Siddhivinayak Station

There was no Plan in 3MRP for Permanent works by CJV.


Report Card-September month Date-21.10.2020
S. Activities Committed Achieved Achieved Overall (%)
No (in numbers) (in numbers) (%) Current month
progress
1 EE5 ent.& Station connection IS slab 48.36sqm 48.36 100%
2 Grid 22-24 D/L side OTE slab& wall 15.21rmt 15.21rmt 100% 100%
3 Grid 19-20 firemen staircase 2nd lift 1 1 100%

Report Card-planned for October month


S. No Activities Committed Achieved Achieved Overall (%) Current
(in numbers) (in numbers) (%) month progress

1 Grid 22-24 D/L concourse slab 308.7 sqm 308.7sqm 100% 100%
partial
2 Grid 5-6 seepage sump pit with 60sqm 60sqm 100% 100%
1200mm wall four sides
(1000x5000x500 and wall)
3 EE3 Intermediate level escalator 34.12sqm 34.12sqm 100% 100%
pit slab
4 EE4 Intermediate slab level 15.75sqm 0 0% 0%
escalator pit slab
5 Grid 22-24 D/l side C14 column 3 3 0 0%
nos.
6 Grid 4-6 HDPE membrane 480 330 68%
waterproofing

Permanent Works:

1. Solid concrete block masonry work started on 23/09/2020.


2. Work of solid block is in progress at site without approved drawing , SEM wall & Floor drawings.
3. E1 entrance excavation not started yet due to traffic permission issue.
4. No work for ancillary building taken up.
5. Work of backfilling & spray waterproofing not in progress at site that need to taken up and expedite.
6. E3, E4 & E5 entrance work of amin wall, staircase is in progress as well as rebar work (intermediate slab level) in E3 entrance is in
progress.
7. No M/s Normet engineer available at site for supervision

Last week achieved:

1. Permanent works.
Target in Oct-20 Target date Progress as on date Planned for Remarks %
this month achieved
Grid 5-6 seepage 14/10/2020 Completed on 16/10/2020 Due to monsoon 100%
sump pit with alert issued
1200mm wall four
sides
(1000x5000x500
and wall )
Grid 20-21 double 14/10/2020 Completed 100%
slab above
intermediate
slab(partial)
Grid 20-21 above 10/10/2020 Completed on 12/10/2020 100%
intermediate slab
partition wall
for(Water tank)-3
nos height 3.15)
Temporary Works:

1. Delay in backfilling & spray waterproofing work will affect ground anchor retraction to be done .