You are on page 1of 15

task_code status_codewbs_id task_name acwp

Activity ID Activity Sta WBS Code Activity Name (*)Actual Cost(RS)


A1000 In ProgressDSG DESGIN TEAM 637056
A1010 Not Started DSG START OF THE PROJECT0
A1020 Completed DSG EXCAVATION TEAM 35370
A1030 In ProgressDSG FINISH OF THE WORK 311976
bcws bcwp cpi spi
(*)Planned Value Cost(RS) (*)Earned Value Cost(RS) (*)Cost Performance Index (*)Schedule Performance I
144855 144855 0.23 1
0 0 0 0
35370 35370 1 1
311976 311976 1 1
cv eac resource_lisstart_date end_date delete_record_flag
(*)Cost Variance(RS) (*)Estimate (*)Resource(*)Start (*)Finish Delete This Row
-492201 679976 worker team ### ###
0 758511 design team ### ###
0 35370 worker team ### ###
0 1490552 concrete wo ### ###
rsrc_short rsrc_name rsrc_title_name
Resource I Resource Title
MathisL Lane Mathis, CIO
AndersonG Glen Anderson, VP Development
VincentI Ian Vincent
CharlesM Mandy Charles, VP IT Ops
ZhuS Shannon Zhu
LaffertyV Vanessa Lafferty
BennettC Carina Bennett
PaxsonD Dan Paxson
SinghD Deepak Singh
SharpeD Dan Sharpe
ITCon IT Consultant
LiR Roy Li
RiceB Barbara Rice, PMO Director
ChopraA Amit Chopra
AbrahamM Molly Abraham
WrenJ Jo Wren
ATM ENG Automation Systems Engineer
IT Information Technology Group
Product De Product Development Resources
ManufEng Manufacturing Engineering Group
CaseyA Andrea CasSix Sigma Engineer
RileyP Paul Riley Product Engineer
MarshallG Gary Marsha Product Engineer
LeeC Cindy Lee Product Engineering Specialist
ProductOpsProduct Operations Group
HillF Frank Hill
WestL Larry West
BaxterS Sue Baxter
WynnA Alice Wynn
ProductMkt Product Marketing Group
LincolnR Robert LincManufacturing Engineer
ShawH Harry ShawSenior Engineering Lead
JacksonL Lendell Jackson
RickelsS Sam Rickels
IthanP Peg Ithan
Corporate Corporate Resources
Bpmpmo Business Process PMO
JohnsonR Rea Johnson
McneillL Lori McNeil
Operations Process Operations
BillingsJ Judy Billings
Chuf Frank Chu
Contr External Contractors
Bpm001 BPM Consultant 1
Bpm002 BPM Consultant 2
Bpm003 BPM Consultant 3
FrostB Ben Frost
CooperP Peter Cooper
PetersonM Michelle Peterson
PrescottW Wayne Prescott
E&C ResourE&C Resources
SubcontractSubcontractor
Trades Trades
ManagemenManagement
Purchasing Purchasing Department
EngineeringEngineering Department
CretefinisheConcrete Finisher
Admin Administrator
Fabrication Fabrication
Elev Inst Elevator Installer
Elec Electrician
Floor Floor and Carpet Layer
Operator Operator
Plumb Plumber
FCarp Finish Carpenter
RCarp Rough Carpenter
GenLabor Laborer-Construction
FieldEng Field Engineer
IrnWrk Ironworker
FieldEngSnField Eng-Senior
FieldEngAssField Eng-Assistant
Exc Excavator
KimP Paul Kim Design Engineer
YoungJ Jeff Young Analyst
PMs Project Managers
ResnerW Wendy Resn Automation Systems Engineer
DesEng Design Engineer
McGuireO Owen McGuire, Project Manager
Project ContProject ContAccounts Manager
InsEng Instrumentation Engineer
HVAC HVAC
Millwork CaMillwork Subcontractor
Thermal ProThermal Protection Subcontractor
Finishes Finishes & Fit-out Subcontractor
Concrete-S Concrete Foundation Subcontractor
Specialty MSpecialty Metal Fabricator Subcontractor
Pools Pool Installation Subcontractor
Conveying- Conveying Subcontractor
Fire SuppreFire Suppression Subcontractor
LandscapinLandscaping Subcontractor
Specialties FF&E Specialties
Drywall Drywall Subcontractor
Roofing Roofing Subcontractor
Glass Glass & Glazing Subcontractor
Paving Paving & Roadways Subcontractor
Utilities Utilities Subcontractor
OPTGP Operations Test Group
INSP Inspections Senior Inspector
Hydro Hydroblaster
Paint Painter
Material Material Resources
Test resour New Resource Name
Test ResourNew Resource Name-1
1 st exca
1 sh
3 concrete
ITB Internal Building Construction Group
Excavation Design Team
Excavation-excavation team
Mrt Sub and Super structure work
R design team
concrete concrete team and supervision team
construc steel work
st12 concrete work
exca12 worker team
R-1 DE
R-2 EXC
R-3 STEEL
task_id TASK__statrsrc_id role_id acct_id
Activity ID (*)Activity SResource I Role ID Cost Account ID
A1000 In Progressexca12
A1000 In ProgressR
A1000 In ProgressR
A1020 Completed exca12
A1020 Completed exca12
A1020 Completed exca12
A1030 In Progressst12
A1010 Not Started R
A1010 Not Started concrete
A1010 Not Started concrete
rsrc_type start_date end_date delete_record_flag
(*)Resource Type (*)Start (*)Finish Delete This Row
Labor 20-Jul-21 08:00 29-Aug-21 16:00
Nonlabor 20-Jul-21 08:00 29-Aug-21 16:00
Nonlabor 20-Jul-21 08:00 29-Aug-21 16:00
Labor 20-Jul-21 08:00 09-Aug-21 17:00
Labor 20-Jul-21 08:00 09-Aug-21 17:00
Labor 20-Jul-21 08:00 09-Aug-21 17:00
Material 10-Aug-21 08:00 28-Sep-21 17:00
Nonlabor 30-Aug-21 08:00 13-Sep-21 17:00
Nonlabor 30-Aug-21 08:00 13-Sep-21 17:00
Nonlabor 30-Aug-21 08:00 13-Sep-21 17:00
task_id cost_name TASK__stattarget_cost act_cost
Activity ID Expense It (*)Activity SBudgeted Cost (RS) Actual Cost(RS)
A1000 DESIGN T In Progress555555 492201
A1020 EXCAVA Completed 444444 0
A1030 FNSH In Progress44444 0
A1030 FNSH1 In Progress33333 0
A1010 SRART Not Started 666666 0
remain_cost total_cost delete_record_flag
Remaining Cost(RS) At Completion Cost(RS) Delete This Row
0 492201
0 0
0 0
0 0
666666 666666
pred_task_itask_id pred_type PREDTASK__status_code TASK__status_code
PredecessoSuccessor Relationshi (*)Predecessor Activity Stat(*)Successor Activity Status
A1000 A1010 FS In Progress Not Started
A1020 A1030 FS Completed In Progress
pred_proj_id proj_id predtask__projwbs__wbs_ftask__projwbs__wbs_full_
(*)Predecessor Project (*)Successor Project (*)Predecessor WBS (*)Successor WBS
DSG DSG DSG 1 STOREY BUILDINGDSG 1 STOREY BUILDING
DSG DSG DSG 1 STOREY BUILDINGDSG 1 STOREY BUILDING
predtask__task_name task__task lag_hr_cnt predtask__rtask__rsrc_delete_record_flag
(*)Predecessor Activity Na (*)SuccessoLag(d) (*)Predeces(*)SuccessoDelete This Row
DESGIN TEAM START OF 0 exca12
EXCAVATION TEAM FINISH OF 0 exca12
user_data
UserSettings Do Not Edit
DurationQtyType=QT_DayShowAsPercentage=0SmallScaleQtyType=QT_HourDateFormat=dd/MMM/yyCurrencyFormat=Nep
ourDateFormat=dd/MMM/yyCurrencyFormat=Nepali Rupees

You might also like