Catatan lembur TBK

Surowinoto
no Tanggal mulai selesai scope pekerjaan
1 23/10/2021 08.00 20.00
2 24/10/2021 08.00 20.00 =
3 25/10/2021 17.00 20.00 weekend
4 26/10/2021 17.00 20.00 QC Bending pipe
5 27/10/2021 17.00 20.00
6 28/10/2021 17.00 20.00
7 29/10/2021 17.00 20.00 =
8 30/10/2021 08.00 20.00 Batam
Delevery pipe
9 31/10/2021 08.00 20.00
10 01/11/2021 17.00 00.00 unit dan drawing assy fan
11 02/11/2021 17.00 20.00 unit
12 03/11/2021 17.00 20.00 unit
13 04/11/2021 17.00 22.00 unit
14 05/11/2021 17.00 22.00 unit
15 06/11/2021 08.00 22.00 unit
16 07/11/2021 08.00 00.00 unit
17 08/11/2021 17.00 00.00 unit dan report coating
18 09/11/2021 17.00 01.00 unit dan report coating
19 10/11/2021 17.00 01.00 unit dan report condensor
20 11/11/2021 17.00 01.00 unit dan report condensor
21 12/11/2021 17.00 00.00 unit dan report CT fan
22 13/11/2021 08.00 22.00 unit
23 14/11/2021 08.00 22.00 hydrotest
24 15/11/2021 17.00 23.00 hydrotest
25 16/11/2021 17.00 20.00 hydrotest
26 17/11/2021 17.00 01.00 refactory
27 18/11/2021 17.00 00.00 refactory
28 19/11/2021 17.00 00.00 comisioning
29 20/11/2021 08.00 22.00 comisioning dan rekap absensi
30 21/11/2021 08.00 22.00 comisioning dan report boiler
31 22/11/2021 17.00 20.00 comisioning
32 23/11/2021 17.00 20.00 comisioning
33 24/11/2021 17.00 23.00 comisioning, report ID dan SA