Professional Documents
Culture Documents
1 Grid 22-24 D/L concourse slab 308.7 sqm 308.7sqm 100% 100%
partial
2 Grid 5-6 seepage sump pit with 60sqm 60sqm 100% 100%
1200mm wall four sides
(1000x5000x500 and wall)
3 EE3 Intermediate level escalator 34.12sqm 34.12sqm 100% 100%
pit slab
4 EE4 Intermediate slab level 15.75sqm 0 0% 0%
escalator pit slab
5 Grid 22-24 D/l side C14 column 3 3 0 0%
nos.
6 Grid 4-6 HDPE membrane 480 330 68%
waterproofing
Permanent Works:
1. Permanent works.
Target in Oct-20 Target date Progress as on date Planned for Remarks %
this month achieved
Grid 5-6 seepage 14/10/2020 Completed on 16/10/2020 Due to monsoon 100%
sump pit with alert issued
1200mm wall four
sides
(1000x5000x500
and wall )
Grid 20-21 double 14/10/2020 Completed 100%
slab above
intermediate
slab(partial)
Grid 20-21 above 10/10/2020 Completed on 12/10/2020 100%
intermediate slab
partition wall
for(Water tank)-3
nos height 3.15)
Temporary Works:
1. Delay in backfilling & spray waterproofing work will affect ground anchor retraction to be done .