Siddhivinayak Tunnels

Report Card-September month Date-21.10.2020

S. No Activities Committed Achieved Achieved


(in numbers) (in numbers) (%)
1 TBM K1 (SV -DADAR) 150 (as per 3MRP) 156 104 %
2 TBM K2 (SV -DADAR) 180 (as per 3MRP) 184 102 %
3 CP - 16 Excavation & support 100%
H/B
4 CP - 15 Excavation & support 01-02 Mtr Running Mtr 01-02 Mtr
heading
5 CP -14 Ground preparation Done 100%
6 CP - 13 No activity No activity 0%
7 CP - 12 No activity No activity 0%

Report Card-planned for October month

S. No Activities Committed Achieved Achieved Overall (%) Current


(in numbers) (in numbers) (%) month progress

1 TBM K1 (SV -DADAR) 150 (as per 3MRP) 83 55 % 83 rings till 19th Oct
2 TBM K2 (SV -DADAR) 40 (as per 3MRP) 29 73 % Breakthrough 05 Oct
3 CP – 16 Excavation completed Excavation 100 % Excavation 100%
H/B completed H/B
4 CP - 15 Breakthrough & Breakthrough 50% 16th Oct
Heading excavation done & heading breakthrough done
completed widening is
ongoing
5 CP -14 Heading excavation On going 05% Excavation started 13
has started Oct 2020
6 CP - 13 Heading excavation On going 01 % Excavation started 16
has started Oct 2020
7 CP - 12 Segment core cutting Segment core Work has started 19
cutting is Oct 2020
ongoing

Permanent Works

1. TBM K2 breakthrough done on 05 Oct 2020 afterwards TBM pushing has done & dismantling preparation is ongoing.
2. As per submitted program of K2 (SST – Dadar) up-line TBM retrieval should be done by 15 Nov 2020 & handover to station.
3. TBM K3 dismantling has been completed & cleaning work is balance subjected to invert preparation, TBM gantries pulling rail
lines dismantling is ongoing.
4. Invert concrete has been done in K3 up-line (SST - Worli) up to 564 Mtr / 1303 Mtr from Worli towards Siddhivinayak.
5. CJV to provide Plan for all Cross Passages works.
Naya Nagar launching Shaft and Cross passage (CP) NN-SSD
Sep’2020 Three Month Rolling Program No mention of CP’s paln.

Report Card-October month

S. No Activities Committed Achieved Achieved Overall (%)


(in numbers) (in numbers) (%) Current month
progress
1 Shaft RCC work base slab 2 (26.80Rmt) 100%
2 CP04 20.90Rmt 100% 83.50%

3- CP05 20.50RMT 50%

Report Card-planned for October month

S. No Activities Committed Achieved Achieved Overall (%) Current


(in numbers) (in numbers) (%) month progress

1 Shaft wall RCC work 72Rmt 0%


2 CP 05 Final lining 20.50Rmt 0%

Permanent Works:

 Shaft Base slab is completed at 05.09.2020.


 Outer wall casting is completed on date 18.09.2020
 CP04 is completed as on date 27.09.2020.
 CP05 water proofing work is in progress from date 10.10.2020
 PU grout is in progress at up-line for NN- Sitladevi

Permanent works.

Target in Sep-20 Target date Progress as on date Planned for Remarks %


this month achieved
Shaft wall 25.10.2020 Reinforcement work is in 00.00%
progress
Cross passage 05 31.10.2020 Water proofing work is
going on.
Tunnel Pu grout
PU grouting is in progress
for both Tunnel.
NATM Tunnel Shitladevi
Report Card-September month

S. Activities Committed Achieved Achieved Overall (%)


No (in numbers) (in numbers) (%) Current month
progress
1 Excavation top heading 44.01 Rm (as per 12.275 m 100%
Completed from CH:17617.275 to 3MRP) North and (South) 100%
17605.000 for South end. South.

Excavation for top heading completed 13m (North)


From17675.975 to 17688.975 for North

Report Card-planned for October month

S. No Activities Committed Achieved Achieved Overall (%) Current


(in numbers) (in numbers) (%) month progress

1 NATM excavation ongoing from 24.01 Rm (as per 17.133 mtr till 75.11% till date
Chainage 17688.975 3MRP) date 20/10/2020
20/10/2020

Permanent Works:

 South end Heading and Primary support completed on date 04 th of October 2020.
 CP 01 started on 04th of October 2020 and Excavation is in progress.
 CP 02 Completed on 13 Feb 2020.
 CP 03 Started on 17th of July 2020 and Finished on 13th of October 2020.
 North end Heading excavation is in progress.

Last week achieved:

1. Permanent works.
Target in Oct Target Progress (Last week) Planned for Remarks %
this month achieved
Excavation 5.15 1 mtr 22.81 Mucking from 18.2
heading bored tunnel is on
Priority so
Heading
excavation was
stopped.