SITLADEVI

December month Points as per Three Month program:


1) Weekly excavation is not achieved as per 3months rolling program.
2) No programme mentioned for ancillary building rather than micro pile.
3) Permanent activity is not achieved as per three months.
4) G: 22-24 Mezzanine slab how many meters will be casted at running month need to be specified.
5) Balance tunnel Ventilation shaft programme is not mentioned

January month Points as per Three Month program:


1) No programme mentioned for ancillary building.
2) As per 3 month program G: 6.5-8 base slab casted date is 10 th January 2021 but Main wall U/L &
D/L Programme is mentioned in 21st Feb.
3) G: 8-11 base slab casting date as per 3 month is 31 st January but Main wall U/L & D/L
Programme is not mentioned.
4) G:17.5-19.5 base slab planning in December and the main wall casting date in 3 month rolling
program is by Jan 3rd week (U/L &D/L).
5) No programme mentioned for South & North shaft header walls.

February month Points as per Three Month program:


1) No programme mentioned for U/L, D/L main for G 15.5-17.5 in Feb 2021.
2) G4.5-6.5 mezzanine slab casting date mentioned in 3 month rolling program is 31 st Jan, but for
starting of wall activity it takes around 14days, casting of 1 st lift of U/L, D/L is 28th Feb.