0.00 -
Mason 714.15 0.00 0.00
Steelman 714.15 0.00 -
LE Operator 921.12 0.00 0.00
Laborer 558.75 8.00 4,470.00
Total Cost 5,453.55
Unit Cost 13.63
SUMMARY
a. Materials = 90.00 /cu.m.
b. Labor = 14.42 /cu.m.
c. Depreciation = 0.19 /cu.m.
d. Spare Parts = 0.06 /cu.m.
e. Fuel = 0.09 /cu.m.
UNIT COST = 104.77 /cu.m.
2. Vetiber Grass
a. Materials
Materials
Description Base Cost Labor Depreciation Spare Parts Fuel
per square meter
Vetiver Grass 1.000 75.00 0.79 0.19 0.06 0.09
TOTAL 75.00 0.79 0.19 0.06 0.09
b. Labor
b.1. Laying of CHB
Crew: 1 - Foreman & 8 - Laborers
Capability = 400 sq.m./day
LABOR
Position Rate /day Concreting Works
No. Cost
Foreman 983.55 1.00 983.55
Carpenter 714.15 0.00 -
Mason 714.15 0.00 0.00
Steelman 714.15 0.00 -
LE Operator 921.12 0.00 0.00
Laborer 558.75 8.00 4,470.00
Total Cost 5,453.55
Unit Cost 13.63
b.3. Equipment
utilize : Water Truck
rental = 825.91 /hr.
1.00 sq.m./sq.m. x 0.1 min./sq.m.
Time of Mixer/cu.m. = = 0.002
60 min./hr.
Fuel = 8.00 lit./hr. x 0.002 hr./pc. x 35 /liter = 0.47
Depreciation = 330.36 /hr. x 0.002 hr./pc. x = 0.55
Spare Parts = 495.55 /hr. x 0.002 hr./pc. x = 0.83
SUMMARY
a. Materials = 75.00 /cu.m.
b. Labor = 14.42 /cu.m.
c. Depreciation = 0.74 /cu.m.
d. Spare Parts = 0.89 /cu.m.
e. Fuel = 0.56 /cu.m.
UNIT COST = 91.61 /cu.m.
SUMMARY
a. Materials = - /cu.m.
b. Labor = 1,753.95 /cu.m.
c. Depreciation = - /cu.m.
d. Spare Parts = - /cu.m.
e. Fuel = - /cu.m.
UNIT COST = 1,753.95 /cu.m.
SUMMARY
a. Materials = - /cu.m.
b. Labor = 3,507.90 /cu.m.
c. Depreciation = - /cu.m.
d. Spare Parts = - /cu.m.
e. Fuel = - /cu.m.
UNIT COST = 3,507.90 /cu.m.
SG
14
11
10
10
9
9
7
6
5
5
5
1
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/bag
/bag
/bag
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/bd.ft.
/bd.ft.
/bd.ft.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/pc.
/pc.
/pc.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/kg.
/kg.
/kg.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/lin.m.
/lin.m.
/lin.m.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/cu.m.
/cu.m.
/cu.m.
/cu.m.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/cu.m.
/cu.m.
/cu.m.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/pc.
/pc.
/pc.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/pc.
/pc.
/pc.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/sq.m.
/sq.m.
/sq.m.
hrs./trip
hrs./trip
hrs./trip
Speed (kph)
w/o Load
45.00
35.00
35.00
25.00
5.00
2,793.75 /day
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
hrs./trip
/lin.m.
/lin.m.
/lin.m.
hrs./trip
hrs./trip
hrs./trip
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./cu.m.
/cu.m.
/cu.m.
/cu.m.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
hr./pc.
/pc.
/pc.
/pc.
DERIVATION OF UNIT COST
(FORCE ACCOUNT WORKS)
SUMMARY
a. Materials = 150,000.00
b. Labor = 706,394.13
c. Depreciation = 66,888.81
d. Spare Parts = 100,333.21
e. Fuel = 66,525.00
UNIT COST = 1,090,141.14 (lump sum)
2. Dewatering
utilize : 5 -5" Æ Centrifugal Pump
rental = 49.00 /hr.
assume : 60 days continuous dewatering works (24 hrs. operation).
a. Labor
2-LE Operator = 1,842.24 /day x 60 days = 110,534.40
Labor Cost = 110,534.40
b. Equipment
Fuel = 5.00 lit./hr. x 1,080 hrs. x 35.00 /lit. = 189,000.00
Depreciation = 98.00 /hr. x 1,440 hrs. = 141,120.00
Spare Parts = 147.00 /hr. x 1,440 hrs. = 211,680.00
SUMMARY
a. Materials = 21,250.00
b. Labor = 234,130.05
c. Depreciation = 255,344.64
d. Spare Parts = 383,016.96
e. Fuel = 361,200.00
UNIT COST = 1,254,941.65 (lump sum)
C. STRUCTURE EXCAVATION
1. Common Materials
a. Using Dozer
utilized = 160 HP Dozer
production = 25 cu.m./hr.
rental = 1,303.34 /hr.
LABOR COST:
921.12 /day
HE Operator = = 4.61 /cu.m.
25 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 2.79 /cu.m.
25 cu.m./hr. x 8 hrs/day
Labor Cost = 7.40 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35.00 /lit.
Fuel = = 23.80 /cu.m.
25 cu.m./hr.
521.34 /hr.
Depreciation = = 20.85 /cu.m.
25 cu.m./hr.
782.00 /hr.
Spare Parts = = 31.28 /cu.m.
25 cu.m./hr.
SUMMARY
a. Labor = 7.40 /cu.m.
b. Depreciation = 20.85 /cu.m.
c. Spare Parts = 31.28 /cu.m.
d. Fuel = 23.80 /cu.m.
UNIT COST = 83.33 /cu.m.
b. Using Backhoe
utilized = 1.0 cu.m. bucket Backhoe
production = 30 cu.m./hr.
rental = 1,308.40 /hr.
LABOR COST:
921.12 /day
HE Operator = = 3.84 /cu.m.
30 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 2.33 /cu.m.
30 cu.m./hr. x 8 hrs/day
Labor Cost = 6.17 /cu.m.
EQUIPMENT:
12.00 lit/hr x 35.00 /lit.
Fuel = = 14.00 /cu.m.
30 cu.m./hr.
523.36 /hr.
Depreciation = = 17.45 /cu.m.
30 cu.m./hr.
785.04 /hr.
Spare Parts = = 26.17 /cu.m.
30 cu.m./hr.
SUMMARY
a. Labor = 6.17 /cu.m.
b. Depreciation = 17.45 /cu.m.
c. Spare Parts = 26.17 /cu.m.
d. Fuel = 14.00 /cu.m.
UNIT COST = 63.78 /cu.m.
c. by Manual
utilize : 1 laborer
Capabilities = 2 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 279.38 /cu.m.
2.00 cu.m./day
UNIT COST = 279.38 /cu.m.
2. Indurated Materials
a. Using Dozer
utilized = 160 HP Dozer
production = 15 cu.m./hr.
rental = 1,303.34 /hr.
LABOR COST:
921.12 /day
HE Operator = = 7.68 /cu.m.
15 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 4.66 /cu.m.
15 cu.m./hr. x 8 hrs/day
Labor Cost = 12.33 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35.00 /lit.
Fuel = = 39.67 /cu.m.
15 cu.m./hr.
521.34 /hr.
Depreciation = = 34.76 /cu.m.
15 cu.m./hr.
782.00 /hr.
Spare Parts = = 52.13 /cu.m.
15 cu.m./hr.
SUMMARY
a. Labor = 12.33 /cu.m.
b. Depreciation = 34.76 /cu.m.
c. Spare Parts = 52.13 /cu.m.
d. Fuel = 39.67 /cu.m.
UNIT COST = 138.89 /cu.m.
b. Using Backhoe
utilized = 1.0 cu.m. bucket Backhoe
production = 15 cu.m./hr.
rental = 1,308.40 /hr.
LABOR COST:
921.12 /day
HE Operator = = 7.68 /cu.m.
15 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 4.66 /cu.m.
15 cu.m./hr. x 8 hrs/day
Labor Cost = 12.33 /cu.m.
EQUIPMENT:
12.00 lit/hr x 35.00 /lit.
Fuel = = 28.00 /cu.m.
15 cu.m./hr.
523.36 /hr.
Depreciation = = 34.89 /cu.m.
15 cu.m./hr.
785.04 /hr.
Spare Parts = = 52.34 /cu.m.
15 cu.m./hr.
SUMMARY
a. Labor = 12.33 /cu.m.
b. Depreciation = 34.89 /cu.m.
c. Spare Parts = 52.34 /cu.m.
d. Fuel = 28.00 /cu.m.
UNIT COST = 127.56 /cu.m.
c. by Manual
utilize : 1 laborer
Capabilities = 1.25 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 447.00 /cu.m.
1.25 cu.m./day
UNIT COST = 447.00 /cu.m.
3. Solid Rocks
a. by Manual
utilize : 1 laborer
Capabilities = 0.2 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 2,793.75 /cu.m.
0.20 cu.m./day
UNIT COST = 2,793.75 /cu.m.
a.2 Mocking
utilized = 1.0 cu.m. bucket Backhoe
production = 20 cu.m./hr.
rental = 1,308.40 /hr.
LABOR COST:
= 921.12 /day = 5.76
HE Operator
20 cu.m./hr. x 8 hrs/day
= 558.75 /day = 3.49
Helper
20 cu.m./hr. x 8 hrs/day
Labor Cost = 9.25
EQUIPMENT:
12.00 lit/hr x 35.00 /lit.
Fuel = = 21.00
20 cu.m./hr.
523.36 /hr.
Depreciation = = 26.17
20 cu.m./hr.
785.04 /hr.
Spare Parts = = 39.25
20 cu.m./hr.
SUMMARY
a. Materials = 458.82 /cu.m.
b. Labor = 164.96 /cu.m.
c. Depreciation = 63.08 /cu.m.
d. Spare Parts = 94.62 /cu.m.
e. Fuel = 71.33 /cu.m.
UNIT COST = 852.82 /cu.m.
D. CANAL EXCAVATION
1. Common Materials
a. Using Dozer
utilized = 160 HP Dozer
production = 40 cu.m./hr.
rental = 1,303.34 /hr.
LABOR COST:
921.12 /day
HE Operator = = 2.88 /cu.m.
40 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 1.75 /cu.m.
40 cu.m./hr. x 8 hrs/day
Labor Cost = 4.62 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35.00 /lit.
Fuel = = 14.88 /cu.m.
40 cu.m./hr.
521.34 /hr.
Depreciation = = 13.03 /cu.m.
40 cu.m./hr.
782.00 /hr.
Spare Parts = = 19.55 /cu.m.
40 cu.m./hr.
SUMMARY
a. Labor = 4.62 /cu.m.
b. Depreciation = 13.03 /cu.m.
c. Spare Parts = 19.55 /cu.m.
d. Fuel = 14.88 /cu.m.
UNIT COST = 52.08 /cu.m.
b. Using Backhoe
utilized = 1.0 cu.m. bucket Backhoe
production = 40 cu.m./hr.
rental = 1,308.40 /hr.
LABOR COST:
921.12 /day
HE Operator = = 2.88 /cu.m.
40 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 1.75 /cu.m.
40 cu.m./hr. x 8 hrs/day
Labor Cost = 4.62 /cu.m.
EQUIPMENT:
12.00 lit/hr x 35.00 /lit.
Fuel = = 10.50 /cu.m.
40 cu.m./hr.
523.36 /hr.
Depreciation = = 13.08 /cu.m.
40 cu.m./hr.
785.04 /hr.
Spare Parts = = 19.63 /cu.m.
Spare Parts = = 19.63 /cu.m.
40 cu.m./hr.
SUMMARY
a. Labor = 4.62 /cu.m.
b. Depreciation = 13.08 /cu.m.
c. Spare Parts = 19.63 /cu.m.
d. Fuel = 10.50 /cu.m.
UNIT COST = 47.83 /cu.m.
c. by Manual
utilize : 1 laborer
Capabilities = 2.5 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 223.50 /cu.m.
2.50 cu.m./day
UNIT COST = 223.50 /cu.m.
2. Indurated Materials
a. Using Dozer
utilized = 160 HP Dozer
production = 20 cu.m./hr.
rental = 1,303.34 /hr.
LABOR COST:
921.12 /day
HE Operator = = 5.76 /cu.m.
20 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 3.49 /cu.m.
20 cu.m./hr. x 8 hrs/day
Labor Cost = 9.25 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35.00 /lit.
Fuel = = 29.75 /cu.m.
20 cu.m./hr.
521.34 /hr.
Depreciation = = 26.07 /cu.m.
20 cu.m./hr.
782.00 /hr.
Spare Parts = = 39.10 /cu.m.
20 cu.m./hr.
SUMMARY
a. Labor = 9.25 /cu.m.
b. Depreciation = 26.07 /cu.m.
c. Spare Parts = 39.10 /cu.m.
d. Fuel = 29.75 /cu.m.
UNIT COST = 104.17 /cu.m.
b. Using Backhoe
utilized = 1.0 cu.m. bucket Backhoe
production = 25 cu.m./hr.
rental = 1,308.40 /hr.
LABOR COST:
921.12 /day
HE Operator = = 4.61 /cu.m.
25 cu.m./hr. x 8 hrs/day
558.75 /day
Helper = = 2.79 /cu.m.
25 cu.m./hr. x 8 hrs/day
Labor Cost = 7.40 /cu.m.
EQUIPMENT:
12.00 lit/hr x 35.00 /lit.
Fuel = = 16.80 /cu.m.
25 cu.m./hr.
523.36 /hr.
Depreciation = = 20.93 /cu.m.
25 cu.m./hr.
785.04 /hr.
Spare Parts = = 31.40 /cu.m.
Spare Parts = = 31.40 /cu.m.
25 cu.m./hr.
SUMMARY
a. Labor = 7.40 /cu.m.
b. Depreciation = 20.93 /cu.m.
c. Spare Parts = 31.40 /cu.m.
d. Fuel = 16.80 /cu.m.
UNIT COST = 76.54 /cu.m.
c. by Manual
utilize : 1 laborer
Capabilities = 1.5 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 372.50 /cu.m.
1.50 cu.m./day
UNIT COST = 372.50 /cu.m.
3. Solid Rocks
a. by Manual
utilize : 1 laborer
Capabilities = 0.3 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 1,862.50 /cu.m.
0.30 cu.m./day
UNIT COST = 1,862.50 /cu.m.
b. Loading
Utilized : 1.0 cu.m. Loader
Production : 50 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 2.30 /cu.m.
8 hrs/day x 50 cu. m./hr.
558.75 /day
Laborer = = 1.40 /cu.m.
8 hrs/day x 50 cu. m./hr.
Labor Cost = 3.70 /cu.m.
EQUIPMENT:
9.00 lit/hr x 35 /liter
Fuel = = 6.30 /cu.m.
50 cu. m./hr.
293.64 /hr.
Depreciation = = 5.87 /cu.m.
50 cu. m./hr.
440.45 /hr.
Spare Parts = = 8.81 /cu.m.
50 cu. m./hr.
c. Hauling
use : 4 cu. m./trip Dump Truck
rental = 342.25 /hr.
AHD = 6 kms.
Shrinkage Factor = 15%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 6 kms. / 20 km./hr. = 0.30 hrs./trip
without load = 6 kms. / 25 km./hr. = 0.24 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 0.66 hrs./trip
LABOR COST:
809.97 /day x 0.66 hrs/trip
Driver = = 19.55
8 hrs/day x 4 cu. m./trip x 85% s.f.
558.75 /day x 0.66 hrs/trip
Laborer = = 13.49
8 hrs/day x 4 cu. m./trip x 85% s.f.
Labor Cost = 33.04
EQUIPMENT:
15.00 lit/hr x 0.66 hrs/trip x 35 /liter
Fuel = = 101.40
4 cu. m./trip x 85% s.f.
136.90 /hr. x 0.66 hrs/trip
Depreciation = = 26.44
4 cu. m./trip x 85% s.f.
205.35 /hr. x 0.66 hrs/trip
Spare Parts = = 39.66
4 cu. m./trip x 85% s.f.
d. Spreading
Utilized : 160 HP Dozer
Production : 110 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.05 /cu.m.
8 hrs/day x 110 cu. m./hr.
558.75 /day
Laborer = = 0.63 /cu.m.
8 hrs/day x 110 cu. m./hr.
Labor Cost = 1.68 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35 /liter
Fuel = = 5.41 /cu.m.
110 cu. m./hr.
521.34 /hr.
Depreciation = = 4.74 /cu.m.
110 cu. m./hr.
782.00 /hr.
Spare Parts = = 7.11 /cu.m.
110 cu. m./hr.
e. Watering
Utilized : 5000 lit Water Truck
Production : 70 cu. m./hr.
Rental : 825.91 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.64 /cu.m.
8 hrs/day x 70 cu. m./hr.
558.75 /day
Laborer = = 1.00 /cu.m.
8 hrs/day x 70 cu. m./hr.
Labor Cost = 2.64 /cu.m.
EQUIPMENT:
8.00 lit/hr x 35 /liter
Fuel = = 4.00 /cu.m.
70 cu. m./hr.
330.36 /hr.
Depreciation = = 4.72 /cu.m.
70 cu. m./hr.
495.55 /hr.
Spare Parts = = 7.08 /cu.m.
70 cu. m./hr.
g. Compaction
Utilized : 8 Tons Road Roller
Production : 40 cu. m./hr.
Rental : 617.00 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 2.88 /cu.m.
8 hrs/day x 40 cu. m./hr.
558.75 /day
Laborer = = 1.75 /cu.m.
8 hrs/day x 40 cu. m./hr.
Labor Cost = 4.62 /cu.m.
EQUIPMENT:
8.50 lit/hr x 35 /liter
Fuel = = 7.44 /cu.m.
40 cu. m./hr.
246.80 /hr.
Depreciation = = 6.17 /cu.m.
40 cu. m./hr.
370.20 /hr.
Spare Parts = = 9.26 /cu.m.
40 cu. m./hr.
SUMMARY
a. Materials (Quarry Pit Fee) = 50.00 /cu.m.
b. Labor = 48.78 /cu.m.
c. Depreciation = 56.63 /cu.m.
d. Spare Parts = 84.95 /cu.m.
e. Fuel = 134.46 /cu.m.
UNIT COST = 374.81 /cu.m.
2. Overhaul
a. Loading
Utilized : 1.0 cu.m. Loader
Production : 50 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 2.30 /cu.m.
8 hrs/day x 50 cu. m./hr.
558.75 /day
Laborer = = 1.40 /cu.m.
8 hrs/day x 50 cu. m./hr.
Labor Cost = 3.70 /cu.m.
EQUIPMENT:
9.00 lit/hr x 35 /liter
Fuel = = 6.30 /cu.m.
50 cu. m./hr.
293.64 /hr.
Depreciation = = 5.87 /cu.m.
50 cu. m./hr.
440.45 /hr.
Spare Parts = = 8.81 /cu.m.
Spare Parts = = 8.81 /cu.m.
50 cu. m./hr.
b. Hauling
use : 4 cu. m./trip Dump Truck
rental = 342.25 /hr.
AHD = 0.6 kms.
Shrinkage Factor = 15%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 0.6 kms. / 20 km./hr. = 0.03 hrs./trip
without load = 0.6 kms. / 25 km./hr. = 0.02 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 0.17 hrs./trip
LABOR COST:
809.97 /day x 0.17 hrs/trip
Driver = = 5.08
8 hrs/day x 4 cu. m./trip x 85% s.f.
558.75 /day x 0.17 hrs/trip
Laborer = = 3.51
8 hrs/day x 4 cu. m./trip x 85% s.f.
Labor Cost = 8.59
EQUIPMENT:
15.00 lit/hr x 0.17 hrs/trip x 35 /liter
Fuel = = 26.35
4 cu. m./trip x 85% s.f.
136.90 /hr. x 0.17 hrs/trip
Depreciation = = 6.87
4 cu. m./trip x 85% s.f.
205.35 /hr. x 0.17 hrs/trip
Spare Parts = = 10.31
4 cu. m./trip x 85% s.f.
c. Spreading
Utilized : 160 HP Dozer
Production : 110 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.05 /cu.m.
8 hrs/day x 110 cu. m./hr.
558.75 /day
Laborer = = 0.63 /cu.m.
8 hrs/day x 110 cu. m./hr.
Labor Cost = 1.68 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35 /liter
Fuel = = 5.41 /cu.m.
110 cu. m./hr.
521.34 /hr.
Depreciation = = 4.74 /cu.m.
110 cu. m./hr.
782.00 /hr.
Spare Parts = = 7.11 /cu.m.
110 cu. m./hr.
d. Watering
Utilized : 5000 lit Water Truck
Production : 70 cu. m./hr.
Rental : 825.91 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.64 /cu.m.
8 hrs/day x 70 cu. m./hr.
558.75 /day
Laborer = = 1.00 /cu.m.
8 hrs/day x 70 cu. m./hr.
Labor Cost = 2.64 /cu.m.
EQUIPMENT:
8.00 lit/hr x 35 /liter
Fuel = = 4.00 /cu.m.
70 cu. m./hr.
330.36 /hr.
Depreciation = = 4.72 /cu.m.
70 cu. m./hr.
495.55 /hr.
Spare Parts = = 7.08 /cu.m.
70 cu. m./hr.
e. Compaction
Utilized : 8 Tons Road Roller
Production : 40 cu. m./hr.
Rental : 617.00 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 2.88 /cu.m.
8 hrs/day x 40 cu. m./hr.
558.75 /day
Laborer = = 1.75 /cu.m.
8 hrs/day x 40 cu. m./hr.
Labor Cost = 4.62 /cu.m.
EQUIPMENT:
8.50 lit/hr x 35 /liter
Fuel = = 7.44 /cu.m.
40 cu. m./hr.
246.80 /hr.
Depreciation = = 6.17 /cu.m.
40 cu. m./hr.
370.20 /hr.
Spare Parts = = 9.26 /cu.m.
40 cu. m./hr.
SUMMARY
a. Labor = 21.24 /cu.m.
b. Depreciation = 28.37 /cu.m.
c. Spare Parts = 42.56 /cu.m.
d. Fuel = 49.50 /cu.m.
UNIT COST = 141.67 /cu.m.
3. Side Borrow
Utilized : 160 HP Dozer
Production : 40 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 2.88 /cu.m.
8 hrs/day x 40 cu. m./hr.
558.75 /day
Laborer = = 1.75 /cu.m.
8 hrs/day x 40 cu. m./hr.
Labor Cost = 4.62 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35 /liter
Fuel = = 14.88 /cu.m.
40 cu. m./hr.
521.34 /hr.
Depreciation = = 13.03 /cu.m.
40 cu. m./hr.
782.00 /hr.
Spare Parts = = 19.55 /cu.m.
40 cu. m./hr.
SUMMARY
a. Labor = 4.62 /cu.m.
b. Depreciation = 13.03 /cu.m.
c. Spare Parts = 19.55 /cu.m.
d. Fuel = 14.88 /cu.m.
UNIT COST = 52.08 /cu.m.
F. STRUCTURE BACKFILL W/ COMPACTION
a. Mechanized
Utilized : 160 HP Dozer
Production : 70 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.64 /cu.m.
8 hrs/day x 70 cu. m./hr.
558.75 /day
Laborer = = 1.00 /cu.m.
8 hrs/day x 70 cu. m./hr.
Labor Cost = 2.64 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35 /liter
Fuel = = 8.50 /cu.m.
70 cu. m./hr.
521.34 /hr.
Depreciation = = 7.45 /cu.m.
70 cu. m./hr.
782.00 /hr.
Spare Parts = = 11.17 /cu.m.
70 cu. m./hr.
SUMMARY
a. Labor = 2.64 /cu.m.
b. Depreciation = 7.45 /cu.m.
c. Spare Parts = 11.17 /cu.m.
d. Fuel = 8.50 /cu.m.
SUB UNIT COST = 29.76 /cu.m.
2. by Manual
utilize : 1 laborer
Capabilities = 3 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 186.25 /cu.m.
3.00 cu.m./day
UNIT COST = 186.25 /cu.m.
b. Hauling
use : 4 cu. m./trip Dump Truck
rental = 342.25 /hr.
AHD = 1.5 kms.
Shrinkage Factor = 15%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 1.5 kms. / 20 km./hr. = 0.08 hrs./trip
without load = 1.5 kms. / 25 km./hr. = 0.06 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 0.25 hrs./trip
LABOR COST:
809.97 /day x 0.25 hrs/trip
Driver = = 7.49
8 hrs/day x 4 cu. m./trip x 85% s.f.
558.75 /day x 0.25 hrs/trip
Laborer = = 5.17
8 hrs/day x 4 cu. m./trip x 85% s.f.
Labor Cost = 12.66
EQUIPMENT:
15.00 lit/hr x 0.25 hrs/trip x 35 /liter
Fuel = = 38.86
4 cu. m./trip x 85% s.f.
136.90 /hr. x 0.25 hrs/trip
Depreciation = = 10.13
4 cu. m./trip x 85% s.f.
205.35 /hr. x 0.25 hrs/trip
Spare Parts = = 15.20
4 cu. m./trip x 85% s.f.
c. Spreading
Utilized : 160 HP Dozer
Production : 110 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.05 /cu.m.
8 hrs/day x 110 cu. m./hr.
558.75 /day
Laborer = = 0.63 /cu.m.
8 hrs/day x 110 cu. m./hr.
Labor Cost = 1.68 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35 /liter
Fuel = = 5.41 /cu.m.
110 cu. m./hr.
521.34 /hr.
Depreciation = = 4.74 /cu.m.
110 cu. m./hr.
782.00 /hr.
Spare Parts = = 7.11 /cu.m.
110 cu. m./hr.
SUMMARY
a. Labor = 18.05 /cu.m.
b. Depreciation = 20.75 /cu.m.
c. Spare Parts = 31.12 /cu.m.
d. Fuel = 50.57 /cu.m.
UNIT COST = 120.48 /cu.m.
H. CONCRETE DEMOLITION
1. Massive Concrete Slab Rental
Utilized : 1 - 600cfm Compressor= 252.40 /hr.
: 2 - Jackhammer = 201.20 /hr.
Total Rental/hr. = 453.60 /hr.
Production : 8 cu. m./hr.
LABOR COST:
2,763.36 /day
3- LE Operator = = 43.18 /cu.m.
3- LE Operator = = 43.18 /cu.m.
8 hrs/day x 8 cu. m./hr.
1,676.25 /day
3 - Laborer = = 26.19 /cu.m.
8 hrs/day x 8 cu. m./hr.
Labor Cost = 69.37 /cu.m.
EQUIPMENT:
5.50 lit/hr x 35 /liter
Fuel = = 24.06 /cu.m.
8 cu. m./hr.
181.44 /hr.
Depreciation = = 22.68 /cu.m.
8 cu. m./hr.
272.16 /hr.
Spare Parts = = 34.02 /cu.m.
8 cu. m./hr.
SUMMARY
a. Labor = 69.37 /cu.m.
b. Depreciation = 22.68 /cu.m.
c. Spare Parts = 34.02 /cu.m.
d. Fuel = 24.06 /cu.m.
SUB UNIT COST = 150.13 /cu.m.
2. by Manual
utilize : 1 laborer
Capabilities = 0.2 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 2,793.75 /cu.m.
0.20 cu.m./day
UNIT COST = 2,793.75 /cu.m.
2. by Manual
utilize : 1 laborer
Capabilities = 0.5 cu.m./day
daily rate = 558.75 /day
558.75 /day
Cost = = 1,117.50 /cu.m.
0.50 cu.m./day
UNIT COST = 1,117.50 /cu.m.
I. ROAD METALLING
a. Quarrying
Utilized : 160 HP Dozer
Production : 65 cu. m./hr.
Rental : 1,303.34 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.77 /cu.m.
8 hrs/day x 65 cu. m./hr.
558.75 /day
Laborer = = 1.07 /cu.m.
8 hrs/day x 65 cu. m./hr.
Labor Cost = 2.85 /cu.m.
EQUIPMENT:
17.00 lit/hr x 35 /liter
Fuel = = 9.15 /cu.m.
65 cu. m./hr.
521.34 /hr.
Depreciation = = 8.02 /cu.m.
65 cu. m./hr.
782.00 /hr.
Spare Parts = = 12.03 /cu.m.
65 cu. m./hr.
b. Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 2.09 /cu.m.
8 hrs/day x 55 cu. m./hr.
558.75 /day
Laborer = = 1.27 /cu.m.
8 hrs/day x 55 cu. m./hr.
Labor Cost = 3.36 /cu.m.
EQUIPMENT:
9.00 lit/hr x 35 /liter
Fuel = = 5.73 /cu.m.
55 cu. m./hr.
293.64 /hr.
Depreciation = = 5.34 /cu.m.
55 cu. m./hr.
440.45 /hr.
Spare Parts = = 8.01 /cu.m.
55 cu. m./hr.
c. Hauling
use : 4 cu. m./trip Dump Truck
rental = 342.25 /hr.
AHD = 25 kms.
Shrinkage Factor = 5%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 25 kms. / 20 km./hr. = 1.25 hrs./trip
without load = 25 kms. / 25 km./hr. = 1.00 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.37 hrs./trip
LABOR COST:
809.97 /day x 2.37 hrs/trip
Driver = = 63.06
8 hrs/day x 4 cu. m./trip x 95% s.f.
558.75 /day x 2.37 hrs/trip
Laborer = = 43.50
Laborer = = 43.50
8 hrs/day x 4 cu. m./trip x 95% s.f.
Labor Cost = 106.56
EQUIPMENT:
15.00 lit/hr x 2.37 hrs/trip x 35 /liter
Fuel = = 326.97
4 cu. m./trip x 95% s.f.
136.90 /hr. x 2.37 hrs/trip
Depreciation = = 85.26
4 cu. m./trip x 95% s.f.
205.35 /hr. x 2.37 hrs/trip
Spare Parts = = 127.89
4 cu. m./trip x 95% s.f.
d. Spreading
Utilized : 110 HP Grader
Production : 70 cu. m./hr.
Rental : 738.25 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.64 /cu.m.
8 hrs/day x 70 cu. m./hr.
558.75 /day
Laborer = = 1.00 /cu.m.
8 hrs/day x 70 cu. m./hr.
Labor Cost = 2.64 /cu.m.
EQUIPMENT:
14.00 lit/hr x 35 /liter
Fuel = = 7.00 /cu.m.
70 cu. m./hr.
295.30 /hr.
Depreciation = = 4.22 /cu.m.
70 cu. m./hr.
442.95 /hr.
Spare Parts = = 6.33 /cu.m.
70 cu. m./hr.
e. Compaction
Utilized : 8 Tons Road Roller
Production : 60 cu. m./hr.
Rental : 617.00 /hr. (incl. Fuel & operator)
LABOR COST:
921.12 /day
HE Operator = = 1.92 /cu.m.
8 hrs/day x 60 cu. m./hr.
558.75 /day
Laborer = = 1.16 /cu.m.
8 hrs/day x 60 cu. m./hr.
Labor Cost = 3.08 /cu.m.
EQUIPMENT:
8.50 lit/hr x 35 /liter
Fuel = = 4.96 /cu.m.
60 cu. m./hr.
246.80 /hr.
Depreciation = = 4.11 /cu.m.
60 cu. m./hr.
370.20 /hr.
Spare Parts = = 6.17 /cu.m.
60 cu. m./hr.
SUMMARY
a. Materials (Quarry Pit Fee) = 50.00 /cu.m.
b. Labor = 118.49 /cu.m.
c. Depreciation = 106.95 /cu.m.
d. Spare Parts = 160.43 /cu.m.
e. Fuel = 353.81 /cu.m.
UNIT COST = 789.69 /cu.m.
J. PILE DRIVING
1. Steel Piles
Rental
Utilized : 1 - 25 TONS Crane = 644.63 /hr.
: 1 - Drop Hammer = 55.00 /hr.
Total Rental/hr. = 699.63 /hr.
Production : 8 lin. m./hr.
LABOR COST:
921.12 /day
1- HE Operator = = 14.39 /lin.m.
8 hrs/day x 8 lin. m./hr.
1,117.50 /day
2 - Laborer = = 17.46 /lin.m.
8 hrs/day x 8 lin. m./hr.
Labor Cost = 31.85 /lin.m.
EQUIPMENT:
5.50 lit/hr x 35 /liter
Fuel = = 24.06 /lin.m.
8 lin. m./hr.
279.85 /hr.
Depreciation = = 34.98 /lin.m.
8 lin. m./hr.
419.78 /hr.
Spare Parts = = 52.47 /lin.m.
8 lin. m./hr.
SUMMARY
a. Labor = 31.85 /lin.m.
b. Depreciation = 34.98 /lin.m.
c. Spare Parts = 52.47 /lin.m.
d. Fuel = 24.06 /lin.m.
UNIT COST = 143.37 /lin.m.
7,466.67 /trip
4,768.84 /trip
7,153.26 /trip
314,731.20
217,114.29
44,800.00
28,613.04
42,919.56
36,718.64
25,330.00
2,975.00
775.77
1,163.65
150,000.00
112,500.00
18,750.00
37,500.00
56,250.00
172,200.00
114,224.64
171,336.96
189,000.00
141,120.00
211,680.00
2,824.00 /day
cu.m./day
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
2,824.00 /day
cu.m./day
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
RECAPITULATION
FORCE ACCOUNT WORKS
Equipment
Rental CONSTRUCTION
ITEM OF WORK UNIT LABOR FUEL
(Depreciation MATERIALS
Cost)
1 Temporary Works, Mob. & Demob. l.s. 706,394.13 66,888.81 150,000.00 66,525.00
2 Cofferdamming and Dewatering Works l.s. 234,130.05 255,344.64 21,250.00 361,200.00
3 Clearing and Grubbing sq.m. 0.88 2.48 - 2.83
4 Structure Excavation
a. Common Materials
a.1. Using Dozer cu.m. 7.40 20.85 - 23.80
a.2. Using Backhoe cu.m. 6.17 17.45 - 14.00
a.3. Manual cu.m. 279.38 - - -
b. Indurated Materials -
b.1. Using Dozer cu.m. 12.33 34.76 - 39.67
b.2. Using Backhoe cu.m. 12.33 34.89 - 28.00
b.3. Manual cu.m. 447.00 - - -
c. Solid Rocks
c.1. By Blasting cu.m. 164.96 63.08 458.82 71.33
c.2. Manual cu.m. 2,793.75 - - -
5 Canal Excavation
a. Common Materials
a.1. Using Dozer cu.m. 4.62 13.03 - 14.88
a.2. Using Backhoe cu.m. 4.62 13.08 - 10.50
a.3. Manual cu.m. 223.50 - - -
b. Indurated Materials
b.1. Using Dozer cu.m. 9.25 26.07 - 29.75
b.2. Using Backhoe cu.m. 7.40 20.93 - 16.80
b.2. Manual cu.m. 372.50 - - -
c. Solid Rocks
c.1. By Blasting cu.m. 154.46 55.80 433.33 22.74
c.2. Manual cu.m. 1,862.50 - - -
6 Embankment Construction and Compaction
a. Haul Borrow cu.m. 48.78 56.63 50.00 134.46
b. Overhaul cu.m. 21.24 28.37 - 49.50
c. Side Borrow cu.m. 4.62 13.03 - 14.88
7 Structure Backfill w/ Compaction
a. Using Dozer cu.m. 2.64 7.45 - 8.50
b. Manual cu.m. 186.25 - - -
8 Disposal of Excess Excavated Materials cu.m. 18.05 20.75 - 50.57
9 Concrete Demolition
a. Massive Concrete Slab
a.1. Mechanized cu.m. 69.37 22.68 - 24.06
a.2. Manual cu.m. 2,793.75 - - -
b. Slab Wall
b.1. Mechanized cu.m. 46.25 15.12 - 16.04
b.2. Manual cu.m. 1,117.50 - - -
10 Road Metalling cu.m. 118.49 106.95 50.00 353.81
11 Pile Driving
a. Steel Sheet Piles cu.m. 31.85 34.98 - 24.06
b. Thick Concrete Piles cu.m. 127.41 139.93 - 96.25
c. Thin Concrete Piles cu.m. 127.41 139.93 - 96.25
12 Concreting Works
a. Class "A" Concrete (211 kscm)
a.1. Diversion Dams cu.m. 4,696.51 125.20 4,129.00 311.13
a.2. Flume, Bridges & Pump Houses cu.m. 4,735.17 128.05 5,929.00 320.24
a.3. Siphon, Box Culvert & Others cu.m. 4,724.09 127.22 5,391.50 317.58
b. Class "B" Concrete
b.1. Concrete Pavement (170 kscm) cu.m. 3,776.36 112.55 2,409.50 294.22
b.2. Canal Lining (200 kscm) cu.m. 3,458.77 114.46 2,540.30 294.30
c. Lean Concrete cu.m. 3,165.89 95.71 1,560.00 262.54
13 Reinforcing Steel Bars
a. Furnishing & Stockpiling kg. 0.78 0.06 55.00 0.07
b. Cut, Bend & Place kg. 15.91 - - -
14 Rubble Masonry cu.m. 3,345.61 96.30 3,845.50 441.35
15 Grouted Riprap cu.m. 3,833.94 81.45 1,357.20 404.21
16 Boulder Riprap cu.m. 1,309.50 36.10 162.00 303.36
17 Filter Drain cu.m. 975.05 36.50 120.00 124.67
18 Gravel Blanket cu.m. 1,005.31 36.50 120.00 124.67
19 4" THK CHB cu.m. 391.31 27.92 539.72 41.96
20 Fabrication & Installation of RCPipes
a. 30cm Ø pc. 1,290.44 10.66 678.44 25.46
b. 46cm Ø pc. 1,714.56 22.27 1,294.62 52.96
c. 61cm Ø pc. 2,127.18 33.69 1,778.39 80.36
d. 76cm Ø pc. 2,923.37 46.37 2,859.90 110.14
e. 91cm Ø pc. 3,615.40 60.93 4,769.74 143.64
f. 122cm Ø pc. 5,378.20 76.58 5,743.85 180.71
21 Gabion cu.m. 1,121.71 34.79 1,430.00 292.03
22 Mattress cu.m. 1,119.24 33.77 964.00 290.96
23 Slope Protection
a. Erosion Control Net (CGN 40) sq.m. 14.42 0.19 90.00 0.09
b. Vetiber Grass sq.m. 14.42 0.74 75.00 0.56
24 Installation of Steel Gates
a. Gate Sizes up 0.60m x 0.60m assy 1,753.95 - - -
b. Gate Sizes above 0.60m x 0.60m assy 3,507.90 - - -
Equipment
Rental (Spare TOTAL REMARKS
Parts)
100,333.21 1,090,141.14
383,016.96 1,254,941.65
3.72 9.92
-
-
31.28 83.33
26.17 63.78
- 279.38
-
52.13 138.89
52.34 127.56
- 447.00
-
94.62 852.82
- 2,793.75
-
-
19.55 52.08
19.63 47.83
- 223.50
-
39.10 104.17
31.40 76.54
- 372.50
-
83.70 750.03
- 1,862.50
-
84.95 374.81
42.56 141.67
19.55 52.08
-
11.17 29.76
- 186.25
31.12 120.48
-
-
34.02 150.13
- 2,793.75
-
22.68 100.09
- 1,117.50
160.43 789.69
-
52.47 143.37
209.89 573.48
209.89 573.48
-
-
187.80 9,449.65
192.08 11,304.54
190.83 10,751.21
-
168.83 6,761.47
171.69 6,579.51
143.56 5,227.69
-
0.09 55.99
- 15.91
144.46 7,873.22
122.17 5,798.97
54.14 1,865.10
54.75 1,310.97
54.75 1,341.23
24.18 1,025.09
-
15.97 2,020.97
33.36 3,117.75
50.47 4,070.09
69.48 6,009.25
91.32 8,681.04
114.77 11,494.11
49.44 2,927.97
49.11 2,457.08
-
0.06 104.77
0.89 91.61
-
- 1,753.95
- 3,507.90
DERIVATION OF UNIT COST
(PARCELLARY SURVEY)
SUMMARY
a. Labor = 108,579.45
b. Depreciation = 35,162.40
c. Spare Parts = 52,743.60
d. Fuel = 78,400.00
UNIT COST = 274,885.45
SUMMARY
a. Labor = 213,641.82
b. Depreciation = 42,194.88
c. Spare Parts = 63,292.32
d. Fuel = 94,080.00
UNIT COST = 413,209.02
C. PADDY/PARCELLARY SURVEY
Service Area : 850.00 Hectares
Capability : 15 ha./day
Cycle Time:
850.00 Hectares
No. of Days = = 56.67 days
15 ha./day
25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 56.79 days
say 56.00 days
or in Hours = 448.00 hours
1. Labor
a. Daily Renumeration
1- Geodetic Engineer x 1,281.67 /day x 56.00 days = 71,773.52
1- Survey Aide x 760.07 /day x 56.00 days = 42,563.92
1- Driver x 809.97 /day x 56.00 days 45,358.32
4- Utility Worker x 558.75 /day x 56.00 days = 125,160.00
Total Labor Cost = 284,855.76
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Fuel = 8.00 lit/hr x 35.00 /lit. x 448.00 hrs. = 125,440.00
Depreciation = 125.58 /hr. x 448.00 hrs. = 56,259.84
Spare Parts = 188.37 /hr. x 448.00 hrs. = 84,389.76
SUMMARY
a. Labor = 284,855.76
b. Depreciation = 56,259.84
c. Spare Parts = 84,389.76
d. Fuel = 125,440.00
UNIT COST = 550,945.36
RECAPITULATION
a. Materials/Office Supplies = 165,750.00
b. Labor = 674,454.45
c. Depreciation = 133,617.12
d. Spare Parts = 200,425.68
e. Fuel = 297,920.00
UNIT COST = 1,472,167.25
SG
14
10
7
6
1
34,424.25
28,348.95
19,556.25
82,329.45
8,750.00
8,750.00
8,750.00
26,250.00
108,579.45
53,830.14
31,922.94
34,018.74
93,870.00
213,641.82
71,773.52
42,563.92
45,358.32
125,160.00
284,855.76
42,295.11
25,082.31
67,377.42
DERIVATION OF UNIT COST
FIELD SUPPORT SUPERVISION AND MONITORING
BICUD SWIS, LALLO, CAGAYAN
WAGES
TOTAL = P 85,308.06
SAY = P 85,308.10
Approved:
FRANCIS C. YU
Acting Manager
85,308.10
-
DERIVATION OF UNIT COST
CONSTRUCTION SURVEY
BICUD SWIS, LALLO, CAGAYAN
*Assumptions:
1. Establishment of Vertical & Horizontal Control is a one-time activity.
2. The Conduct of Profile and Cross Section Survey shall be at least once a month which shall serve as a
basis in the preparation of Monthly Statistical Report/Status Report as a requisite for Contract Billing, Monthly
Progress Report and other similar report which survey results maybe needed. Profile & Cross Section Survey
may be conducted as often as needed depending on the needed data to be gathered.
3. For presentation, profile & cross section survey shall be conducted on (1) Stake-Out Surveys (2) Once a month
in a year.
No. of Surveys = 1 Profile & Cross-Section Surveys
PROGRAMMED LENGTH OF CANAL : 1.00 km.
A. ESTABLISHMENT OF VERTICAL & HORIZONTAL CONTROL
Length of Canal : 1.00 km.
Capability : 5 km./day
Cycle Time:
1.00 km.
No. of Days = = 0.20 days
5 km./day
25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 0.33 days
say 0.39 days
or in Hours = 3.12 hours
1. Labor
1- Geodetic Engineer x 1,281.67 /day x 0.39 days = 499.85
1- Instrumentation x 983.55 /day x 0.39 days = 383.58
1- Survey Aide x 760.07 /day x 0.39 days = 296.43
1- Driver x 809.97 /day x 0.39 days 315.89
5- Utility Worker x 558.75 /day x 0.39 days = 1,089.56
Total Labor Cost = 2,585.31
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Fuel = 8.00 lit/hr x 35.00 /lit. x 3.12 hrs. = 873.60
Depreciation = 125.58 /hr. x 3.12 hrs. = 391.81
Spare Parts = 188.37 /hr. x 3.12 hrs. = 587.71
SUMMARY
a. Labor = 2,585.31
b. Depreciation = 391.81
c. Spare Parts = 587.71
d. Fuel = 873.60
UNIT COST = 4,438.44
B. PROFILE SURVEY
Length of Canal : 1.00 km.
Capability : 2 km./day
Cycle Time:
1.00 km.
No. of Days = = 0.50 days
2 km./day
25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 0.63 days
say 1.00 days
or in Hours = 8.00 hours
Page 153
1. Labor
1- Geodetic Engineer x 1,281.67 /day x 1.00 days = 1,281.67
1- Instrumentation x 983.55 /day x 1.00 days = 983.55
1- Survey Aide x 760.07 /day x 1.00 days = 760.07
1- Driver x 809.97 /day x 1.00 days 809.97
5- Utility Worker x 558.75 /day x 1.00 days = 2,793.75
Total Labor Cost = 6,629.01
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Fuel = 8.00 lit/hr x 35.00 /lit. x 8.00 hrs. = 2,240.00
Depreciation = 125.58 /hr. x 8.00 hrs. = 1,004.64
Spare Parts = 188.37 /hr. x 8.00 hrs. = 1,506.96
SUMMARY
a. Labor = 6,629.01
b. Depreciation = 1,004.64
c. Spare Parts = 1,506.96
d. Fuel = 2,240.00
UNIT COST = 11,380.61
SUMMARY
a. Labor = 6,629.01
b. Depreciation = 1,004.64
c. Spare Parts = 1,506.96
d. Fuel = 2,240.00
UNIT COST = 11,380.61
Page 154
UNIT COST = 501.33
2. Cross-Section
Length of Canal : 1.00 km.
1. Materials/Office Supplies
Cross Section Paper = 350.00 /km. x 1.00 km. = 350.00
Data Book = 75.00 /km. x 1.00 km. = 75.00
Miscellaneous = 55.00 /km. x 1.00 km. = 55.00
Total Materials Cost 480.00
2. Labor
Length of Canal : 1.00 km.
Capability : 8 km./day
Cycle Time:
1.00 km.
No. of Days = = 0.13 days
8 km./day
Total Number of Days = 0.13 days
say 0.20 day
1- Engineering Asst. A x 1,281.67 /day x 0.20 days = 256.33
Sub-Total = 256.33
SUMMARY
a. Materials Cos = 480.00
b. Labor Cost = 256.33
UNIT COST = 736.33
Materials/Off
a. = 725.00
ice Supplies
b. Labor = 16,356.00
c. Depreciation = 2,401.09
d. Spare Parts = 3,601.63
e. Fuel = 5,353.60
UNIT COST = 28,437.33
SAY = 28,437.30
Page 155
28436
1.30
Page 156
INSTITUTIONAL DEVELOPMENT PROGRAM
PHYSICAL PROGRAM OF WORK FOR CY-2017
REGION 2
BICUD SWIS, LALLO, CAGAYAN
TARGET BY QUARTER
TOTAL TARGET
PARTICULARS
FOR THE YEAR 1 2 3 4
I PERSONAL SERVICE `
a. Salaries/Wages and Allowances 18,785.00 2,817.00 13,151.00 2,817.00 18,785.00
b. Other remunerations 4,976.00 710.00 3,556.00 710.00 4,976.00
Sub-Total I 23,761.00 3,527.00 16,707.00 3,527.00
II MOOE
a. Capacity Building for Ias
b. Capacity Building for NIA Staff
c. Assistance Programs/Inter- 7,000.00 3,500.00 3,500.00
agency Coordination
d. Supervision Cost
e. Office Supplies and Materials 8,481.12 4,240.56 4,240.56
f. Miscellaneous 2,893.00 2,893.00
Sub-Total II 18,374.12 10,633.56 7,740.56
APPROVED BY:
FRANCIS C. YU
ACTING MANAGER
42654
(518.88)
BICUD SWIS
Lallo, Cagayan
PERCENTA
ESTIMATED GE WT. 2017
ITEM NO. UNIT QTY.
COST
(P'000) (%) April May June July August 100%
TEMPORARY WORKS, CONSTRUCTION PLANT, MOBILIZATION OF CONSTRUCTION EQUIPMENT 50.00% 50.00%
I. AND DEMOBILIZATION WORKS units 1 - 0.00%
0.00% 0.00% 0.00% 0.00% 0.00%
10.00% 25.00% 30.00% 25.00% 10.00%
II. CANALIZATION WORKS km. 1.72 - 0.00%
0.00% 0.00% 0.00% 0.00% 0.00%
10.00% 25.00% 30.00% 25.00% 10.00% 80%
III. CANAL STRUCTURES units 6 - 0.00%
0.00% 0.00% 0.00% 0.00% 0.00%
IX. FIELD SUPPORT, SUPERVISION AND MONITORING l.s. 1 - 0.00% 10.00% 25.00% 30.00% 25.00% 10.00%
0.00% 0.00% 0.00% 0.00% 0.00%
X. CONSULTANCY SERVICES
20%
XI. CONTINGENCIES
0%
5. CHB Lining
= 0.40 x 700.00 x 2.00 = 560.00 sq.m
6. RSB
= 89.60 x 40.00 + 560.0 x 4.40 = 6,048.00 kg
Page 170
B. CHB LINING AT Sta 0+703.35 - 1+065, MC
Clearing &
Grubbing Area (sq. m.) Volume (cu. m.)
Station Remarks
width Area fill cut fill cut
0+703.35 0.50 1.00 0.00 0.00
0+720 0.50 2.14 8.32 26.14
0+740 0.95 0.08 14.50 22.20
0+760 0.50 1.50 14.50 15.80
0+780 0.58 0.73 10.80 22.30
0+800 0.16 1.43 7.40 21.60
0+820 0.13 2.00 2.90 34.30
0+840 0.95 0.07 10.80 20.70
0+860 0.40 0.90 13.50 9.70
0+880 0.45 1.91 8.50 28.10
0+900 0.40 1.82 8.50 37.30
0+920 0.40 1.04 8.00 28.60
0+940 0.40 2.04 8.00 30.80
0+960 0.30 1.20 7.00 32.40
0+980 0.50 0.97 8.00 21.70
1+000 0.43 0.15 9.30 11.20
1+020 0.70 0.05 11.30 2.00
1+040 0.65 0.05 13.50 1.00
1+065 0.44 0.20 13.63 3.13
TOTAL - 178.45 368.97
2. Side Borrow
= 178.00 cu.m
S U M M A R Y
Page 171
`
Page 172
`
Page 173
Estimated Quantities
Concrete Works
1. Class "A"Concrete
a. footing and shaft Vol. = 0.20 x 0.60 x 0.6 = 0.072
+ 0.2 x 0.2 x 1.6 = 0.064 = 0.136 cu.m
x 28.00 pcs
= 3.808 cu.m
b. floor slab = 38 x 0.5 x 0.1 = 1.9
32 x 0.5 x 0.1 = 1.6 = 3.500 cu.m
68 + 1 = 228
0.3 364 = 61 pcs = 225.653 kg.
364 6
e. for slab
= 0.5 = 2 x 70 = 140 = 24 pcs = 88.781 kg.
0.3 6
= 70 = 234 x 0.5 = 117 = 20 pcs = 73.985 kg.
0.3 6
a. footing Excavation
Vol. = 0.6 x 0.6 x 0.6 x 28 = 6.05 cu.m
b. for chb wall footing
= 0.4 x 0.3 x 68 = 8.16 cu.m
c. for RCP Excavation
= 1.86 + 5.86 x 2 x 12 = 92.64 cu.m
2
d. floor excavation
Vol. = 38 x 1 x 0.2 x 2
+ 32 x 1 x 0.2 x 2 = 28.00 cu.m.
TOTAL EXCAVATION = 134.85 cu.m
6. GRAVEL BLANKET
a. for wall & footing
= 0.3 x 0.1 x 68 = 2.04
0.6 x 0.6 x 0.1 = 0.036 = 2.08 cu.m.
b. div. box
= 1.5 x 0.1 x 0.5 = 0.075
b. GI Pipe 1 1/4"ø
= 68 x 2 = 136 182 = 188.00 lin.m.
+ 2 x 23 = 46 6
c. GI Pipe 3" ø
= 6 x 6 pcs = 36.00 lin.m.
d. Flat bar = 391
= 17 x 23.00 6 = 66.00 pcs.
8. CHB Canal Lining
a. 4" THK CHB
= 0.4 x 140 = 56.00 sq.m.
b. Class "A" Concrete
= 0.1 x 140 x 0.5 = 7.00 cu.m.
c. RSB
c.1. horizontal Bars = 4 x 140 = 560
c.2.U bars = 0.9 x 351 = 316 876 = 146 pcs
876 6 = 540.09 kg.
d. Gravel Blanket
= 140 x 0.1 x 0.5 = 7.00 cu.m
Prepared by:
Checked and Submitted:
Approved by:
FRANCIS C. YU
Acting Manager
ESTIMATED QUANTITIES
BICUD SWIS
Lallo, Cagayan
III. CANAL STRUCTURES
@ MAIN CANAL
A. Vert Drop (sta 0+700 Sta 0+703.35, MC)
1. Class "A" Concrete
3. Structure Excavation
C. Basin = [ 1 ( 1.60 + 2.40 ) x 2.40 x 1.80 = 8.640 cu.m.
2
Otrans = [ 1 ( 1.60 + 2.00 ) x 0.90 x 1.80 = 2.916 cu.m.
2
OCOW = [ 1 ( 0.50 + 0.70 ) x 0.60 x 2.20 = 0.792 cu.m.
2 Excavation = 12.00 cu.m.
4. Structure Backfill
C. Basin = 8.640 -( 2.15 x 1.60 x 0.9 ) = 5.540 cu.m.
I Ballustrade =[( 0.86 x 1.37 )-( 0.25 x 0.6 x 0.6 )] x 0.15 = 0.13 cu.m.
@ Outlet:
OCOW = ( 0.8 x 2.06 x 0.13 = 0.323 cu.m.
[ 1 ( 0.80 x 1.05 x 0.13 )x 2]
2
O Fillet = 1 ( 0.13 x 0.13 x 2.06 ) = 0.017 cu.m.
2
Page 176
OSide Walls = 1 ( 1.62 x 1 )x 0.13 x 2 = 0.211 cu.m.
2
OFlr = ( 0.86 + 2.06 )x 1.50 x 0.13 = 0.285 cu.m.
2.00
O Ballustrade =[( 0.86 x 1.22 )-( 0.25 x 0.6 x 0.6 )] x 0.15 = 0.11 cu.m.
1.b. RSB
= 1.50 x 60.00 = 90.00 kg.
2. STRUCTURE EXCAVATION:
=[( 3.20 + 2.40 )x 0.80 x 1.8 ]+(
2
+( 3.20 + 2.40 )x 1.50 x 7
2
+( 3.20 + 2.40 )x 1.00 x 2.6
2
+( 0.5 x 0.6 x 2.40 )+( 0.5 x 0.8 x 3.00 ) = 42.60 cu.m.
3. STRUCTURAL BACKFILL:
= 42.60 - {[( 0.86 + 1.86 )x 1.30 x 1.0 x 0.5 ]
2
+( 0.25 x 0.60 x 0.60 x 7)
I Ballustrade =[( 2.80 x 1.95 )-( 0.25 x 1.11 x 1.11 )] x 0.15 = 0.67 cu.m.
@ Outlet:
OCOW = 1 x 4.1 x 0.15 = 0.773 cu.m.
[ 1 ( 1.00 x 1.05 x 0.15 )x 2]
2
O Fillet = 1 ( 0.13 x 0.13 x 4.10 ) = 0.035 cu.m.
2
OSide Walls = 1 ( 2.60 x 2.25 )x 0.15 x 2 = 0.878 cu.m.
2
OFlr = ( 2.80 + 4.10 )x 2.55 x 0.15 = 1.320 cu.m.
2.00
O Ballustrade =[( 2.80 x 2.50 )-( 0.25 x 1.11 x 1.11 )] x 0.15 = 0.9 cu.m.
1.b. RSB
= 6.80 x 60.00 = 408.00 kg.
2. STRUCTURE EXCAVATION:
=[( 5.20 + 2.40 )x 1.00 x 2.6 ]+(
2
+( 4.00 + 2.40 )x 1.80 x 9
2
+( 5.20 + 2.40 )x 1.00 x 3.2
2
+( 0.5 x 0.8 x 4.20 )+( 0.5 x 1 x 5.60 ) = 78.40 cu.m.
Page 177
3. STRUCTURAL BACKFILL:
= 78.40 - {[( 2.80 + 3.80 )x 1.45 x 2.6 x 0.5 ]
2
+( 0.25 x 1.11 x 1.11 x 9)
I Ballustrade =[( 0.86 x 1.35 )-( 0.25 x 0.6 x 0.6 )] x 0.15 = 0.13 cu.m.
@ Outlet:
OCOW = 0.8 x 2.66 x 0.13 = 0.370 cu.m.
[ 1 ( 0.80 x 0.90 x 0.13 )x 2]
2
O Fillet = 1 ( 0.13 x 0.13 x 2.66 ) = 0.022 cu.m.
2
OSide Walls = 1 ( 2.01 x 1.2 )x 0.13 x 2 = 0.314 cu.m.
2
OFlr = ( 0.86 + 2.66 )x 1.80 x 0.13 = 0.412 cu.m.
2.00
O Ballustrade =[( 0.86 x 1.42 )-( 0.25 x 0.6 x 0.6 )] x 0.15 = 0.14 cu.m.
1.b. RSB
= 2.10 x 60.00 = 126.00 kg.
2. STRUCTURE EXCAVATION:
=[( 3.20 + 2.40 )x 1.00 x 1.8 ]+(
2
+( 3.20 + 2.40 )x 1.50 x 7
2
+( 3.20 + 2.40 )x 1.00 x 2.6
2
+( 0.5 x 0.6 x 2.40 )+( 0.5 x 0.8 x 3.00 ) = 43.60 cu.m.
3. STRUCTURAL BACKFILL:
= 43.60 - {[( 0.86 + 2.06 )x 1.13 x 1.3 x 0.5 ]
2
+( 0.25 x 0.60 x 0.60 x 7)
S U M M A R Y
Common Structure Excavation = 176.60 cu.m.
Reinforced Class "A" Conc., 211 kgsc = 12.60 cu.m.
Reinforcing Steel Bars =
a. Furnishing & Stockfilling = 756.00 kg
b. Cutting, Bending &Placing = 756.00 kg
46 cm ø x 1.00 m std RCP = 16.00 pc
91 cm ø x 1.00 m std RCP = 9.00 pc
Structure Backfill = 140.50 cu.m.
Page 178
ANGELO S. DAGUNA BENJAMIN N. RIVERA FRANCIS C. YU
Engineer A Chief, Engineering Section Acting Manager
Page 179
Page 180
Page 181
INDIVIDUAL BREAKDOWN OF PACKAGES
BICUD SWIS
LALLO, CAGAYAN
Schedule I
Type of Procurement : Civil Works/Competitive Bidding
Delegated Authority : CBIMO
Description of Works :
Construction of Canalization Works and Canal Structures
Location : Main Canal
Approved:
FRANCIS C. YU
Acting Manager
SUMMARY OF PACKAGES
BICUD SWIS
LALLO, CAGAYAN
TOTAL -
Prepared by:
Checked & Submitted by:
Approved:
FRANCIS C. YU
Acting Manager