Task Name Start Finish Work Predecessors % Complete

1st floor swimming pool


Sun 03-10-21 8:00 AM 10/28/2021 8 hrs 0%
area slab
2nd Fl Slab Mon 04-10-21 8:00 AM 10/15/2021 0 hrs 0%
3rd Fl Slab Casting Fri 29-10-21 8:00 AM Fri 29-10-21 5:00 PM 8 hrs 0%
Terrace Slab Casting Mon 13-11-21 8:00 AM Mon 13-11-21 5:00 PM 8 hrs 0%
Terrace Parapet wall Tue 16-11-21 8:00 AM Sat 20-11-21 5:00 PM 8 hrs 0%
LMR & SHR Casting Thu 07-10-21 8:00 AM Thu 30-11-21 5:00 PM 0 hrs 0%
1st FL B/W 10/29/2021 11/7/2021 8 hrs 0%
1st FL Electric Conduit Sun 5-11-21 5:00 PM 9-11-21 5:00 PM 8 hrs 0%
1st FL Plastering Mon 08-11-21 8:00 AM 11/16/2021 8 hrs 0%
1st FL putty 11/24/2021 11/30/2021 0 hrs 0%
1st FL Primer 11/30/2021 12/5/2021 0 hrs 0%
1st FL 1st coat painting 12/5/2021 12/10/2021 0 hrs 0%
1st FL 2nd coat Painting Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
2nd FL B/W 11/12/2021 11/20/2021 8 hrs 0%
2nd FL Electric Conduit 11/19/2021 11/24/2021 0 hrs 0%
2nd FL Plastering 11/23/2021 11/30/2021 8 hrs 0%
2nd FL putty 12/6/2021 12/11/2021 0 hrs 0%
2nd FL Primer 12/10/2021 12/15/2021 0 hrs 0%
2nd FL 1st coat painting 12/15/2021 12/20/2021 0 hrs 0%
2nd FL 2nd coat Painting Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
3rd FL B/W Mon 22-11-21 8:00 AM Mon 29-11-21 5:00 PM 8 hrs 0%
3rd FL Electric Conduit Thu 28-10-21 8:00 AM Sat 30-10-21 5:00 PM 8 hrs 0%
3rd FL Plastering Tue 30-11-21 8:00 AM Tue 07-12-21 5:00 PM 8 hrs 0%
3rd FL putty Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 8 hrs 0%
3rd FL Primer Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
3rd FL 1st coat painting Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
3rd FL 2nd coat Painting Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
External Plastering
Sat 27-11-21 8:00 AM Sat 27-11-21 5:00 PM 0 hrs 0%
Elevation- A
External putty & Primer Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
External Painting Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
External Plastering
Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
Elevation - B
External Plastering
Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
Elevation - C
External Plastering
Thu 07-10-21 8:00 AM Thu 07-10-21 5:00 PM 0 hrs 0%
Elevation - D
Godrej Azure - Club House Schedule
Task Name Start Finish Days
1st floor swimming pool 10/3/2021 10/28/2021 25
area slab
2nd Fl Slab 10/4/2021 10/18/2021 14
3rd Fl Slab Casting 10/19/2021 10/29/2021 10
Terrace Slab Casting 10/30/2021 11/13/2021 14
Terrace Parapet wall 11/14/2021 11/20/2021 6
LMR & SHR Casting 11/14/2021 11/25/2021 11
1st FL B/W 10/30/2021 11/7/2021 8
1st FL Electric Conduit 11/5/2021 11/9/2021 4
1st FL Plastering 11/8/2021 11/16/2021 8
2nd FL B/W 11/2/2021 11/10/2021 8
2nd FL Electric Conduit 11/8/2021 11/12/2021 4
2nd FL Plastering 11/11/2021 11/19/2021 8
3rd FL B/W 11/27/2021 12/5/2021 8
3rd FL Electric Conduit 10/28/2021 11/1/2021 4
3rd FL Plastering 11/30/2021 12/8/2021 8
External Plastering 12/6/2021 12/14/2021 8
Elevation- A
External Plastering 12/7/2021 12/11/2021 4
Elevation -B
External Plastering 12/7/2021 12/15/2021 8
Elevation -C
External Plastering 12/7/2021 12/11/2021 4
Elevation - D
Godrej Azure Club House Revised Schedule
Sl.No Description of work Days Start End Remarks

3rd Floor Slab Concrete 27-Nov-21 casted on 3rd dec, so delay is 6 day
Terrace floor 14 28-Nov-21 11-Dec-21 casted on 19th dec night, so delay i
Above Terrace 10 12-Dec-21 21-Dec-21

Backfilling 15 29-Nov-21 14-Dec-21


PCC 3 17-Dec-21 20-Dec-21 Backfilling not completed.
Stitch Slab 3 25-Dec-21 28-Dec-21 PCC not completed.
Grano 3 3-Jan-22 6-Jan-22 Backfilling not completed.

Grinding Basement 10 18-Dec-21 28-Dec-21

Finishing
Blockwork
1st floor 9 29-Nov-21 8-Dec-21
2nd floor 9 7-Dec-21 16-Dec-21
3rd floor 9 21-Dec-21 30-Dec-21
Above Terrace 7 31-Dec-21 7-Jan-22

External Plastering
South 18 24-Dec-21 11-Jan-22
North 18 26-Dec-21 13-Jan-22
East 13 28-Dec-21 10-Jan-22
West 12 30-Dec-21 11-Jan-22

Inner Wall Plastering


1st floor 7 11-Dec-21 18-Dec-21
2nd floor 7 19-Dec-21 26-Dec-21
3rd floor 7 2-Jan-22 9-Jan-22
Remarks

rd dec, so delay is 6 days.


9th dec night, so delay is 8 days.

not completed.
mpleted.
not completed.
Activities Days Start Finish
First Floor
Blockwork 9 12/6/2021 12/15/2021
Electrical Conduiting 10 12/12/2021 12/22/2021
Internal Plastering 7 12/18/2021 12/25/2021
Fire erection work 10 12/15/2021 12/25/2021
HVAC 10 12/15/2021 12/25/2021
Toilets Waterproofing 7 12/25/2021 1/1/2022
Plumbing 4 1/1/2022 1/5/2022
IPS Flooring 7 1/5/2022 1/12/2022
Curtain window (10 No.s) 10 12/25/2021 1/4/2022
False Ceiling 15 1/1/2022 1/16/2022
POP 7 1/6/2022 1/13/2022
Putty 1st coat 7 1/6/2022 1/13/2022
Tiling works 10 1/6/2022 1/16/2022
Putty 2nd coat 7 1/13/2022 1/20/2022
Primer 4 1/18/2022 1/22/2022
MDF Partition work 20 1/17/2022 2/6/2022
Door frame & fixtures 10 1/17/2022 1/27/2022
Electrical wiring 5 1/17/2022 1/22/2022

Granite activities 5 1/28/2022 2/2/2022


Plumbing Fixtures 5 1/23/2022 1/28/2022
First coat Painting 7 2/3/2022 2/10/2022

2nd Coat painting


MDF Skirting
Vinyl Flooring
Rubber flooring
Full length mirror fixing
Exterior Green turf
Masonry bench clad
Mdf beading on painted wall
MDF Open cell Ceiling
MDF Boxing around beam
Pelmet clad
Bathroom Partition cubicle

Blockwork 9 12/15/2021 12/24/2021


Electrical Conduiting 10 12/20/2021 12/30/2021
Internal Plastering 7 12/26/2021 1/2/2022
Fire erection work 10 12/24/2021 1/3/2022
HVAC 10 12/24/2021 1/3/2022
Toilets Waterproofing 7 1/2/2022 1/9/2022
Plumbing 4 1/9/2022 1/13/2022
IPS Flooring 7 1/13/2022 1/20/2022
Window glazing work 10 1/2/2022 1/12/2022
False Ceiling 15 1/9/2022 1/24/2022
POP 7 1/14/2022 1/21/2022
Putty 1st coat 7 1/14/2022 1/21/2022
Tiling works 10 1/14/2022 1/24/2022
Putty 2nd coat 7 1/21/2022 1/28/2022
Primer 4 1/26/2022 1/30/2022
MDF Partition work 20 1/25/2022 2/14/2022
Door frame & fixtures 10 1/25/2022 2/4/2022
Electrical wiring 5 1/25/2022 1/30/2022
Granite activities 5 2/5/2022 2/10/2022
Plumbing Fixtures 5 1/31/2022 2/5/2022
First coat Painting 7 2/11/2022 2/18/2022
Vinyl Flooring 4 2/18/2022 2/22/2022
2nd Coat painting 5 2/23/2022 2/28/2022
Rubber flooring 4 2/18/2022 2/22/2022
Full length mirror fixing 3 2/23/2022 2/26/2022

Blockwork 9 12/24/2021 1/2/2022


Electrical Conduiting 10 12/29/2021 1/8/2022
Internal Plastering 7 1/4/2022 1/11/2022
Fire erection work 10 1/2/2022 1/12/2022
HVAC 10 1/2/2022 1/12/2022
Toilets Waterproofing 7 1/11/2022 1/18/2022
Plumbing 4 1/18/2022 1/22/2022
IPS Flooring 7 1/22/2022 1/29/2022
Window glazing work 10 1/11/2022 1/21/2022
False Ceiling 15 1/18/2022 2/2/2022
POP 7 1/23/2022 1/30/2022
Putty 1st coat 7 1/23/2022 1/30/2022
Tiling works 10 1/23/2022 2/2/2022
Putty 2nd coat 7 1/30/2022 2/6/2022
Primer 4 2/4/2022 2/8/2022
MDF Partition work 20 2/3/2022 2/23/2022
Door frame & fixtures 10 2/3/2022 2/13/2022
Electrical wiring 5 2/3/2022 2/8/2022

Granite activities 5 2/14/2022 2/19/2022


Plumbing Fixtures 5 2/9/2022 2/14/2022
First coat Painting 7 2/20/2022 2/27/2022
IPS Flooring
2nd Coat painting

Vinyl Flooring
Rubber flooring
Full length mirror fixing