3rd Floor Slab Concrete 27-Nov-21 casted on 3rd dec, so delay is 6 day
Terrace floor 14 28-Nov-21 11-Dec-21 casted on 19th dec night, so delay i
Above Terrace 10 12-Dec-21 21-Dec-21
Finishing
Blockwork
1st floor 9 29-Nov-21 8-Dec-21
2nd floor 9 7-Dec-21 16-Dec-21
3rd floor 9 21-Dec-21 30-Dec-21
Above Terrace 7 31-Dec-21 7-Jan-22
External Plastering
South 18 24-Dec-21 11-Jan-22
North 18 26-Dec-21 13-Jan-22
East 13 28-Dec-21 10-Jan-22
West 12 30-Dec-21 11-Jan-22
not completed.
mpleted.
not completed.
Activities Days Start Finish
First Floor
Blockwork 9 12/6/2021 12/15/2021
Electrical Conduiting 10 12/12/2021 12/22/2021
Internal Plastering 7 12/18/2021 12/25/2021
Fire erection work 10 12/15/2021 12/25/2021
HVAC 10 12/15/2021 12/25/2021
Toilets Waterproofing 7 12/25/2021 1/1/2022
Plumbing 4 1/1/2022 1/5/2022
IPS Flooring 7 1/5/2022 1/12/2022
Curtain window (10 No.s) 10 12/25/2021 1/4/2022
False Ceiling 15 1/1/2022 1/16/2022
POP 7 1/6/2022 1/13/2022
Putty 1st coat 7 1/6/2022 1/13/2022
Tiling works 10 1/6/2022 1/16/2022
Putty 2nd coat 7 1/13/2022 1/20/2022
Primer 4 1/18/2022 1/22/2022
MDF Partition work 20 1/17/2022 2/6/2022
Door frame & fixtures 10 1/17/2022 1/27/2022
Electrical wiring 5 1/17/2022 1/22/2022
Vinyl Flooring
Rubber flooring
Full length mirror fixing