CONSTRUCTION UPDATE As of June 2021.

Overview

The Tower 2 final coat painting and deep cleaning works are in progress.

The Tower 2 wooden flooring work is in progress.


The Tower 2 false ceiling tile fixing work is in progress.

The security cabin structural work is in progress.

The compound wall painting work is in progress.

The barbeque counter subbase work is in progress.


The quadrangle roof ACP work is in progress.

The entrance portal ACP work is in progress.


The external planter boxes, yoga center and open amphitheater works are in progress.

The external sports development works (beach volleyball, basketball


and badminton court) are in progress.

The external fitness station and trellis subbase works are in progress.

The fire driveway pavers work is in progress.


The fire driveway pavers work is in progress.

The transformer yard fencing and earth pit chamber cover fixing works are in progress.

The clubhouse party hall window fixing and flooring works are in progress.

The clubhouse gym IPS flooring work has been completed.


TOWER 1

ACTIVITIES % OF COMPLETION

Superstructure 100%

Terrace - Structure 100%

Toilet Waterproofing 100%

Toilet Tiling 100%

Balcony Handrail 99%

Unit Painting - Till Primer 75%

Flooring 100%

Wiring 99%

UPVC Windows 100%

Unit Doors 48%

MISCELLANEOUS

Basement Plastering 100%

Basement 2 Blockwork 100%

Basement 1 Blockwork 100%

TOWER 2

ACTIVITIES % OF COMPLETION

Superstructure 100%

Terrace - Structure 100%

Toilet Waterproofing 100%

Toilet Tiling 100%

Balcony Handrail 100%

Unit Painting -Till Primer 100%

Flooring 100%

Wiring 100%

UPVC Windows 100%

Unit Doors 96%

Final Coat Painting 18%

MISCELLANEOUS

Grade Slab 100%

Podium Waterproofing 95%

Basement Screed 100%