JADWAL PELAKSANAAN

TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
0 TA-NPK1-07-2021 25 days 31/07/21 07:00 24/08/21 23:00
1 PENGAMANAN AREA 2 days 31/07/21 07:00 02/08/21 07:00
2 Shutdown & Pengamanan 1 eday 31/07/21 07:00 01/08/21 07:00 Opr NPK-1
3 Cleaning 2 edays 31/07/21 07:00 02/08/21 07:00 Opr NPK-1
4 Pemasangan scaffolding (R-001, 2 days 31/07/21 07:00 01/08/21 23:00 Beng S3
5 PEKERJAAN PEMELIHARAAN 21 days 02/08/21 07:00 22/08/21 23:00
6 ROTARY DRUM & DRAG CONVEYOR 21 days 02/08/21 07:00 22/08/21 23:00
7 CR-001 (GRANULATOR) - Optimalisasi 300000372647 20 days 02/08/21 07:00 21/08/21 23:00
8 Penggantian rubber lining baru 10 days 02/08/21 07:00 11/08/21 23:00
9 Pasang blower&lampu penerangan 2 hrs 02/08/21 07:00 02/08/21 09:00 List NPK;RPK
10 Pembongkaran rubber liner lama 2,71 days 02/08/21 07:00 04/08/21 18:00
11 Lepas baut&plate klem belt 10 hrs 02/08/21 07:00 02/08/21 18:00 Beng S2 NPK (1)
12 Lepas rubber liner lama 23 hrs 02/08/21 19:00 04/08/21 13:00 Beng S2 NPK (1)
13 Bersihkan shell drum 5 hrs 04/08/21 13:00 04/08/21 18:00 Beng S3
14 Pemasangan rubber liner baru 7,29 days 04/08/21 19:00 11/08/21 23:00
15 Brushing shell 8 hrs 04/08/21 19:00 05/08/21 11:00 Beng S3
16 Coating shell 10 hrs 05/08/21 11:00 05/08/21 23:00 Beng S3
17 Pasang rubber liner baru, baut& klem belt 56 hrs 06/08/21 07:00 09/08/21 23:00 Beng S2 NPK (1)
18 Lepas chute inlet lama 5 hrs 10/08/21 07:00 10/08/21 13:00 Beng S2 NPK (1)
19 Fabrikasi & pasang chute inlet baru 23 hrs 10/08/21 13:00 11/08/21 23:00 Beng S2 NPK (1)
20 Penggantian trunion & cover big gear 5 days 17/08/21 07:00 21/08/21 23:00
21 Pasang support drum sisi outlet 2 hrs 17/08/21 07:00 17/08/21 09:00 Mek NPK
22 Pasang jack pada tyre sisi outlet 2 hrs 17/08/21 09:00 17/08/21 11:00 Mek NPK
23 Lepas trunion sisi outlet 4 hrs 17/08/21 11:00 17/08/21 16:00 Mek NPK
24 Pasang trunion sisi outlet 6 hrs 17/08/21 16:00 17/08/21 23:00 Mek NPK
25 Lepas jack tyre sisi outlet 2 hrs 18/08/21 07:00 18/08/21 09:00 Mek NPK
26 Lepas support drum sisi outlet 2 hrs 18/08/21 09:00 18/08/21 11:00 Mek NPK
27 Perbaikan trunion Sisi Inlet 8 hrs 18/08/21 11:00 18/08/21 21:00 Mek NPK
28 Ganti baut housing trunion 4 hrs 18/08/21 16:00 18/08/21 21:00 Mek NPK
29 Lepas cover big gear lama 4 hrs 18/08/21 21:00 19/08/21 09:00 A2B Galion;Mek NPK
30 Pasang cover big gear baru 26 hrs 19/08/21 09:00 20/08/21 23:00 A2B Galion;Mek NPK
31 Preventive maintenance 1 day 21/08/21 07:00 21/08/21 23:00
32 Ganti Oli Gearbox 2 hrs 21/08/21 07:00 21/08/21 09:00 Mek NPK
33 Ganti Oil Big Gear 2 hrs 21/08/21 09:00 21/08/21 11:00 Mek NPK
34 Ganti Oil Fluid Coupling 1 hr 21/08/21 11:00 21/08/21 13:00 Mek NPK
35 Ganti Rubber Coupling Fluid Coupling 2 hrs 21/08/21 13:00 21/08/21 15:00 Mek NPK
36 CEK&GREASING BEARING TRUNION INLET 2 hrs 21/08/21 15:00 21/08/21 17:00 Mek NPK
37 CEK&GREASING BEARING PINION GEAR 2 hrs 21/08/21 17:00 21/08/21 20:00 Mek NPK
38 CEK&GREASING BEARING TRUSH ROLLER 2 hrs 21/08/21 20:00 21/08/21 22:00 Mek NPK
39 ISI RESERVOIR OLI TETES 1 hr 21/08/21 22:00 21/08/21 23:00 Mek NPK
40 PM motor 1 hr 21/08/21 22:00 21/08/21 23:00 List NPK
41 RBP-5047A-19 Modifikasi Line Slurry 911000051285 2 days 12/08/21 07:00 13/08/21 23:00
42 Fabrikasi Modifikasi Line Slurry R001 2 days 12/08/21 07:00 13/08/21 23:00 Beng S2 NPK (1)
43 CR-002 (DRYER) 14 days 09/08/21 07:00 22/08/21 23:00
44 Optimalisasi 300000395216 1 day 22/08/21 07:00 22/08/21 23:00
45 GANTI OLI GEARBOX PRIMARY 2 hrs 22/08/21 07:00 22/08/21 09:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
46 GANTI OLI GEARBOX AUXILIARY 2 hrs 22/08/21 09:00 22/08/21 11:00 Mek NPK
47 GANTI OLI BIG GEAR 2 hrs 22/08/21 11:00 22/08/21 14:00 Mek NPK
48 GANTI OLI FLUID KOPLING 2 hrs 22/08/21 14:00 22/08/21 16:00 Mek NPK
49 GANTI RUBBER KOPLING FLUID KOPLING 2 hrs 22/08/21 16:00 22/08/21 18:00 Mek NPK
50 CEK&GREASING BEARING TRUNION 1 hr 22/08/21 19:00 22/08/21 20:00 Mek NPK
51 CEK&GREASING BEARING PINION GEAR 1 hr 22/08/21 20:00 22/08/21 21:00 Mek NPK
52 CEK&GREASING BEARING TRUSH ROLLER 1 hr 22/08/21 21:00 22/08/21 22:00 Mek NPK
53 ISI RESERVOIR OLI TETES 1 hr 22/08/21 22:00 22/08/21 23:00 Mek NPK
54 PM main & assistant motor 1 hr 22/08/21 22:00 22/08/21 23:00 List NPK
55 RBP-5048A-19 Hammer Dryer 300000374846 7 days 09/08/21 07:00 15/08/21 23:00
56 Pengamanan area 1 hr 09/08/21 07:00 09/08/21 08:00 Opr NPK-1
57 Pasang Scafolding 4 hrs 09/08/21 07:00 09/08/21 11:00 Beng S3
58 Pasang Hammer baru 90 hrs 09/08/21 11:00 15/08/21 18:00 Beng S2 NPK (2)
59 Inspection Check 2 hrs 15/08/21 19:00 15/08/21 21:00 InsP NPK
60 Bongkar Scafolding 2 hrs 15/08/21 21:00 15/08/21 23:00 Beng S3
61 CR-003 (COOLER) - Optimalisasi 200000201472 8 days 02/08/21 07:00 09/08/21 23:00
62 PENGGANTIAN TYER&TRUNION SISI OUTLET 8 days 02/08/21 07:00 09/08/21 23:00
63 Lepas Dust box sisi outlet 1 day 02/08/21 07:00 02/08/21 23:00 Beng S2 NPK (2)
64 Lepas cover big gear 5 hrs 03/08/21 07:00 03/08/21 13:00 A2B Galion;Mek NPK
65 Lepas thrust roller sisi outlet 4 hrs 03/08/21 13:00 03/08/21 17:00 Mek NPK
66 pasang spesial tool untuk angkat drum 6 hrs 03/08/21 17:00 04/08/21 08:00 A2B Galion;Mek NPK
67 Pasang stopper tyre sisi dalam 5 hrs 04/08/21 08:00 04/08/21 14:00 Beng S2 NPK (2)
68 Lepas shoe tyre 1 day 04/08/21 14:00 05/08/21 14:00 Mek NPK;Beng S2 NPK (2)
69 Lepas tyre lama 1 day 05/08/21 14:00 06/08/21 14:00 A2B Galion;Mek NPK
70 Lepas trunion sisi outlet 5 hrs 06/08/21 14:00 06/08/21 20:00 Mek NPK
71 Pasang trunion baru sisi outlet 6 hrs 06/08/21 20:00 07/08/21 10:00 Mek NPK
72 Pasang tyre baru 1 day 07/08/21 10:00 08/08/21 10:00 A2B Galion;Mek NPK
73 Pasang shoe dan setting round out radial axial tyre 5 hrs 08/08/21 10:00 08/08/21 16:00 Mek NPK;Beng S2 NPK (2)
74 Pasang thrust roller sisi out 5 hrs 08/08/21 16:00 08/08/21 22:00 Mek NPK
75 Turunkan shell 5 hrs 08/08/21 22:00 09/08/21 11:00 A2B Galion
76 Pasang cover big gear dan dust box outlet 10 hrs 09/08/21 11:00 09/08/21 23:00 A2B Galion;Mek NPK
77 Preventive maintenance 1 day 09/08/21 07:00 09/08/21 23:00
78 GANTI TEFLON KOPLING 4 hrs 09/08/21 07:00 09/08/21 11:00 Mek NPK
79 CEK&GREASING BEARING TRUNION 3 hrs 09/08/21 11:00 09/08/21 15:00 Mek NPK
80 CEK&GREASING BEARING PINION GEAR 3 hrs 09/08/21 15:00 09/08/21 18:00 Mek NPK
81 CEK&GREASING BEARING TRUSH ROLLER 2 hrs 09/08/21 19:00 09/08/21 21:00 Mek NPK
82 ISI RESERVOIR OLI TETES 2 hrs 09/08/21 21:00 09/08/21 23:00 Mek NPK
83 PM motor 1 hr 09/08/21 21:00 09/08/21 22:00 List NPK
84 CR-004 (COATER) 16 days 02/08/21 07:00 17/08/21 23:00
85 Penggantian Linning 300000376904 8 days 02/08/21 07:00 09/08/21 23:00
86 Pasang blower&lampu penerangan 2 hrs 02/08/21 07:00 02/08/21 09:00 List NPK;RPK
87 Bongkar liner stainless steel lama 3 days 02/08/21 07:00 04/08/21 23:00
88 Lepas baut& klem siku 8 hrs 02/08/21 07:00 02/08/21 16:00 Beng S2 NPK (3)
89 Lepas liner SS lama 26 hrs 02/08/21 16:00 04/08/21 14:00 Beng S2 NPK (3)
90 Pembersihan shell drum 8 hrs 04/08/21 14:00 04/08/21 23:00 Beng S3
91 Pasang liner stainless steel 5 days 05/08/21 07:00 09/08/21 23:00
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
92 Brushing shell 14 hrs 05/08/21 07:00 05/08/21 23:00 Beng S3
93 Pasang liner stainless steel, baut& klem siku 4 days 06/08/21 07:00 09/08/21 23:00 Beng S2 NPK (3)
94 Optimasasi 300000390517 8 days 10/08/21 07:00 17/08/21 23:00
95 Pengamanan area 2 hrs 10/08/21 07:00 10/08/21 09:00 Opr NPK-1
96 Lepas dustbox inlet/outlet 1 day 10/08/21 07:00 10/08/21 23:00 Mek NPK;Beng S2 NPK (3)
97 Pasang support drum sisi outlet 4 hrs 11/08/21 07:00 11/08/21 11:00 Mek NPK
98 Pasang jack pada tyre sisi outlet 4 hrs 11/08/21 11:00 11/08/21 16:00 Mek NPK
99 Lepas trunion sisi outlet 6 hrs 11/08/21 16:00 11/08/21 23:00 Mek NPK
100 Pasang trunion ex-repair 1 day 12/08/21 07:00 12/08/21 23:00 Mek NPK
101 Ganti baut housing trunion 3 hrs 12/08/21 20:00 12/08/21 23:00 Mek NPK
102 Lepas jack tyre sisi outlet 4 hrs 13/08/21 07:00 13/08/21 11:00 Mek NPK
103 Lepas support drum sisi outlet 4 hrs 13/08/21 07:00 13/08/21 11:00 Mek NPK
104 Pasang support drum sisi inlet 6 hrs 13/08/21 11:00 13/08/21 18:00 Mek NPK
105 Pasang jack pada tyre sisi inlet 5 hrs 13/08/21 19:00 14/08/21 08:00 Mek NPK
106 Lepas trunion sisi inlet 8 hrs 14/08/21 08:00 14/08/21 17:00 Mek NPK
107 Pasang trunion sisi inlet baru 1 day 14/08/21 17:00 15/08/21 17:00 Mek NPK
108 Ganti baut housing trunion 3 hrs 15/08/21 14:00 15/08/21 17:00 Mek NPK
109 Lepas jack tyre sisi inlet 4 hrs 15/08/21 17:00 15/08/21 22:00 Mek NPK
110 Lepas support drum sisi inlet 4 hrs 15/08/21 17:00 15/08/21 22:00 Mek NPK
111 Lepas trush roller unit 6 hrs 15/08/21 22:00 16/08/21 13:00 Mek NPK
112 Pasang trush roller unit baru 4 hrs 16/08/21 13:00 16/08/21 17:00 Mek NPK
113 Ganti baut trush roller 3 hrs 16/08/21 14:00 16/08/21 17:00 Mek NPK
114 Ganti teflon coupling motor to gearbox 3 hrs 16/08/21 17:00 16/08/21 21:00 Mek NPK
115 Ganti oli gearbox 2 hrs 16/08/21 21:00 16/08/21 23:00 Mek NPK
116 Isi reservoir oli tetes 2 hrs 16/08/21 21:00 16/08/21 23:00 Mek NPK
117 Pasang dustbox & ganti penyangga sisi Inlet 1 day 17/08/21 07:00 17/08/21 23:00 Beng S2 NPK (3)
118 PM motor 1 hr 17/08/21 07:00 17/08/21 08:00 List NPK
119 CL-001 (DRAG CONVEYOR) 17 days 03/08/21 07:00 19/08/21 23:00
120 Optimalisasi 500000003874 15 days 04/08/21 07:00 18/08/21 23:00
121 Lepas power perkabelan listrik 1 hr 04/08/21 07:00 04/08/21 08:00 List NPK
122 Lepas casing tail 4 hrs 04/08/21 08:00 04/08/21 13:00 Mek NPK
123 Lepas casing upper drive 5 hrs 04/08/21 13:00 04/08/21 18:00 Mek NPK
124 Potong chain sisi drive 2 hrs 04/08/21 19:00 04/08/21 21:00 Beng S2 NPK (4)
125 Lepas Chain& Lamela 8 hrs 04/08/21 19:00 05/08/21 11:00 Mek NPK
126 Lepas sprocket drive& tail 6 hrs 05/08/21 11:00 05/08/21 18:00 Mek NPK
127 Lepas bearing sprocket drive& tail 4 hrs 05/08/21 19:00 05/08/21 23:00 Mek NPK
128 Cleaning 8 ehrs 05/08/21 23:00 06/08/21 07:00 Opr NPK-1
129 Lepas bottom casing 1,5 days 06/08/21 07:00 07/08/21 15:00 Beng S2 NPK (4)
130 Lepas rail lama 1,5 days 07/08/21 15:00 08/08/21 23:00 Beng S2 NPK (4)
131 Pasang rail baru& setting 2 days 09/08/21 07:00 10/08/21 23:00 Mek NPK;InsP NPK
132 Pasang bottom casing baru 2 days 11/08/21 07:00 12/08/21 23:00 Beng S2 NPK (4)
133 Pasang bearing sprocket drive& tail baru 10 hrs 13/08/21 07:00 13/08/21 18:00 Mek NPK
134 Pasang sprocket drive& tail baru 12 hrs 13/08/21 19:00 14/08/21 16:00 Mek NPK
135 Pasang chain baru 1 day 14/08/21 16:00 15/08/21 16:00 Mek NPK
136 Pasang lamela baru 3 days 15/08/21 16:00 18/08/21 16:00 Mek NPK
137 Pasang power perkabelan listrik 1 hr 18/08/21 16:00 18/08/21 17:00 List NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
138 PM & test uncouple motor 1 hr 18/08/21 17:00 18/08/21 18:00 InsP NPK;Opr NPK-1;List NPK
139 Couple drive to gearbox 4 hrs 18/08/21 19:00 18/08/21 23:00 Mek NPK
140 Modifikasi Chute Inlet 500000004047 17 days 03/08/21 07:00 19/08/21 23:00
141 Bongkar chute inlet lama 7 hrs 03/08/21 07:00 03/08/21 15:00 Beng S2 NPK (4)
142 Bongkar chute outlet 7 hrs 03/08/21 15:00 03/08/21 23:00 Beng S2 NPK (4)
143 Fabrikasi chute outlet baru 2 days 04/08/21 07:00 05/08/21 23:00 Beng S2 NPK (4)
144 fabrikasi chute inlet baru 2 days 06/08/21 07:00 07/08/21 23:00 Beng S2 NPK (4)
145 Pasang chute outlet baru 10 hrs 18/08/21 16:00 19/08/21 11:00 Beng S2 NPK (4)
146 pasang chute inlet baru 10 hrs 19/08/21 11:00 19/08/21 23:00 Beng S2 NPK (4)
147 FAN 17 days 03/08/21 07:00 19/08/21 23:00
148 CC-003 (DRYER FAN) - Penggantian Unit Fan 300000374845 4 days 03/08/21 07:00 06/08/21 23:00
149 Pengamanan area 2 hrs 03/08/21 07:00 03/08/21 09:00 Opr NPK-1
150 Lepas power perkabelan listrik 2 hrs 03/08/21 07:00 03/08/21 09:00 List NPK
151 Lepas v-belt 2 hrs 03/08/21 09:00 03/08/21 11:00 Mek NPK
152 Lepas baut inlet fan 3 hrs 03/08/21 11:00 03/08/21 15:00 Mek NPK
153 Lepas baut outlet fan 3 hrs 03/08/21 15:00 03/08/21 18:00 Mek NPK
154 Lepas unit ID fan existing 10 hrs 03/08/21 19:00 04/08/21 14:00 Mek NPK
155 Grouting pondasi baseplate 8 hrs 04/08/21 14:00 04/08/21 23:00 Jaspil
156 Angkat unit ID fan baru 2 hrs 05/08/21 07:00 05/08/21 09:00 A2B Galion
157 PASANG UNIT ID FAN BARU 1 day 05/08/21 09:00 06/08/21 09:00 A2B Galion;Mek NPK
158 Pasang baut inlet fan 4 hrs 06/08/21 09:00 06/08/21 14:00 Mek NPK
159 Pasang baut outlet fan 4 hrs 06/08/21 14:00 06/08/21 18:00 Mek NPK
160 Pasang power perkabelan listrik 2 hrs 06/08/21 19:00 06/08/21 21:00 List NPK
161 PM motor 2 hrs 06/08/21 19:00 06/08/21 21:00 List NPK
162 Final check & running test 2 hrs 06/08/21 21:00 06/08/21 23:00 InsP NPK;Opr NPK-1
163 CC-004 (GRANULATOR FAN) - Penggantian rotor fan 300000656388 3 days 07/08/21 07:00 09/08/21 23:00
164 Pengamanan area 2 hrs 07/08/21 07:00 07/08/21 09:00 Opr NPK-1
165 Lepas power perkabelan listrik 2 hrs 07/08/21 07:00 07/08/21 09:00 List NPK
166 Lepas v-belt 2 hrs 07/08/21 09:00 07/08/21 11:00 Mek NPK
167 Lepas baut cover fan 4 hrs 07/08/21 11:00 07/08/21 16:00 Mek NPK
168 Angkat cover fan 2 hrs 07/08/21 16:00 07/08/21 18:00 A2B Galion
169 Lepas unit rotor fan existing 4 hrs 07/08/21 19:00 07/08/21 23:00 A2B Galion;Mek NPK
170 Pasang rotor unit fan baru 6 hrs 08/08/21 07:00 08/08/21 14:00 A2B Galion;Mek NPK
171 Alignment rotor to motor 8 hrs 08/08/21 14:00 08/08/21 23:00 Mek NPK
172 Pasang v-belt 3 hrs 09/08/21 07:00 09/08/21 10:00 Mek NPK
173 Angkat pasang cover fan 3 hrs 09/08/21 10:00 09/08/21 14:00 A2B Galion
174 Ikat baut cover fan 4 hrs 09/08/21 14:00 09/08/21 18:00 Mek NPK
175 Pasang power perkabelan listrik 2 hrs 09/08/21 19:00 09/08/21 21:00 List NPK
176 PM motor 2 hrs 09/08/21 19:00 09/08/21 21:00 List NPK
177 Final check & running test 2 hrs 09/08/21 21:00 09/08/21 23:00 InsP NPK;Opr NPK-1
178 CC-005 (COOLER FAN) - Penggantian Unit Rotor Ex-repair 200000201492 6 days 10/08/21 07:00 15/08/21 23:00
179 Pengamanan area 2 hrs 10/08/21 07:00 10/08/21 09:00 Opr NPK-1
180 Lepas power perkabelan listrik 2 hrs 10/08/21 07:00 10/08/21 09:00 List NPK
181 Lepas v-belt 2 hrs 10/08/21 09:00 10/08/21 11:00 Mek NPK
182 Lepas baut inlet fan 3 hrs 10/08/21 11:00 10/08/21 15:00 Mek NPK
183 Lepas baut outlet fan 3 hrs 10/08/21 15:00 10/08/21 18:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
184 Lepas baut cover fan 4 hrs 10/08/21 19:00 10/08/21 23:00 Mek NPK
185 Angkat cover fan 2 hrs 11/08/21 07:00 11/08/21 09:00 Mek NPK
186 Lepas rotor unit 2 hrs 11/08/21 09:00 11/08/21 11:00 Mek NPK
187 Lepas bottom casing 2 hrs 11/08/21 11:00 11/08/21 14:00 Mek NPK
188 Penggantian Baseplate& Damper 300000376044 2 days 11/08/21 14:00 13/08/21 14:00
189 Ganti baseplate 1 day 11/08/21 14:00 12/08/21 14:00 Beng S2 NPK (2)
190 Ganti damper 1 day 12/08/21 14:00 13/08/21 14:00 Beng S2 NPK (2)
191 Pasang rotor unit baru (ex-repair)& ganti oli bearing 6 hrs 13/08/21 14:00 13/08/21 21:00 Mek NPK
192 Alignment rotor to motor 4 hrs 13/08/21 21:00 14/08/21 09:00 Mek NPK
193 Balancing rotor 4 hrs 14/08/21 09:00 14/08/21 14:00 Mek NPK
194 Angkat cover fan 2 hrs 14/08/21 14:00 14/08/21 16:00 A2B Galion
195 Ikat baut cover ID fan 4 hrs 14/08/21 16:00 14/08/21 21:00 Mek NPK
196 Ganti pulley motor 4 hrs 14/08/21 21:00 15/08/21 09:00 Mek NPK
197 Ganti pulley rotor 4 hrs 15/08/21 09:00 15/08/21 14:00 Mek NPK
198 Pasang v-belt baru 2 hrs 15/08/21 14:00 15/08/21 16:00 Mek NPK
199 Pasang power perkabelan listrik 2 hrs 15/08/21 16:00 15/08/21 18:00 List NPK
200 PM motor 2 hrs 15/08/21 19:00 15/08/21 21:00 List NPK
201 Final check & running test 2 hrs 15/08/21 21:00 15/08/21 23:00 Opr NPK-1
202 CC-006 (DE-DUSTER FAN) - Upgrade Unit Fan 500000003994 4 days 16/08/21 07:00 19/08/21 23:00
203 Pengamanan area 2 hrs 16/08/21 07:00 16/08/21 09:00 Opr NPK-1
204 Lepas power perkabelan listrik & PM motor 2 hrs 16/08/21 07:00 16/08/21 09:00 List NPK
205 Lepas v-belt 2 hrs 16/08/21 09:00 16/08/21 11:00 Mek NPK
206 Lepas baut inlet fan 2 hrs 16/08/21 11:00 16/08/21 14:00 Mek NPK
207 Lepas baut outlet fan 2 hrs 16/08/21 14:00 16/08/21 16:00 Mek NPK
208 Lepas unit ID fan existing 10 hrs 16/08/21 16:00 17/08/21 11:00 Mek NPK
209 Grouting pondasi baseplate 8 hrs 17/08/21 11:00 17/08/21 21:00 Jaspil
210 Angkat unit ID fan baru 2 hrs 17/08/21 21:00 17/08/21 23:00 A2B Crane
211 Pasang unit ID fan baru (MIR) 1 day 18/08/21 07:00 18/08/21 23:00 A2B Crane;Mek NPK
212 Pasang baut inlet fan 3 hrs 19/08/21 07:00 19/08/21 10:00 Mek NPK
213 Pasang baut outlet fan 3 hrs 19/08/21 10:00 19/08/21 14:00 Mek NPK
214 Ganti pulley motor 3 hrs 19/08/21 14:00 19/08/21 17:00 Mek NPK
215 Ganti pulley rotor 2 hrs 19/08/21 17:00 19/08/21 20:00 Mek NPK
216 Pasang v-belt 1 hr 19/08/21 20:00 19/08/21 21:00 Mek NPK
217 Pasang power perkabelan listrik 1 hr 19/08/21 21:00 19/08/21 22:00 List NPK
218 Final check & running test 1 hr 19/08/21 22:00 19/08/21 23:00 Opr NPK-1
219 CONVEYOR 21 days 02/08/21 07:00 22/08/21 23:00
220 CL-002-A (WEIGHT CONVEYOR) - Pemasangan Flow Switch 500000003849 1,5 days 17/08/21 07:00 18/08/21 15:00
221 Buat support kabel tray & flow switch 6 hrs 17/08/21 07:00 17/08/21 14:00 Jaspil;List NPK;Beng S2 NPK (3)
222 Pasang kabel kabel tray & support flow switch 4 hrs 17/08/21 14:00 17/08/21 18:00 Beng S2 NPK (3)
223 Ramset support flow switch 2 hrs 17/08/21 16:00 17/08/21 18:00 Jaspil
224 Pasang flow switch 2 hrs 17/08/21 19:00 17/08/21 21:00 InsT NPK
225 Pasang Juction Box Flow switch&Acc 2 hrs 17/08/21 21:00 17/08/21 23:00 InsT NPK
226 Penarikan Kabel dr flow switch ke JB 2 hrs 18/08/21 07:00 18/08/21 09:00 InsT NPK
227 Taging dan Terminasi kabel di back panel 2 hrs 18/08/21 09:00 18/08/21 11:00 InsT NPK
228 Buat Program ladder di PLC dan popup HMI 2 hrs 18/08/21 11:00 18/08/21 14:00 InsT NPK
229 Final check 1 hr 18/08/21 14:00 18/08/21 15:00 Opr NPK-1;InsT NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
230 PM motor 1 hr 17/08/21 07:00 17/08/21 08:00 List NPK
231 CL-002-B (WEIGHT CONVEYOR) - Pemasangan Flow Switch 500000003850 1,5 days 18/08/21 07:00 19/08/21 15:00
232 Buat support kabel tray & flow switch 6 hrs 18/08/21 07:00 18/08/21 14:00 Jaspil;List NPK;Beng S2 NPK (3)
233 Pasang kabel kabel tray & support flow switch 4 hrs 18/08/21 14:00 18/08/21 18:00 Beng S2 NPK (3)
234 Ramset support flow switch 2 hrs 18/08/21 16:00 18/08/21 18:00 Jaspil
235 Pasang flow switch 2 hrs 18/08/21 19:00 18/08/21 21:00 InsT NPK
236 Pasang Juction Box Flow switch&Acc 2 hrs 18/08/21 21:00 18/08/21 23:00 InsT NPK
237 Penarikan Kabel dr flow switch ke JB 2 hrs 19/08/21 07:00 19/08/21 09:00 InsT NPK
238 Taging dan Terminasi kabel di back panel 2 hrs 19/08/21 09:00 19/08/21 11:00 InsT NPK
239 Buat Program ladder di PLC dan popup HMI 2 hrs 19/08/21 11:00 19/08/21 14:00 InsT NPK
240 Final check 1 hr 19/08/21 14:00 19/08/21 15:00 Opr NPK-1;InsT NPK
241 PM motor 1 hr 18/08/21 07:00 18/08/21 08:00 List NPK
242 CL-002-C (WEIGHT CONVEYOR) 3 days 17/08/21 07:00 19/08/21 23:00
243 Penggantian Driver Pulley 500000003871 2 days 17/08/21 07:00 18/08/21 23:00
244 Pengamanan area 2 hrs 17/08/21 07:00 17/08/21 09:00 Opr NPK-1
245 Lepas power perkabelan listrik 2 hrs 17/08/21 07:00 17/08/21 09:00 List NPK
246 Lepas motorise pulley 2 hrs 17/08/21 09:00 17/08/21 11:00 Mek NPK
247 Pasang bearing drive pulley baru 2 hrs 17/08/21 11:00 17/08/21 14:00 Mek NPK
248 Pasang drive pulley baru 2 hrs 17/08/21 14:00 17/08/21 16:00 Mek NPK
249 Ganti baut housing drive 1 hr 17/08/21 16:00 17/08/21 17:00 Mek NPK
250 Pasang gearbox bevel helical baru 2 hrs 17/08/21 17:00 17/08/21 20:00 Mek NPK
251 Pasang gearbox intermediate baru 2 hrs 17/08/21 20:00 17/08/21 22:00 Mek NPK
252 Pasang&cople motor to gearbox 2 hrs 17/08/21 22:00 18/08/21 08:00 Mek NPK
253 Lepas roller yang macet 1 hr 18/08/21 08:00 18/08/21 09:00 Mek NPK
254 Pasang roller yang baru 2 hrs 18/08/21 09:00 18/08/21 11:00 Mek NPK
255 Lepas bearing tail pulley 2 hrs 18/08/21 11:00 18/08/21 14:00 Mek NPK
256 Pasang bearing tail pulley baru 2 hrs 18/08/21 14:00 18/08/21 16:00 Mek NPK
257 Ganti baut sambungan frame tail 1 hr 18/08/21 16:00 18/08/21 17:00 Mek NPK
258 Ganti baut adjuster 1 hr 18/08/21 16:00 18/08/21 17:00 Mek NPK
259 Lepas rubber seal skirtboard 2 hrs 18/08/21 17:00 18/08/21 20:00 Mek NPK
260 Pasang rubber seal skirtboard 2 hrs 18/08/21 20:00 18/08/21 22:00 Mek NPK
261 Pasang power perkabelan listrik & PM motor 2 hrs 18/08/21 20:00 18/08/21 22:00 List NPK
262 Final check 1 hr 18/08/21 22:00 18/08/21 23:00 Opr NPK-1;InsP NPK
263 Pemasangan Flow Switch 500000003851 1 day 19/08/21 07:00 19/08/21 23:00
264 Buat support kabel tray & flow switch 6 hrs 19/08/21 07:00 19/08/21 14:00 Jaspil;List NPK;Beng S2 NPK (3)
265 Pasang kabel kabel tray & support flow switch 4 hrs 19/08/21 14:00 19/08/21 18:00 Beng S2 NPK (3)
266 Ramset support flow switch 2 hrs 19/08/21 19:00 19/08/21 21:00 Jaspil
267 Pasang flow switch 2 hrs 19/08/21 21:00 19/08/21 23:00 InsT NPK
268 CL-002-D (WEIGHT CONVEYOR) 3 days 19/08/21 07:00 21/08/21 23:00
269 Penggantian Driver Pulley 500000003872 2 days 19/08/21 07:00 20/08/21 23:00
270 Pengamanan area 2 hrs 19/08/21 07:00 19/08/21 09:00 Opr NPK-1
271 Lepas power perkabelan listrik 2 hrs 19/08/21 07:00 19/08/21 09:00 List NPK
272 Lepas motorise pulley 2 hrs 19/08/21 09:00 19/08/21 11:00 Mek NPK
273 Pasang bearing drive pulley baru 2 hrs 19/08/21 11:00 19/08/21 14:00 Mek NPK
274 Pasang drive pulley baru 2 hrs 19/08/21 14:00 19/08/21 16:00 Mek NPK
275 Ganti baut housing drive 1 hr 19/08/21 16:00 19/08/21 17:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
276 Pasang gearbox bevel helical baru 2 hrs 19/08/21 17:00 19/08/21 20:00 Mek NPK
277 Pasang gearbox intermediate baru 2 hrs 19/08/21 20:00 19/08/21 22:00 Mek NPK
278 Pasang&cople motor to gearbox 2 hrs 19/08/21 22:00 20/08/21 08:00 Mek NPK
279 Lepas roller yang macet 1 hr 20/08/21 08:00 20/08/21 09:00 Mek NPK
280 Pasang roller yang baru 2 hrs 20/08/21 09:00 20/08/21 11:00 Mek NPK
281 Lepas bearing tail pulley 2 hrs 20/08/21 11:00 20/08/21 14:00 Mek NPK
282 Pasang bearing tail pulley baru 2 hrs 20/08/21 14:00 20/08/21 16:00 Mek NPK
283 Ganti baut sambungan frame tail 1 hr 20/08/21 16:00 20/08/21 17:00 Mek NPK
284 Ganti baut adjuster 1 hr 20/08/21 16:00 20/08/21 17:00 Mek NPK
285 Lepas rubber seal skirtboard 2 hrs 20/08/21 17:00 20/08/21 20:00 Mek NPK
286 Pasang rubber seal skirtboard 2 hrs 20/08/21 20:00 20/08/21 22:00 Mek NPK
287 Pasang power perkabelan listrik & PM motor 2 hrs 20/08/21 20:00 20/08/21 22:00 List NPK
288 Final check 1 hr 20/08/21 22:00 20/08/21 23:00 Opr NPK-1;InsP NPK
289 Pemasangan Flow Switch 500000003852 1 day 21/08/21 07:00 21/08/21 23:00
290 Buat dan Pasang support kabel tray 6 hrs 21/08/21 07:00 21/08/21 14:00 Jaspil;List NPK;Beng S2 NPK (3
291 Buat dan Pasang support flow switch 4 hrs 21/08/21 14:00 21/08/21 18:00 Beng S2 NPK (3)
292 Ramset support flow switch 2 hrs 21/08/21 19:00 21/08/21 21:00 Jaspil
293 Pasang flow switch 2 hrs 21/08/21 21:00 21/08/21 23:00 InsT NPK
294 CL-002-F (WEIGHT CONVEYOR) 2 days 21/08/21 07:00 22/08/21 23:00
295 Penggantian Drive Pulley 500000003873 2 days 21/08/21 07:00 22/08/21 23:00
296 Pengamanan area 2 hrs 21/08/21 07:00 21/08/21 09:00 Opr NPK-1
297 Lepas power perkabelan listrik 2 hrs 21/08/21 07:00 21/08/21 09:00 List NPK
298 Lepas motorise pulley 2 hrs 21/08/21 09:00 21/08/21 11:00 Mek NPK
299 Pasang bearing drive pulley baru 2 hrs 21/08/21 11:00 21/08/21 14:00 Mek NPK
300 Pasang drive pulley baru 2 hrs 21/08/21 14:00 21/08/21 16:00 Mek NPK
301 Ganti baut housing drive 1 hr 21/08/21 16:00 21/08/21 17:00 Mek NPK
302 Pasang gearbox bevel helical baru 2 hrs 21/08/21 17:00 21/08/21 20:00 Mek NPK
303 Pasang gearbox intermediate baru 2 hrs 21/08/21 20:00 21/08/21 22:00 Mek NPK
304 Pasang&cople motor to gearbox 2 hrs 21/08/21 22:00 22/08/21 08:00 Mek NPK
305 Lepas roller yang macet 1 hr 22/08/21 08:00 22/08/21 09:00 Mek NPK
306 Pasang roller yang baru 2 hrs 22/08/21 09:00 22/08/21 11:00 Mek NPK
307 Lepas bearing tail pulley 2 hrs 22/08/21 11:00 22/08/21 14:00 Mek NPK
308 Pasang bearing tail pulley baru 2 hrs 22/08/21 14:00 22/08/21 16:00 Mek NPK
309 Ganti baut sambungan frame tail 1 hr 22/08/21 16:00 22/08/21 17:00 Mek NPK
310 Ganti baut adjuster 1 hr 22/08/21 16:00 22/08/21 17:00 Mek NPK
311 Lepas rubber seal skirtboard 2 hrs 22/08/21 17:00 22/08/21 20:00 Mek NPK
312 Pasang rubber seal skirtboard 2 hrs 22/08/21 20:00 22/08/21 22:00 Mek NPK
313 Pasang power perkabelan listrik & PM motor 2 hrs 22/08/21 20:00 22/08/21 22:00 List NPK
314 Final check 1 hr 22/08/21 22:00 22/08/21 23:00 Opr NPK-1;InsP NPK
315 Pemasangan Flow Switch 500000003853 1 day 22/08/21 07:00 22/08/21 23:00
316 Buat dan Pasang support kabel tray 6 hrs 22/08/21 07:00 22/08/21 14:00 Jaspil;List NPK;Beng S2 NPK
317 Buat dan Pasang support flow switch 4 hrs 22/08/21 14:00 22/08/21 18:00 Beng S2 NPK (3)
318 Ramset support flow switch 2 hrs 22/08/21 19:00 22/08/21 21:00 Jaspil
319 Pasangflow switch 2 hrs 22/08/21 21:00 22/08/21 23:00 InsT NPK
320 CL-007 (GRANULATOR OUTLET CONVEYOR) - OPTIMALISASI 300000636685 17 days 02/08/21 07:00 18/08/21 23:00
321 Un Install Existing Conveyor 3 days 02/08/21 07:00 04/08/21 23:00
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
322 Dismantling Mechanical Equipment 3 days 02/08/21 07:00 04/08/21 23:00
323 Lepas kelistrikan 2 hrs 02/08/21 07:00 02/08/21 09:00 List NPK
324 Lepas primary scrapper & gearbox & motor 4 hrs 02/08/21 07:00 02/08/21 11:00 Mek NPK;List NPK
325 Lepas belt conveyor 5 hrs 02/08/21 11:00 02/08/21 17:00 Mek NPK
326 Lepas drive pulley 3 hrs 02/08/21 17:00 02/08/21 21:00 Mek NPK;A2B Galion
327 Lepas tail pulley 2 hrs 02/08/21 21:00 02/08/21 23:00 Mek NPK;A2B Galion
328 Lepas bend pulley 2 hrs 03/08/21 07:00 03/08/21 09:00 Mek NPK;A2B Galion
329 Lepas wing pulley 2 hrs 03/08/21 09:00 03/08/21 11:00 Mek NPK;A2B Galion
330 Lepas rubber seal dan skirt board 2 hrs 03/08/21 11:00 03/08/21 14:00 Mek NPK
331 Cek motor di bengkel listrik 8 hrs 02/08/21 11:00 02/08/21 21:00 Beng Listrik
332 Dismantling Frame Conveyor,Support,Platform 2 days 03/08/21 07:00 04/08/21 23:00 A2B Galion;Beng S2 NPK (5)
333 Install New Conveyor 14 days 05/08/21 07:00 18/08/21 23:00
334 Preparation Existing Area 3 hrs 05/08/21 07:00 05/08/21 10:00 Opr NPK-1;Jaspil
335 Install Scapolding/reposisi 4 hrs 05/08/21 10:00 05/08/21 15:00 Beng S3
336 Install New Support 1 day 05/08/21 15:00 06/08/21 15:00 Beng S2 NPK (5)
337 Erection new Frame Conveyor 3 days 06/08/21 15:00 09/08/21 15:00 Mek NPK;A2B Galion;Beng S2 NPK (5)
338 Install Platform & ladder new 2 days 09/08/21 15:00 11/08/21 15:00 A2B Galion;Beng S2 NPK (5)
339 Setting alignment 1 day 11/08/21 15:00 12/08/21 15:00 Mek NPK;Beng S2 NPK (5)
340 Install Mechanical Equipment 6,36 days 12/08/21 15:00 18/08/21 21:00
341 Pasang drive pulley 6 hrs 12/08/21 15:00 12/08/21 22:00 Mek NPK;A2B Galion
342 Pasang tail pulley 4 hrs 12/08/21 22:00 13/08/21 10:00 Mek NPK;A2B Galion
343 Pasang bend pulley 8 hrs 13/08/21 10:00 13/08/21 20:00 Mek NPK;A2B Galion
344 Pasang wing pulley 6 hrs 13/08/21 20:00 14/08/21 10:00 Mek NPK;A2B Galion
345 Pasang bracket dan setting 1 day 14/08/21 10:00 15/08/21 10:00 Mek NPK
346 Pasang roller idler, impact, return 6 hrs 14/08/21 20:00 15/08/21 10:00 Mek NPK
347 Pasang base plate, gearbox unit (ganti oli) & motor 2 days 15/08/21 10:00 17/08/21 10:00 Mek NPK;A2B Galion;Beng S2 NPK (5);List N
348 Pasang belt conveyor 1 day 17/08/21 10:00 18/08/21 10:00 Mek NPK
349 Pasang primary scrapper 5 hrs 18/08/21 10:00 18/08/21 16:00 Mek NPK
350 Pasang skirt board dan rubber seal 4 hrs 18/08/21 16:00 18/08/21 21:00 Mek NPK
351 Pasang power perkabelan listrik & PM motor 2 hrs 18/08/21 16:00 18/08/21 18:00 List NPK
352 Final check 2 hrs 18/08/21 21:00 18/08/21 23:00 InsP NPK
353 CL-008 (DRYER OUTLET CONVEYOR) - Optimalisasi 300000397049 4 days 19/08/21 07:00 22/08/21 23:00
354 Un Install Existing Conveyor 1 day 19/08/21 07:00 19/08/21 23:00
355 Dismantling Mechanical Equipment 1 day 19/08/21 07:00 19/08/21 23:00
356 Lepas power perkabelan listrik 1 hr 19/08/21 07:00 19/08/21 08:00 List NPK
357 Lepas primary scrapper & gearbox & motor 2 hrs 19/08/21 07:00 19/08/21 09:00 Mek NPK
358 Lepas belt conveyor 2 hrs 19/08/21 09:00 19/08/21 11:00 Mek NPK
359 Lepas drive pulley 1 hr 19/08/21 11:00 19/08/21 13:00 Mek NPK;A2B Galion
360 Lepas tail pulley 1 hr 19/08/21 13:00 19/08/21 14:00 Mek NPK;A2B Galion
361 Lepas rubber seal dan skirt board 1 hr 19/08/21 14:00 19/08/21 15:00 Mek NPK
362 Cek motor di bengkel listrik 8 hrs 19/08/21 09:00 19/08/21 18:00 Beng Listrik
363 Dismantling Frame Conveyor,Support,Platform 7 hrs 19/08/21 15:00 19/08/21 23:00 A2B Galion;Beng S2 NPK (5)
364 Install New Conveyor 3 days 20/08/21 07:00 22/08/21 23:00
365 Preparation Existing Area 2 hrs 20/08/21 07:00 20/08/21 09:00 Opr NPK-1;Jaspil
366 Install New Support 4 hrs 20/08/21 09:00 20/08/21 14:00 Beng S2 NPK (5)
367 Erection new Frame Conveyor 8 hrs 20/08/21 14:00 20/08/21 23:00 Mek NPK;A2B Galion;Beng S2 NP
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
368 Setting alignment 5 hrs 21/08/21 07:00 21/08/21 13:00 Mek NPK;Beng S2 NPK (5)
369 Install Mechanical Equipment 1,57 days 21/08/21 13:00 22/08/21 22:00
370 Pasang drive pulley 4 hrs 21/08/21 13:00 21/08/21 17:00 Mek NPK;A2B Galion
371 Pasang tail pulley 2 hrs 21/08/21 17:00 21/08/21 20:00 Mek NPK;A2B Galion
372 Pasang bracket dan setting 2 hrs 21/08/21 20:00 21/08/21 22:00 Mek NPK
373 Pasang roller idler, impact, return 2 hrs 21/08/21 22:00 22/08/21 08:00 Mek NPK
374 Pasang base plate, gearbox unit (ganti oli) & motor 6 hrs 22/08/21 08:00 22/08/21 15:00 Mek NPK;A2B Galion
375 Pasang belt conveyor 4 hrs 22/08/21 15:00 22/08/21 20:00 Mek NPK
376 Pasang primary scrapper 1 hr 22/08/21 20:00 22/08/21 21:00 Mek NPK
377 Pasang skirt board dan rubber seal 1 hr 22/08/21 21:00 22/08/21 22:00 Mek NPK
378 Pasang transducer indikasi ampere HMI 2 hrs 22/08/21 15:00 22/08/21 17:00 List NPK
379 Pasang power perkabelan listrik & PM motor 2 hrs 22/08/21 17:00 22/08/21 20:00 List NPK
380 Final check 1 hr 22/08/21 22:00 22/08/21 23:00 InsP NPK
381 CL-010 (COOLER OUTLET CONVEYOR) - Optimalisasi 300000395220 5 days 03/08/21 07:00 07/08/21 23:00
382 Un Install Existing Conveyor 1 day 03/08/21 07:00 03/08/21 23:00
383 Dismantling Mechanical Equipment 1 day 03/08/21 07:00 03/08/21 23:00
384 Lepas power perkabelan listrik 1 hr 03/08/21 07:00 03/08/21 08:00 List NPK
385 Lepas primary scrapper & gearbox & motor 2 hrs 03/08/21 07:00 03/08/21 09:00 Mek NPK
386 Lepas belt conveyor 2 hrs 03/08/21 09:00 03/08/21 11:00 Mek NPK
387 Lepas drive pulley 1 hr 03/08/21 11:00 03/08/21 13:00 Mek NPK;A2B Galion
388 Lepas tail pulley 1 hr 03/08/21 13:00 03/08/21 14:00 Mek NPK;A2B Galion
389 Lepas rubber seal dan skirt board 1 hr 03/08/21 14:00 03/08/21 15:00 Mek NPK
390 Cek motor di bengkel listrik 8 hrs 03/08/21 09:00 03/08/21 18:00 Beng Listrik
391 Dismantling Frame Conveyor,Support,Platform 7 hrs 03/08/21 15:00 03/08/21 23:00 A2B Galion;Beng S2 NPK (5)
392 Install New Conveyor 4 days 04/08/21 07:00 07/08/21 23:00
393 Preparation Existing Area 2 hrs 04/08/21 07:00 04/08/21 09:00 Opr NPK-1;Jaspil
394 Install Scapolding/reposisi 2 hrs 04/08/21 07:00 04/08/21 09:00 Beng S3
395 Install New Support 8 hrs 04/08/21 09:00 04/08/21 18:00 Beng S2 NPK (5)
396 Erection new Frame Conveyor 1 day 04/08/21 19:00 05/08/21 18:00 Mek NPK;A2B Galion;Beng S2 NPK (5)
397 Setting alignment 6 hrs 05/08/21 19:00 06/08/21 09:00 Mek NPK;Beng S2 NPK (5)
398 Install Mechanical Equipment 1,79 days 06/08/21 09:00 07/08/21 22:00
399 Pasang drive pulley 4 hrs 06/08/21 09:00 06/08/21 14:00 Mek NPK;A2B Galion
400 Pasang tail pulley 2 hrs 06/08/21 14:00 06/08/21 16:00 Mek NPK;A2B Galion
401 Pasang bracket dan setting 2 hrs 06/08/21 16:00 06/08/21 18:00 Mek NPK
402 Pasang roller idler, impact, return 3 hrs 06/08/21 19:00 06/08/21 22:00 Mek NPK
403 Pasang base plate, gearbox unit (ganti oli) & motor 6 hrs 06/08/21 22:00 07/08/21 13:00 Mek NPK;A2B Galion
404 Pasang belt conveyor 4 hrs 07/08/21 13:00 07/08/21 17:00 Mek NPK
405 Pasang primary scrapper 2 hrs 07/08/21 17:00 07/08/21 20:00 Mek NPK
406 Pasang skirt board dan rubber seal 2 hrs 07/08/21 20:00 07/08/21 22:00 Mek NPK
407 Pasang transducer indikasi ampere HMI 2 hrs 07/08/21 13:00 07/08/21 15:00 List NPK
408 Pasang power perkabelan listrik & PM motor 2 hrs 07/08/21 15:00 07/08/21 17:00 List NPK
409 Final check 1 hr 07/08/21 22:00 07/08/21 23:00 InsP NPK
410 CL-012-A (1st SCREEN CRUSHER OUTLET CONV) - Optimalisasi 300000396870 8 days 08/08/21 07:00 15/08/21 23:00
411 Un Install Existing Conveyor 1,93 days 08/08/21 07:00 09/08/21 22:00
412 Dismantling Mechanical Equipment 1,93 days 08/08/21 07:00 09/08/21 22:00
413 Lepas power perkabelan listrik 1 hr 08/08/21 07:00 08/08/21 08:00 List NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
414 Lepas primary scrapper & gearbox & motor 2 hrs 08/08/21 07:00 08/08/21 09:00 Mek NPK
415 Lepas belt conveyor 3 hrs 08/08/21 09:00 08/08/21 13:00 Mek NPK
416 Lepas drive pulley 3 hrs 08/08/21 13:00 08/08/21 16:00 Mek NPK;A2B Galion
417 Lepas tail pulley 2 hrs 08/08/21 16:00 08/08/21 18:00 Mek NPK;A2B Galion
418 Lepas rubber seal dan skirt board 1 hr 08/08/21 19:00 08/08/21 20:00 Mek NPK
419 Cek motor di bengkel listrik 8 hrs 08/08/21 09:00 08/08/21 18:00 Beng Listrik
420 Dismantling Frame Conveyor,Support,Platform 16 hrs 08/08/21 20:00 09/08/21 22:00 A2B Galion;Beng S2 NPK (5)
421 Install New Conveyor 6,07 days 09/08/21 22:00 15/08/21 23:00
422 Preparation Existing Area 2 hrs 09/08/21 22:00 10/08/21 08:00 Opr NPK-1;Jaspil
423 Install Scapolding/reposisi 2 hrs 09/08/21 22:00 10/08/21 08:00 Beng S3
424 Install New Support 9 hrs 10/08/21 08:00 10/08/21 18:00 Beng S2 NPK (5)
425 Erection new Frame Conveyor 26 hrs 10/08/21 19:00 12/08/21 16:00 Mek NPK;A2B Galion;Beng S2 NPK (5)
426 Setting alignment 6 hrs 12/08/21 16:00 12/08/21 23:00 Mek NPK;Beng S2 NPK (5)
427 Install Mechanical Equipment 2,93 days 13/08/21 07:00 15/08/21 22:00
428 Pasang drive pulley 4 hrs 13/08/21 07:00 13/08/21 11:00 Mek NPK;A2B Galion
429 Pasang tail pulley 2 hrs 13/08/21 11:00 13/08/21 14:00 Mek NPK;A2B Galion
430 Pasang bracket dan setting 8 hrs 13/08/21 14:00 13/08/21 23:00 Mek NPK
431 Pasang roller idler, impact, return 3 hrs 14/08/21 07:00 14/08/21 10:00 Mek NPK
432 Pasang base plate, gearbox unit (ganti oli) & motor 8 hrs 14/08/21 10:00 14/08/21 20:00 Mek NPK;A2B Galion
433 Pasang belt conveyor 6 hrs 14/08/21 20:00 15/08/21 10:00 Mek NPK
434 Pasang primary scrapper 2 hrs 15/08/21 10:00 15/08/21 13:00 Mek NPK
435 Pasang skirt board dan rubber seal 8 hrs 15/08/21 13:00 15/08/21 22:00 Mek NPK
436 Pasang transducer indikasi ampere HMI 2 hrs 14/08/21 20:00 14/08/21 22:00 List NPK
437 Pasang power perkabelan listrik & PM motor 2 hrs 14/08/21 22:00 15/08/21 08:00 List NPK
438 Final check 1 hr 15/08/21 22:00 15/08/21 23:00 InsP NPK
439 CL-012-B (CYCLONE RECYCLE CONVEYOR) - Optimalisasi 300000396871 2 days 16/08/21 07:00 17/08/21 23:00
440 Pengamanan area 1 hr 16/08/21 07:00 16/08/21 08:00 Opr NPK-1
441 Lepas bracket& roller carrier 3 hrs 16/08/21 08:00 16/08/21 11:00 Mek NPK
442 Lepas bracket& roller return idler 3 hrs 16/08/21 11:00 16/08/21 15:00 Mek NPK
443 Lepas roller impact 3 hrs 16/08/21 15:00 16/08/21 18:00 Mek NPK
444 Pasang braket&roller carrier baru 3 hrs 16/08/21 19:00 16/08/21 22:00 Mek NPK
445 Pasang braket&roller return idler baru 3 hrs 16/08/21 22:00 17/08/21 09:00 Mek NPK
446 Pasang roller impact baru 2 hrs 17/08/21 09:00 17/08/21 11:00 Mek NPK
447 GANTI TAIL PULLEY 3 hrs 17/08/21 11:00 17/08/21 15:00 Mek NPK
448 GANTI PRIMARY SCRAPPER 2 hrs 17/08/21 15:00 17/08/21 17:00 Mek NPK
449 CEK BEARING DRIVE PULLEY/GANTI JIKA AUS 1 hr 17/08/21 17:00 17/08/21 18:00 Mek NPK
450 CEK BEARING TAIL PULLEY/GANTI JIKA RUSAK 1 hr 17/08/21 19:00 17/08/21 20:00 Mek NPK
451 Ganti baut adjuster 1 hr 17/08/21 20:00 17/08/21 21:00 Mek NPK
452 Ganti oli gearbox 1 hr 17/08/21 21:00 17/08/21 22:00 Mek NPK
453 PM motor 2 hrs 16/08/21 08:00 16/08/21 10:00 List NPK
454 Final check 1 hr 17/08/21 22:00 17/08/21 23:00 InsP NPK
455 CL-013 (1st SCREEN OUTLET CONVEYOR) - Optimalisasi 200000201762 2 days 18/08/21 07:00 19/08/21 23:00
456 Pengamanan area 1 hr 18/08/21 07:00 18/08/21 08:00 Opr NPK-1
457 Ganti belt conveyor 4 hrs 18/08/21 07:00 18/08/21 11:00 Mek NPK
458 Lepas bracket& roller carrier 2 hrs 18/08/21 11:00 18/08/21 14:00 Mek NPK
459 Lepas bracket& roller return idler 2 hrs 18/08/21 14:00 18/08/21 16:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
460 Lepas roller impact 3 hrs 18/08/21 16:00 18/08/21 20:00 Mek NPK
461 Pasang braket&roller carrier baru 3 hrs 18/08/21 20:00 18/08/21 23:00 Mek NPK
462 Pasang braket&roller return idler baru 3 hrs 19/08/21 07:00 19/08/21 10:00 Mek NPK
463 Pasang roller impact baru 2 hrs 19/08/21 10:00 19/08/21 13:00 Mek NPK
464 Buka rubber seal skirtboard 1 hr 19/08/21 13:00 19/08/21 14:00 Mek NPK
465 Buat&pasang skirtboard baru 2 hrs 19/08/21 14:00 19/08/21 16:00 Mek NPK
466 Ganti oli gearbox 1 hr 19/08/21 16:00 19/08/21 17:00 Mek NPK
467 Cek bearing drive pulley (ganti jika rus 1 hr 19/08/21 17:00 19/08/21 18:00 Mek NPK
468 CEK BEARING&TAIL PULLEY/GANTI JIKA RUSAK 1 hr 19/08/21 19:00 19/08/21 20:00 Mek NPK
469 Lepas primary scraper 1 hr 19/08/21 20:00 19/08/21 21:00 Mek NPK
470 Pasang&setting primary scraper baru 2 hrs 19/08/21 21:00 19/08/21 23:00 Mek NPK
471 Ganti baut adjuster 1 hr 19/08/21 21:00 19/08/21 22:00 Mek NPK
472 Final check 1 hr 19/08/21 22:00 19/08/21 23:00 InsP NPK
473 CL-015-A (2nd SCREEN UNDERSIZE OUT CONV) - Optimalisasi 300000386582 2 days 20/08/21 07:00 21/08/21 23:00
474 Pengamanan area 1 hr 20/08/21 07:00 20/08/21 08:00 Opr NPK-1
475 Lepas bracket& roller carrier 2 hrs 20/08/21 08:00 20/08/21 10:00 Mek NPK
476 Lepas bracket& roller return idler 2 hrs 20/08/21 10:00 20/08/21 13:00 Mek NPK
477 Lepas roller impact 3 hrs 20/08/21 13:00 20/08/21 16:00 Mek NPK
478 Pasang braket&roller carrier baru 3 hrs 20/08/21 16:00 20/08/21 20:00 Mek NPK
479 Pasang braket&roller return idler baru 3 hrs 20/08/21 20:00 20/08/21 23:00 Mek NPK
480 Pasang roller impact baru 2 hrs 21/08/21 07:00 21/08/21 09:00 Mek NPK
481 Buka rubber seal skirtboard 1 hr 21/08/21 09:00 21/08/21 10:00 Mek NPK
482 Buat&pasang skirtboard baru 1 hr 21/08/21 10:00 21/08/21 11:00 Mek NPK
483 Ganti oli gearbox 1 hr 21/08/21 11:00 21/08/21 13:00 Mek NPK
484 Cek bearing drive pulley (ganti jika rus 2 hrs 21/08/21 13:00 21/08/21 15:00 Mek NPK
485 CEK BEARING&TAIL PULLEY/GANTI JIKA RUSAK 2 hrs 21/08/21 15:00 21/08/21 17:00 Mek NPK
486 Lepas primary scraper 1 hr 21/08/21 17:00 21/08/21 18:00 Mek NPK
487 Pasang&setting primary scraper baru 2 hrs 21/08/21 19:00 21/08/21 21:00 Mek NPK
488 Ganti baut adjuster 1 hr 21/08/21 21:00 21/08/21 22:00 Mek NPK
489 PM motor 2 hrs 20/08/21 08:00 20/08/21 10:00 List NPK
490 Final check 1 hr 21/08/21 22:00 21/08/21 23:00 InsP NPK
491 CL-015-B (2nd SCREEN PRODUCT OUT CONV) - Optimalisasi 300000389943 6 days 16/08/21 07:00 21/08/21 23:00
492 Un Install Existing Conveyor 1 day 16/08/21 07:00 16/08/21 23:00
493 Dismantling Mechanical Equipment 1 day 16/08/21 07:00 16/08/21 23:00
494 Lepas power perkabelan listrik 1 hr 16/08/21 07:00 16/08/21 08:00 List NPK
495 Lepas primary scrapper & gearbox & motor 2 hrs 16/08/21 07:00 16/08/21 09:00 Mek NPK
496 Lepas belt conveyor 2 hrs 16/08/21 09:00 16/08/21 11:00 Mek NPK
497 Lepas drive pulley 1 hr 16/08/21 11:00 16/08/21 13:00 Mek NPK;A2B Galion
498 Lepas tail pulley 1 hr 16/08/21 13:00 16/08/21 14:00 Mek NPK;A2B Galion
499 Lepas rubber seal dan skirt board 1 hr 16/08/21 14:00 16/08/21 15:00 Mek NPK
500 Cek motor di bengkel listrik 8 hrs 16/08/21 09:00 16/08/21 18:00 Beng Listrik
501 Dismantling Frame Conveyor,Support,Platform 7 hrs 16/08/21 15:00 16/08/21 23:00 A2B Galion;Beng S2 NPK (5)
502 Install New Conveyor 5 days 17/08/21 07:00 21/08/21 23:00
503 Preparation Existing Area 2 hrs 17/08/21 07:00 17/08/21 09:00 Opr NPK-1;Jaspil
504 Install Scapolding/reposisi 4 hrs 17/08/21 07:00 17/08/21 11:00 Beng S3
505 Install New Support 8 hrs 17/08/21 11:00 17/08/21 21:00 Beng S2 NPK (5)
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
506 Erection new Frame Conveyor 1 day 17/08/21 21:00 18/08/21 21:00 Mek NPK;A2B Galion;Beng S2 NPK (5)
507 Setting alignment 6 hrs 18/08/21 21:00 19/08/21 11:00 Mek NPK;Beng S2 NPK (5)
508 Install Mechanical Equipment 2,64 days 19/08/21 11:00 21/08/21 22:00
509 Pasang drive pulley 4 hrs 19/08/21 11:00 19/08/21 16:00 Mek NPK;A2B Galion
510 Pasang tail pulley 4 hrs 19/08/21 16:00 19/08/21 21:00 Mek NPK;A2B Galion
511 Pasang bracket dan setting 8 hrs 19/08/21 21:00 20/08/21 14:00 Mek NPK
512 Pasang roller idler, impact, return 3 hrs 20/08/21 14:00 20/08/21 17:00 Mek NPK
513 Pasang base plate, gearbox unit (ganti oli) & motor 6 hrs 20/08/21 17:00 21/08/21 08:00 Mek NPK;A2B Galion
514 Pasang belt conveyor 6 hrs 21/08/21 08:00 21/08/21 15:00 Mek NPK
515 Pasang primary scrapper 2 hrs 21/08/21 15:00 21/08/21 17:00 Mek NPK
516 Pasang skirt board dan rubber seal 4 hrs 21/08/21 17:00 21/08/21 22:00 Mek NPK
517 Pasang power perkabelan listrik & PM motor 2 hrs 21/08/21 17:00 21/08/21 20:00 List NPK
518 Final check 1 hr 21/08/21 22:00 21/08/21 23:00 InsP NPK
519 CL-016 (COATER INLET CONVEYOR) - Optimalisasi 300000387053 9 days 02/08/21 07:00 10/08/21 23:00
520 Un Install Existing Conveyor 2,5 days 02/08/21 07:00 04/08/21 15:00
521 Dismantling Mechanical Equipment 2,5 days 02/08/21 07:00 04/08/21 15:00
522 Lepas power perkabelan listrik 1 hr 02/08/21 07:00 02/08/21 08:00 List NPK
523 Lepas primary scrapper & gearbox & motor 3 hrs 02/08/21 07:00 02/08/21 10:00 Mek NPK
524 Lepas belt conveyor 3 hrs 02/08/21 10:00 02/08/21 14:00 Mek NPK
525 Lepas drive pulley 3 hrs 02/08/21 14:00 02/08/21 17:00 Mek NPK;A2B Galion
526 Lepas tail pulley 3 hrs 02/08/21 17:00 02/08/21 21:00 Mek NPK;A2B Galion
527 Lepas rubber seal dan skirt board 1 hr 02/08/21 21:00 02/08/21 22:00 Mek NPK
528 Cek motor di bengkel listrik 8 hrs 02/08/21 10:00 02/08/21 20:00 List NPK
529 Dismantling Frame Conveyor,Support,Platform 22 hrs 02/08/21 22:00 04/08/21 15:00 A2B Galion;Beng S2 NPK (6)
530 Install New Conveyor 6,5 days 04/08/21 15:00 10/08/21 23:00
531 Preparation Existing Area 2 hrs 04/08/21 15:00 04/08/21 17:00 Opr NPK-1;Jaspil
532 Install Scapolding/reposisi 3 hrs 04/08/21 15:00 04/08/21 18:00 Beng S3
533 Install New Support 10 hrs 04/08/21 19:00 05/08/21 14:00 Beng S2 NPK (6)
534 Erection new Frame Conveyor 2 days 05/08/21 14:00 07/08/21 14:00 Mek NPK;A2B Galion;Beng S2 NPK (6)
535 Setting alignment 8 hrs 07/08/21 14:00 07/08/21 23:00 Mek NPK;Beng S2 NPK (6)
536 Install Mechanical Equipment 2,93 days 08/08/21 07:00 10/08/21 22:00
537 Pasang drive pulley 4 hrs 08/08/21 07:00 08/08/21 11:00 Mek NPK;A2B Galion
538 Pasang tail pulley 4 hrs 08/08/21 11:00 08/08/21 16:00 Mek NPK;A2B Galion
539 Pasang bracket dan setting 8 hrs 08/08/21 16:00 09/08/21 09:00 Mek NPK
540 Pasang roller idler, impact, return 4 hrs 09/08/21 09:00 09/08/21 14:00 Mek NPK
541 Pasang base plate, gearbox unit (ganti oli) & motor 9 hrs 09/08/21 14:00 10/08/21 08:00 Mek NPK;A2B Galion
542 Pasang belt conveyor 8 hrs 10/08/21 08:00 10/08/21 17:00 Mek NPK
543 Pasang primary scrapper 2 hrs 10/08/21 17:00 10/08/21 20:00 Mek NPK
544 Pasang skirt board dan rubber seal 2 hrs 10/08/21 20:00 10/08/21 22:00 Mek NPK
545 Pasang power perkabelan listrik & PM motor 1 hr 10/08/21 20:00 10/08/21 21:00 List NPK
546 Final check 1 hr 10/08/21 22:00 10/08/21 23:00 InsP NPK
547 CL-017 (COATER OUTLET CONVEYOR) - Optimalisasi 300000387054 2 days 11/08/21 07:00 12/08/21 23:00
548 Pengamanan area 1 hr 11/08/21 07:00 11/08/21 08:00 Opr NPK-1
549 Lepas bracket& roller carrier 3 hrs 11/08/21 08:00 11/08/21 11:00 Mek NPK
550 Lepas bracket& roller return idler 3 hrs 11/08/21 11:00 11/08/21 15:00 Mek NPK
551 Lepas roller impact 3 hrs 11/08/21 15:00 11/08/21 18:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
552 Pasang braket&roller carrier baru 3 hrs 11/08/21 19:00 11/08/21 22:00 Mek NPK
553 Pasang braket&roller return idler baru 3 hrs 11/08/21 22:00 12/08/21 09:00 Mek NPK
554 Pasang roller impact baru 3 hrs 12/08/21 09:00 12/08/21 13:00 Mek NPK
555 Buka rubber seal skirtboard 1 hr 12/08/21 13:00 12/08/21 14:00 Mek NPK
556 Buat&pasang skirtboard baru 1 hr 12/08/21 14:00 12/08/21 15:00 Mek NPK
557 Ganti oli gearbox 1 hr 12/08/21 15:00 12/08/21 16:00 Mek NPK
558 CEK BEARING&TAIL PULLEY/GANTI JIKA RUSAK 2 hrs 12/08/21 16:00 12/08/21 18:00 Mek NPK
559 Cek bearing tail pulley (ganti jika rusa 2 hrs 12/08/21 19:00 12/08/21 21:00 Mek NPK
560 Ganti baut adjuster 1 hr 12/08/21 21:00 12/08/21 22:00 Mek NPK
561 PM motor 2 hrs 11/08/21 08:00 11/08/21 10:00 List NPK
562 Final check 1 hr 12/08/21 22:00 12/08/21 23:00 Mek NPK
563 CL-019-A (SEWING CONVEYOR) - Optimalisasi 300000388039 2 days 13/08/21 07:00 14/08/21 23:00
564 Pengamanan area 1 hr 13/08/21 07:00 13/08/21 08:00 Opr NPK-1
565 Lepas conveyor modular 1 hr 13/08/21 08:00 13/08/21 09:00 Mek NPK
566 Lepas chain roller 1 hr 13/08/21 09:00 13/08/21 10:00 Mek NPK
567 Lepas drive pulley 1 hr 13/08/21 10:00 13/08/21 11:00 Mek NPK
568 Lepas sprocket pulley 1 hr 13/08/21 11:00 13/08/21 13:00 Mek NPK
569 Lepas bearing drive pulley 1 hr 13/08/21 13:00 13/08/21 14:00 Mek NPK
570 Lepas sprocket modular drive 1 hr 13/08/21 14:00 13/08/21 15:00 Mek NPK
571 Pasang sprocket modular drive baru 2 hrs 13/08/21 15:00 13/08/21 17:00 Mek NPK
572 Pasang bearing drive pulley baru 1 hr 13/08/21 17:00 13/08/21 18:00 Mek NPK
573 Pasang sprocket pulley baru 1 hr 13/08/21 19:00 13/08/21 20:00 Mek NPK
574 Pasang drive pulley 1 hr 13/08/21 20:00 13/08/21 21:00 Mek NPK
575 Ganti baut housing drive 1 hr 13/08/21 21:00 13/08/21 22:00 Mek NPK
576 Lepas sprocket gearbox 1 hr 13/08/21 22:00 13/08/21 23:00 Mek NPK
577 Pasang sprocket gearbox baru 1 hr 14/08/21 07:00 14/08/21 08:00 Mek NPK
578 Pasang chain roller baru 1 hr 14/08/21 08:00 14/08/21 09:00 Mek NPK
579 Lepas tail pulley 1 hr 14/08/21 09:00 14/08/21 10:00 Mek NPK
580 Lepas bearing tail pulley 1 hr 14/08/21 10:00 14/08/21 11:00 Mek NPK
581 Lepas sprocket modular tail 1 hr 14/08/21 11:00 14/08/21 13:00 Mek NPK
582 Pasang sprocket modular tail baru 1 hr 14/08/21 13:00 14/08/21 14:00 Mek NPK
583 Pasang bearing tail baru 1 hr 14/08/21 14:00 14/08/21 15:00 Mek NPK
584 Pasang tail pulley 1 hr 14/08/21 15:00 14/08/21 16:00 Mek NPK
585 Ganti baut frame tail DAN DRIVE 1 hr 14/08/21 16:00 14/08/21 17:00 Mek NPK
586 Ganti baut housing tail 1 hr 14/08/21 17:00 14/08/21 18:00 Mek NPK
587 Ganti oli gearbox 1 hr 14/08/21 19:00 14/08/21 20:00 Mek NPK
588 Ganti rail modular 1 hr 14/08/21 20:00 14/08/21 21:00 Mek NPK
589 Pasang conveyor modular baru 1 hr 14/08/21 21:00 14/08/21 22:00 Mek NPK
590 Final check 1 hr 14/08/21 22:00 14/08/21 23:00 InsP NPK
591 CL-019-B (SEWING CONVEYOR) - Optimalisasi 300000388040 2 days 15/08/21 07:00 16/08/21 23:00
592 Pengamanan area 1 hr 15/08/21 07:00 15/08/21 08:00 Opr NPK-1
593 Lepas conveyor modular 1 hr 15/08/21 08:00 15/08/21 09:00 Mek NPK
594 Lepas chain roller 1 hr 15/08/21 09:00 15/08/21 10:00 Mek NPK
595 Lepas drive pulley 1 hr 15/08/21 10:00 15/08/21 11:00 Mek NPK
596 Lepas sprocket pulley 1 hr 15/08/21 11:00 15/08/21 13:00 Mek NPK
597 Lepas bearing drive pulley 1 hr 15/08/21 13:00 15/08/21 14:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
598 Lepas sprocket modular drive 1 hr 15/08/21 14:00 15/08/21 15:00 Mek NPK
599 Pasang sprocket modular drive baru 2 hrs 15/08/21 15:00 15/08/21 17:00 Mek NPK
600 Pasang bearing drive pulley baru 1 hr 15/08/21 17:00 15/08/21 18:00 Mek NPK
601 Pasang sprocket pulley baru 1 hr 15/08/21 19:00 15/08/21 20:00 Mek NPK
602 Pasang drive pulley 1 hr 15/08/21 20:00 15/08/21 21:00 Mek NPK
603 Ganti baut housing drive 1 hr 15/08/21 21:00 15/08/21 22:00 Mek NPK
604 Lepas sprocket gearbox 1 hr 15/08/21 22:00 15/08/21 23:00 Mek NPK
605 Pasang sprocket gearbox baru 2 hrs 16/08/21 07:00 16/08/21 09:00 Mek NPK
606 Pasang chain roller baru 1 hr 16/08/21 09:00 16/08/21 10:00 Mek NPK
607 Lepas tail pulley 1 hr 16/08/21 10:00 16/08/21 11:00 Mek NPK
608 Lepas bearing tail pulley 1 hr 16/08/21 11:00 16/08/21 13:00 Mek NPK
609 Lepas sprocket modular tail 1 hr 16/08/21 13:00 16/08/21 14:00 Mek NPK
610 Pasang sprocket modular tail baru 1 hr 16/08/21 14:00 16/08/21 15:00 Mek NPK
611 Pasang bearing tail baru 1 hr 16/08/21 15:00 16/08/21 16:00 Mek NPK
612 Pasang tail pulley 1 hr 16/08/21 16:00 16/08/21 17:00 Mek NPK
613 Ganti baut frame tail DAN DRIVE 1 hr 16/08/21 17:00 16/08/21 18:00 Mek NPK
614 Ganti baut housing tail 1 hr 16/08/21 19:00 16/08/21 20:00 Mek NPK
615 Ganti oli gearbox 1 hr 16/08/21 20:00 16/08/21 21:00 Mek NPK
616 Pasang conveyor modular baru 1 hr 16/08/21 21:00 16/08/21 22:00 Mek NPK
617 Final check 1 hr 16/08/21 22:00 16/08/21 23:00 InsP NPK
618 CL-021-A (SHORT LOADING CONV A) 3 days 11/08/21 07:00 13/08/21 23:00
619 Penggantian Frame Conveyor 200000196720 1,57 days 11/08/21 07:00 12/08/21 16:00
620 Un Install Existing Conveyor 0,71 days 11/08/21 07:00 11/08/21 18:00
621 Dismantling Mechanical Equipment 0,71 days 11/08/21 07:00 11/08/21 18:00
622 Lepas power perkabelan listrik 1 hr 11/08/21 07:00 11/08/21 08:00 List NPK
623 Lepas primary scrapper & gearbox & motor 1 hr 11/08/21 07:00 11/08/21 08:00 Mek NPK
624 Lepas belt conveyor 1 hr 11/08/21 08:00 11/08/21 09:00 Mek NPK
625 Lepas drive pulley 1 hr 11/08/21 09:00 11/08/21 10:00 Mek NPK;A2B Galion
626 Lepas tail pulley 1 hr 11/08/21 10:00 11/08/21 11:00 Mek NPK;A2B Galion
627 Lepas rubber seal dan skirt board 1 hr 11/08/21 11:00 11/08/21 13:00 Mek NPK
628 Cek motor di bengkel listrik 8 hrs 11/08/21 08:00 11/08/21 17:00 Beng Listrik
629 Dismantling Frame Conveyor,Support,Platform 5 hrs 11/08/21 13:00 11/08/21 18:00 A2B Galion;Beng S2 NPK (6)
630 Install New Conveyor 0,86 days 11/08/21 19:00 12/08/21 16:00
631 Preparation Existing Area 1 hr 11/08/21 19:00 11/08/21 20:00 Opr NPK-1;Jaspil
632 Install New Support 3 hrs 11/08/21 19:00 11/08/21 22:00 Beng S2 NPK (6)
633 Erection new Frame Conveyor 6 hrs 11/08/21 22:00 12/08/21 13:00 Mek NPK;A2B Galion;Beng S2 NPK (6)
634 Setting alignment 3 hrs 12/08/21 13:00 12/08/21 16:00 Mek NPK;Beng S2 NPK (6)
635 Install Mechanical Equipment 300000387152 1,43 days 12/08/21 16:00 13/08/21 23:00
636 Pasang drive pulley 2 hrs 12/08/21 16:00 12/08/21 18:00 Mek NPK;A2B Galion
637 Pasang tail pulley 2 hrs 12/08/21 19:00 12/08/21 21:00 Mek NPK;A2B Galion
638 Pasang bracket dan setting 2 hrs 12/08/21 21:00 12/08/21 23:00 Mek NPK
639 Pasang roller idler, impact, return 2 hrs 13/08/21 07:00 13/08/21 09:00 Mek NPK
640 Pasang base plate, gearbox unit (ganti oli) & motor 4 hrs 13/08/21 09:00 13/08/21 14:00 Mek NPK;A2B Galion
641 Pasang belt conveyor 2 hrs 13/08/21 14:00 13/08/21 16:00 Mek NPK
642 Pasang primary scrapper 2 hrs 13/08/21 16:00 13/08/21 18:00 Mek NPK
643 Pasang skirt board dan rubber seal 2 hrs 13/08/21 19:00 13/08/21 21:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
644 PASANG BEARING DRIVE PULLEY BARU 2 hrs 12/08/21 16:00 12/08/21 18:00 Mek NPK
645 Ganti baut housing drive 1 hr 12/08/21 19:00 12/08/21 20:00 Mek NPK
646 GANTI BAUT ADJUSTER 1 hr 12/08/21 19:00 12/08/21 20:00 Mek NPK
647 Pasang bearing head pulley baru 1 hr 12/08/21 20:00 12/08/21 21:00 Mek NPK
648 Ganti baut housing head pulley 1 hr 12/08/21 20:00 12/08/21 21:00 Mek NPK
649 Pasang bearing bend pulley baru 2 hrs 12/08/21 21:00 12/08/21 23:00 Mek NPK
650 Ganti baut housing bend pulley 1 hr 12/08/21 22:00 12/08/21 23:00 Mek NPK
651 PASANG BEARING TAIL BARU 1 hr 12/08/21 20:00 12/08/21 21:00 Mek NPK
652 Ganti baut housing tail pulley 1 hr 12/08/21 20:00 12/08/21 21:00 Mek NPK
653 Pasang sprocket gearbox baru 2 hrs 13/08/21 09:00 13/08/21 11:00 Mek NPK
654 Pasang chain roller baru 1 hr 13/08/21 21:00 13/08/21 22:00 Mek NPK
655 Pasang power perkabelan listrik 1 hr 13/08/21 21:00 13/08/21 22:00 List NPK
656 Final check 1 hr 13/08/21 22:00 13/08/21 23:00 InsP NPK
657 CL-021-B (SHORT LOADING CONV B) 3 days 14/08/21 07:00 16/08/21 23:00
658 Penggantian Frame Conveyor 200000196723 1,57 days 14/08/21 07:00 15/08/21 16:00
659 Un Install Existing Conveyor 0,71 days 14/08/21 07:00 14/08/21 18:00
660 Dismantling Mechanical Equipment 0,71 days 14/08/21 07:00 14/08/21 18:00
661 Lepas power perkabelan listrik 1 hr 14/08/21 07:00 14/08/21 08:00 List NPK
662 Lepas primary scrapper & gearbox 1 hr 14/08/21 07:00 14/08/21 08:00 Mek NPK
663 Lepas belt conveyor 1 hr 14/08/21 08:00 14/08/21 09:00 Mek NPK
664 Lepas drive pulley 1 hr 14/08/21 09:00 14/08/21 10:00 Mek NPK;A2B Galion
665 Lepas tail pulley 1 hr 14/08/21 10:00 14/08/21 11:00 Mek NPK;A2B Galion
666 Lepas rubber seal dan skirt board 1 hr 14/08/21 11:00 14/08/21 13:00 Mek NPK
667 Cek motor di bengkel listrik 8 hrs 14/08/21 08:00 14/08/21 17:00 Beng Listrik
668 Dismantling Frame Conveyor,Support,Platform 5 hrs 14/08/21 13:00 14/08/21 18:00 A2B Galion;Beng S2 NPK (6)
669 Install New Conveyor 0,86 days 14/08/21 19:00 15/08/21 16:00
670 Preparation Existing Area 1 hr 14/08/21 19:00 14/08/21 20:00 Opr NPK-1;Jaspil
671 Install New Support 3 hrs 14/08/21 19:00 14/08/21 22:00 Beng S2 NPK (6)
672 Erection new Frame Conveyor 6 hrs 14/08/21 22:00 15/08/21 13:00 Mek NPK;A2B Galion;Beng S2 NPK (6)
673 Setting alignment 3 hrs 15/08/21 13:00 15/08/21 16:00 Mek NPK;Beng S2 NPK (6)
674 Install Mechanical Equipment 300000387153 1,43 days 15/08/21 16:00 16/08/21 23:00
675 Pasang drive pulley 2 hrs 15/08/21 16:00 15/08/21 18:00 Mek NPK;A2B Galion
676 Pasang tail pulley 2 hrs 15/08/21 19:00 15/08/21 21:00 Mek NPK;A2B Galion
677 Pasang bracket dan setting 2 hrs 15/08/21 21:00 15/08/21 23:00 Mek NPK
678 Pasang roller idler, impact, return 2 hrs 16/08/21 07:00 16/08/21 09:00 Mek NPK
679 Pasang base plate, gearbox unit (ganti oli) & motor 4 hrs 16/08/21 09:00 16/08/21 14:00 Mek NPK;A2B Galion
680 Pasang belt conveyor 2 hrs 16/08/21 14:00 16/08/21 16:00 Mek NPK
681 Pasang primary scrapper 2 hrs 16/08/21 16:00 16/08/21 18:00 Mek NPK
682 Pasang skirt board dan rubber seal 2 hrs 16/08/21 19:00 16/08/21 21:00 Mek NPK
683 PASANG BEARING DRIVE PULLEY BARU 2 hrs 15/08/21 16:00 15/08/21 18:00 Mek NPK
684 Ganti baut housing drive 1 hr 15/08/21 19:00 15/08/21 20:00 Mek NPK
685 GANTI BAUT ADJUSTER 1 hr 15/08/21 19:00 15/08/21 20:00 Mek NPK
686 Pasang bearing head pulley baru 1 hr 15/08/21 20:00 15/08/21 21:00 Mek NPK
687 Ganti baut housing head pulley 1 hr 15/08/21 21:00 15/08/21 22:00 Mek NPK
688 Pasang bearing bend pulley baru 2 hrs 15/08/21 22:00 16/08/21 08:00 Mek NPK
689 Ganti baut housing bend pulley 1 hr 16/08/21 08:00 16/08/21 09:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
690 PASANG BEARING TAIL BARU 1 hr 15/08/21 19:00 15/08/21 20:00 Mek NPK
691 Ganti baut housing tail pulley 1 hr 15/08/21 20:00 15/08/21 21:00 Mek NPK
692 Pasang sprocket gearbox baru 2 hrs 16/08/21 09:00 16/08/21 11:00 Mek NPK
693 Pasang chain roller baru 1 hr 16/08/21 21:00 16/08/21 22:00 Mek NPK
694 Pasang power perkabelan listrik 1 hr 16/08/21 21:00 16/08/21 22:00 List NPK
695 Final check 1 hr 16/08/21 22:00 16/08/21 23:00 Mek NPK
696 CL-203 (TRANSFER CONVEYOR) - Optimalisasi 300000381599 2 days 11/08/21 07:00 12/08/21 23:00
697 PENGAMANAN AREA 1 hr 11/08/21 07:00 11/08/21 08:00 Opr NPK-1
698 LEPAS RUBBER SEAL SKIRTBOARD 2 hrs 11/08/21 08:00 11/08/21 10:00 Mek NPK
699 BUAT&PASANG RUBBER SEAL SKIRTBOARD BAR 2 hrs 11/08/21 10:00 11/08/21 13:00 Mek NPK
700 PASANG BAUT ADJUSTER 1 hr 11/08/21 13:00 11/08/21 14:00 Mek NPK
701 CEK BEARING DRIVE 2 hrs 11/08/21 14:00 11/08/21 16:00 Mek NPK
702 CEK BEARING SNUB DRIVE 2 hrs 11/08/21 16:00 11/08/21 18:00 Mek NPK
703 CEK BEARING SNUB TAIL 2 hrs 11/08/21 19:00 11/08/21 21:00 Mek NPK
704 CEK BEARING BEND 2 hrs 11/08/21 21:00 11/08/21 23:00 Mek NPK
705 CEK BEARING WING 2 hrs 12/08/21 07:00 12/08/21 09:00 Mek NPK
706 CEK BEARING TAIL 2 hrs 12/08/21 09:00 12/08/21 11:00 Mek NPK
707 CEK RUBBER LAGGING DRIVE 2 hrs 12/08/21 11:00 12/08/21 14:00 Mek NPK
708 GANTI ROLLER CARRIER 2 hrs 12/08/21 14:00 12/08/21 16:00 Mek NPK
709 GANTI ROLLER RETURN 2 hrs 12/08/21 16:00 12/08/21 18:00 Mek NPK
710 GANTI ROLLER IMPACT 2 hrs 12/08/21 19:00 12/08/21 21:00 Mek NPK
711 GANTI OLI GEARBOX 1 hr 12/08/21 21:00 12/08/21 22:00 Mek NPK
712 PM motor 2 hrs 11/08/21 08:00 11/08/21 10:00 List NPK
713 Ganti Sling Pullcord 2 hrs 11/08/21 10:00 11/08/21 13:00 List NPK
714 Final check 1 hr 12/08/21 22:00 12/08/21 23:00 InsP NPK
715 CL-204 (TRANSFER CONVEYOR) - Optimalisasi 300000381600 2 days 13/08/21 07:00 14/08/21 23:00
716 PENGAMANAN AREA 1 hr 13/08/21 07:00 13/08/21 08:00 Opr NPK-1
717 LEPAS RUBBER SEAL SKIRTBOARD 2 hrs 13/08/21 08:00 13/08/21 10:00 Mek NPK
718 BUAT&PASANG RUBBER SEAL SKIRTBOARD BAR 2 hrs 13/08/21 10:00 13/08/21 13:00 Mek NPK
719 PASANG BAUT ADJUSTER 2 hrs 13/08/21 13:00 13/08/21 15:00 Mek NPK
720 CEK BEARING DRIVE 2 hrs 13/08/21 15:00 13/08/21 17:00 Mek NPK
721 CEK BEARING SNUB DRIVE 2 hrs 13/08/21 17:00 13/08/21 20:00 Mek NPK
722 CEK BEARING SNUB TAIL 2 hrs 13/08/21 20:00 13/08/21 22:00 Mek NPK
723 CEK BEARING BEND 2 hrs 13/08/21 22:00 14/08/21 08:00 Mek NPK
724 CEK BEARING WING 2 hrs 14/08/21 08:00 14/08/21 10:00 Mek NPK
725 CEK BEARING TAIL 2 hrs 14/08/21 10:00 14/08/21 13:00 Mek NPK
726 GANTI ROLLER CARRIER 2 hrs 14/08/21 13:00 14/08/21 15:00 Mek NPK
727 GANTI ROLLER RETURN 2 hrs 14/08/21 15:00 14/08/21 17:00 Mek NPK
728 GANTI ROLLER IMPACT 2 hrs 14/08/21 17:00 14/08/21 20:00 Mek NPK
729 GANTI OLI GEARBOX 2 hrs 14/08/21 20:00 14/08/21 22:00 Mek NPK
730 PM motor 2 hrs 13/08/21 08:00 13/08/21 10:00 List NPK
731 Ganti Sling Pullcord 2 hrs 13/08/21 10:00 13/08/21 13:00 List NPK
732 Final check 1 hr 14/08/21 22:00 14/08/21 23:00 InsP NPK
733 CL-205-A (TRAVEL&TRIPPER CONV) - Optimalisasi 300000394596 1,79 days 15/08/21 07:00 16/08/21 20:00
734 PENGAMANAN AREA 1 hr 15/08/21 07:00 15/08/21 08:00 Opr NPK-1
735 LEPAS RUBBER SEAL SKIRTBOARD 2 hrs 15/08/21 08:00 15/08/21 10:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
736 BUAT&PASANG RUBBER SEAL SKIRTBOARD BAR 2 hrs 15/08/21 10:00 15/08/21 13:00 Mek NPK
737 PASANG BAUT ADJUSTER 2 hrs 15/08/21 13:00 15/08/21 15:00 Mek NPK
738 CEK BEARING DRIVE 2 hrs 15/08/21 15:00 15/08/21 17:00 Mek NPK
739 CEK BEARING HEAD PULLEY 2 hrs 15/08/21 17:00 15/08/21 20:00 Mek NPK
740 CEK BEARING BEND 2 hrs 15/08/21 20:00 15/08/21 22:00 Mek NPK
741 CEK BEARING WING 2 hrs 15/08/21 22:00 16/08/21 08:00 Mek NPK
742 CEK BEARING TAIL 2 hrs 16/08/21 08:00 16/08/21 10:00 Mek NPK
743 GANTI ROLLER CARRIER 2 hrs 16/08/21 10:00 16/08/21 13:00 Mek NPK
744 GANTI ROLLER RETURN 2 hrs 16/08/21 13:00 16/08/21 15:00 Mek NPK
745 GANTI ROLLER IMPACT 2 hrs 16/08/21 15:00 16/08/21 17:00 Mek NPK
746 GANTI OLI GEARBOX 1 hr 16/08/21 17:00 16/08/21 18:00 Mek NPK
747 PM motor 1 hr 15/08/21 08:00 15/08/21 09:00 List NPK
748 GANTI SELING PULLCORD 2 hrs 15/08/21 09:00 15/08/21 11:00 List NPK
749 GANTI PANEL CONTROL TRAVELING TRIPPER 2 hrs 15/08/21 11:00 15/08/21 14:00 List NPK
750 GANTI MOTOR TRIPPER CONVEYOR 2 hrs 15/08/21 14:00 15/08/21 16:00 List NPK
751 Final check 1 hr 16/08/21 19:00 16/08/21 20:00 InsP NPK
752 ELEVATOR 21 days 02/08/21 07:00 22/08/21 23:00
753 CL-006 (AGITATOR INLET ELEVATOR) - Optimalisasi 300000394659 2 days 15/08/21 09:00 17/08/21 09:00
754 GANTI TAIL PULLEY ELEVATOR 1 day 15/08/21 09:00 16/08/21 09:00 Mek NPK
755 BAUT HOUSING TAIL 1 day 15/08/21 09:00 16/08/21 09:00 Mek NPK
756 BAUT FRAME SLIDING GATE 1 day 15/08/21 09:00 16/08/21 09:00 Mek NPK
757 GANTI PULLEY GEARBOX 1 day 16/08/21 09:00 17/08/21 09:00 Mek NPK
758 GANTI PULLEY MOTOR 1 day 16/08/21 09:00 17/08/21 09:00 Mek NPK
759 GANTI TEFLON KOPLING 1 day 16/08/21 09:00 17/08/21 09:00 Mek NPK
760 GANTI V-BELT ELEVATOR 1 day 16/08/21 09:00 17/08/21 09:00 Mek NPK
761 Pasang transducer indikasi ampere HMI 2 hrs 16/08/21 09:00 16/08/21 11:00 List NPK
762 PM motor 2 hrs 16/08/21 11:00 16/08/21 14:00 List NPK
763 CL-009 (COOLER INLET ELEVATOR) - Optimalisasi 300000395218 5 days 10/08/21 09:00 15/08/21 09:00
764 BAUT COVER TOP ELEVATOR 2 hrs 10/08/21 09:00 10/08/21 11:00 Mek NPK;A2B Crane
765 GANTI CHAIN & BUCKET SET 2 days 10/08/21 09:00 12/08/21 09:00 Mek NPK;A2B Crane;Beng S2 NPK (7)
766 GANTI U-BOLT 2 days 10/08/21 09:00 12/08/21 09:00 Mek NPK
767 BAUT HOUSING DRIVE 1 day 12/08/21 09:00 13/08/21 09:00 Mek NPK
768 GANTI DRIVE PULLEY ELEVATOR 1 day 12/08/21 09:00 13/08/21 09:00 Mek NPK;A2B Crane
769 GANTI TAIL PULLEY ELEVATOR 1 day 13/08/21 09:00 14/08/21 09:00 Mek NPK
770 BAUT HOUSING TAIL 1 day 13/08/21 09:00 14/08/21 09:00 Mek NPK
771 BAUT FRAME SLIDING GATE 1 day 13/08/21 09:00 14/08/21 09:00 Mek NPK
772 GANTI PULLEY GEARBOX 1 day 14/08/21 09:00 15/08/21 09:00 Mek NPK
773 GANTI PULLEY MOTOR 1 day 14/08/21 09:00 15/08/21 09:00 Mek NPK
774 GANTI TEFLON KOPLING 1 day 14/08/21 09:00 15/08/21 09:00 Mek NPK
775 GANTI V-BELT ELEVATOR 1 day 14/08/21 09:00 15/08/21 09:00 Mek NPK
776 Pasang transducer indikasi ampere HMI 2 hrs 14/08/21 09:00 14/08/21 11:00 List NPK
777 PM motor 2 hrs 14/08/21 11:00 14/08/21 14:00 List NPK
778 CL-011 (1st SCREEN INLET ELEVATOR) - Penggantian Unit Elevator 300000376045 14,14 days 02/08/21 07:00 16/08/21 09:00
779 Un Install Existing Elevator 2,71 days 02/08/21 07:00 04/08/21 18:00
780 Dismantling Mechanical Equipment 1,5 days 02/08/21 07:00 03/08/21 15:00
781 Lepas power perkabelan listrik 1 hr 02/08/21 07:00 02/08/21 08:00 List NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
782 Lepas baut cover elevator 2 hrs 02/08/21 07:00 02/08/21 09:00 Mek NPK
783 Angkat cover elevator 2 hrs 02/08/21 07:00 02/08/21 09:00 A2B Crane
784 Lepas chain dan bucket unit lama 3 hrs 02/08/21 09:00 02/08/21 13:00 Mek NPK;A2B Crane
785 Lepas gearbox unit & motor 2 hrs 02/08/21 13:00 02/08/21 15:00 Mek NPK;A2B Crane
786 Lepas chute outlet & inlet 6 hrs 02/08/21 15:00 02/08/21 22:00 Beng S2 NPK (7)
787 Lepas support casing temporary 8 hrs 02/08/21 22:00 03/08/21 15:00 Beng S2 NPK (7)
788 Cek motor di bengkel listrik 8 hrs 02/08/21 15:00 03/08/21 08:00 Beng Listrik
789 Dismantling Casing Elevator 17 hrs 03/08/21 15:00 04/08/21 18:00 A2B Crane;Beng S2 NPK (7)
790 Install New Elevator 6 days 10/08/21 09:00 16/08/21 09:00
791 Erection new Elevator & pasang scaffolding 40 hrs 10/08/21 09:00 12/08/21 23:00 A2B Crane;Mek NPK;Beng S2 NPK (7)
792 Install Mechanical Equipment 3,71 days 12/08/21 07:00 15/08/21 18:00
793 Setting elevator 1 day 12/08/21 07:00 12/08/21 23:00 Mek NPK;A2B Crane;Beng S2 NPK (7)
794 Pasang chain, bucket set, U-bolt & cover 8 hrs 13/08/21 07:00 13/08/21 16:00 Mek NPK;A2B Crane
795 Pasang teflon kopling 2 hrs 13/08/21 16:00 13/08/21 18:00 Mek NPK
796 Pasang v-belt elevator 2 hrs 13/08/21 16:00 13/08/21 18:00 Mek NPK
797 Pasang transducer indikasi ampere HMI 2 hrs 13/08/21 16:00 13/08/21 18:00 List NPK
798 Pasang power perkabelan listrik & tes putaran 2 hrs 13/08/21 18:00 13/08/21 21:00 List NPK
799 Pasang chute outlet & inlet baru 2 days 13/08/21 19:00 15/08/21 18:00 Beng S2 NPK (7)
800 Install Ladder 1 day 13/08/21 19:00 14/08/21 18:00 Beng S2 NPK (7)
801 Final check 2 hrs 15/08/21 19:00 15/08/21 21:00 InsP NPK
802 Bongkar scafolding 4 hrs 15/08/21 21:00 16/08/21 09:00 Beng S3
803 CL-014 (2nd SCREEN INLET ELEVATOR) - Penggantian Unit Elevator 300000376046 14,86 days 04/08/21 19:00 19/08/21 16:00
804 Un Install Existing Elevator 2,71 days 04/08/21 19:00 07/08/21 14:00
805 Dismantling Mechanical Equipment 1,5 days 04/08/21 19:00 06/08/21 10:00
806 Lepas power perkabelan listrik 1 hr 04/08/21 19:00 04/08/21 20:00 List NPK
807 Lepas baut cover elevator 2 hrs 04/08/21 19:00 04/08/21 21:00 Mek NPK
808 Angkat cover elevator 2 hrs 04/08/21 19:00 04/08/21 21:00 A2B Crane
809 Lepas chain dan bucket unit lama 3 hrs 04/08/21 21:00 05/08/21 08:00 A2B Crane;Mek NPK
810 Lepas gearbox unit & motor 2 hrs 05/08/21 08:00 05/08/21 10:00 A2B Crane;Mek NPK
811 Lepas chute outlet & inlet 6 hrs 05/08/21 10:00 05/08/21 17:00 Beng S2 NPK (7)
812 Lepas support casing temporary 8 hrs 05/08/21 17:00 06/08/21 10:00 Beng S2 NPK (7)
813 Cek motor di bengkel listrik 8 hrs 05/08/21 10:00 05/08/21 20:00 Beng Listrik
814 Dismantling Casing Elevator 17 hrs 06/08/21 10:00 07/08/21 14:00 A2B Crane;Beng S2 NPK (7)
815 Install New Elevator 6 days 13/08/21 16:00 19/08/21 16:00
816 Erection new Elevator 40 hrs 13/08/21 16:00 16/08/21 14:00 Mek NPK;A2B Crane;Beng S2 NPK (7)
817 Install Mechanical Equipment 3,71 days 15/08/21 14:00 19/08/21 09:00
818 Setting elevator 1 day 15/08/21 14:00 16/08/21 14:00 A2B Crane;Mek NPK
819 Pasang chain, bucket set, U-bolt & cover 8 hrs 16/08/21 14:00 16/08/21 23:00 A2B Crane;Mek NPK
820 Pasang teflon kopling 2 hrs 17/08/21 07:00 17/08/21 09:00 A2B Crane;Mek NPK
821 Pasang v-belt elevator 2 hrs 17/08/21 07:00 17/08/21 09:00 Mek NPK
822 Pasang transducer indikasi ampere HMI 2 hrs 17/08/21 07:00 17/08/21 09:00 List NPK
823 Pasang power perkabelan listrik & tes putaran 2 hrs 17/08/21 09:00 17/08/21 11:00 List NPK
824 Pasang chute outlet & inlet baru 2 days 17/08/21 09:00 19/08/21 09:00 A2B Crane;Beng S2 NPK (7)
825 Install Ladder 1 day 17/08/21 09:00 18/08/21 09:00 Beng S2 NPK (7)
826 Final check 2 hrs 19/08/21 09:00 19/08/21 11:00 InsP NPK
827 Bongkar scafolding 4 hrs 19/08/21 11:00 19/08/21 16:00 Beng S3
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
828 CL-018 (BAGING INLET ELEVATOR) - Penggantian Unit Elevator 300000376047 15,57 days 07/08/21 14:00 22/08/21 23:00
829 Un Install Existing Elevator 2,71 days 07/08/21 14:00 10/08/21 09:00
830 Dismantling Mechanical Equipment 1,5 days 07/08/21 14:00 08/08/21 22:00
831 Lepas power perkabelan listrik 1 hr 07/08/21 14:00 07/08/21 15:00 List NPK
832 Lepas baut cover elevator 2 hrs 07/08/21 14:00 07/08/21 16:00 Mek NPK
833 Angkat cover elevator 2 hrs 07/08/21 14:00 07/08/21 16:00 A2B Crane
834 Lepas chain dan bucket unit lama 3 hrs 07/08/21 16:00 07/08/21 20:00 Mek NPK;A2B Crane
835 Lepas gearbox unit & motor 2 hrs 07/08/21 20:00 07/08/21 22:00 Mek NPK;A2B Crane
836 Lepas chute outlet & inlet 6 hrs 07/08/21 22:00 08/08/21 13:00 Beng S2 NPK (7)
837 Lepas support casing temporary 8 hrs 08/08/21 13:00 08/08/21 22:00 Beng S2 NPK (7)
838 Cek motor di bengkel listrik 8 hrs 07/08/21 22:00 08/08/21 15:00 Beng Listrik
839 Dismantling Casing Elevator 17 hrs 08/08/21 22:00 10/08/21 09:00 A2B Crane;Beng S2 NPK (7)
840 Install New Elevator 6 days 17/08/21 07:00 22/08/21 23:00
841 Erection new Elevator 40 hrs 17/08/21 07:00 19/08/21 21:00 A2B Crane;Mek NPK;Beng S2 NPK (7
842 Install Mechanical Equipment 3,71 days 18/08/21 21:00 22/08/21 16:00
843 Setting elevator 1 day 18/08/21 21:00 19/08/21 21:00 Mek NPK;A2B Crane
844 Pasang chain, bucket set, U-bolt & cover 8 hrs 19/08/21 21:00 20/08/21 14:00 Mek NPK;A2B Crane
845 Pasang teflon kopling 2 hrs 20/08/21 14:00 20/08/21 16:00 Mek NPK;A2B Crane
846 Pasang v-belt elevator 2 hrs 20/08/21 14:00 20/08/21 16:00 Mek NPK
847 Pasang transducer indikasi ampere HMI 2 hrs 20/08/21 14:00 20/08/21 16:00 List NPK
848 Pasang power perkabelan listrik & tes putaran 2 hrs 20/08/21 16:00 20/08/21 18:00 List NPK
849 Pasang chute outlet & inlet baru 2 days 20/08/21 16:00 22/08/21 16:00 A2B Crane;Beng S2 NPK (7)
850 Install Ladder 1 day 20/08/21 16:00 21/08/21 16:00 Beng S2 NPK (7)
851 Final check 2 hrs 22/08/21 16:00 22/08/21 18:00 InsP NPK
852 Bongkar scafolding 4 hrs 22/08/21 19:00 22/08/21 23:00 Beng S3
853 CRUSHER 6 days 17/08/21 07:00 22/08/21 23:00
854 CM-003-A (RECYCLE CRUSHER) - Penggantian Internal 300000374852 3 days 17/08/21 07:00 19/08/21 23:00
855 Pengamanan area 1 hr 17/08/21 07:00 17/08/21 08:00 Opr NPK-1
856 Lepas v-belt 2 hrs 17/08/21 08:00 17/08/21 10:00 Mek NPK
857 Lepas housing crusher 2 hrs 17/08/21 10:00 17/08/21 13:00 Mek NPK
858 Lepas rotor crusher 2 hrs 17/08/21 13:00 17/08/21 15:00 Mek NPK
859 Lepas pulley rotor 2 hrs 17/08/21 15:00 17/08/21 17:00 Mek NPK
860 Lepas bearing inboard&outboard 2 hrs 17/08/21 17:00 17/08/21 20:00 Mek NPK
861 Ganti chain hammer 4 hrs 17/08/21 20:00 18/08/21 08:00 Mek NPK
862 Pasang bearing inboard&outboard 4 hrs 18/08/21 08:00 18/08/21 13:00 Mek NPK
863 Pasang pulley rotor 3 hrs 18/08/21 13:00 18/08/21 16:00 Mek NPK
864 Pasang rotor crusher 3 hrs 18/08/21 16:00 18/08/21 20:00 Mek NPK
865 Ganti pulley motor 3 hrs 18/08/21 20:00 18/08/21 23:00 Mek NPK
866 Ganti rubber seal housing crusher 6 hrs 19/08/21 07:00 19/08/21 14:00 Mek NPK
867 Pasang housing crusher 5 hrs 19/08/21 14:00 19/08/21 20:00 Mek NPK
868 Ganti baut housing crusher 1 hr 19/08/21 19:00 19/08/21 20:00 Mek NPK
869 Pasang v-belt baru 2 hrs 19/08/21 20:00 19/08/21 22:00 Mek NPK
870 PM motor 1 hr 17/08/21 08:00 17/08/21 09:00 List NPK
871 Final check 1 hr 19/08/21 22:00 19/08/21 23:00 InsP NPK
872 CM-003-B (RECYCLE CRUSHER) - Penggantian Internal 300000374853 3 days 20/08/21 07:00 22/08/21 23:00
873 Pengamanan area 1 hr 20/08/21 07:00 20/08/21 08:00 Opr NPK-1
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
874 Lepas v-belt 2 hrs 20/08/21 08:00 20/08/21 10:00 Mek NPK
875 Lepas housing crusher 2 hrs 20/08/21 10:00 20/08/21 13:00 Mek NPK
876 Lepas rotor crusher 2 hrs 20/08/21 13:00 20/08/21 15:00 Mek NPK
877 Lepas pulley rotor 2 hrs 20/08/21 15:00 20/08/21 17:00 Mek NPK
878 Lepas bearing inboard&outboard 2 hrs 20/08/21 17:00 20/08/21 20:00 Mek NPK
879 Ganti chain hammer 4 hrs 20/08/21 20:00 21/08/21 08:00 Mek NPK
880 Pasang bearing inboard&outboard 4 hrs 21/08/21 08:00 21/08/21 13:00 Mek NPK
881 Pasang pulley rotor 3 hrs 21/08/21 13:00 21/08/21 16:00 Mek NPK
882 Pasang rotor crusher 3 hrs 21/08/21 16:00 21/08/21 20:00 Mek NPK
883 Ganti pulley motor 3 hrs 21/08/21 20:00 21/08/21 23:00 Mek NPK
884 Ganti rubber seal housing crusher 6 hrs 22/08/21 07:00 22/08/21 14:00 Mek NPK
885 Pasang housing crusher 5 hrs 22/08/21 14:00 22/08/21 20:00 Mek NPK
886 Ganti baut housing crusher 1 hr 22/08/21 19:00 22/08/21 20:00 Mek NPK
887 Pasang v-belt baru 2 hrs 22/08/21 20:00 22/08/21 22:00 Mek NPK
888 PM motor 1 hr 20/08/21 08:00 20/08/21 09:00 List NPK
889 Final check 1 hr 22/08/21 22:00 22/08/21 23:00 InsP NPK
890 SCREEN 20 days 02/08/21 07:00 21/08/21 23:00
891 CX-002-A (1st SCREEN) 6 days 02/08/21 07:00 07/08/21 23:00
892 Penggantian Support&Platform 200000201251 6 days 02/08/21 07:00 07/08/21 23:00
893 Pengamanan Area 2 hrs 02/08/21 07:00 02/08/21 09:00 Opr NPK-1
894 Bongkar support dan platform lama 1 day 02/08/21 07:00 02/08/21 23:00 Beng S2 NPK (8)
895 pasang support dan platform baru 3 days 04/08/21 07:00 06/08/21 23:00 Beng S2 NPK (8)
896 Finnishing 1 day 07/08/21 07:00 07/08/21 23:00 Mek NPK;Beng S2 NPK (8)
897 Optimalisasi 300000374848 5,64 days 02/08/21 13:00 07/08/21 23:00
898 Lepas cover screen 2 hrs 02/08/21 13:00 02/08/21 15:00 Mek NPK
899 Lepas baut adjuster screen 1 hr 02/08/21 15:00 02/08/21 16:00 Mek NPK
900 Lepas baut arm screen 1 hr 02/08/21 16:00 02/08/21 17:00 Mek NPK
901 Lepas screen 2 hrs 02/08/21 17:00 02/08/21 20:00 Mek NPK
902 Lepas rubber penjepit screen 1 hr 02/08/21 20:00 02/08/21 21:00 Mek NPK
903 Lepas rubber mounting vibrator 2 hrs 02/08/21 21:00 02/08/21 23:00 Mek NPK
904 Pasang rubber penjepit screen baru 4 hrs 06/08/21 15:00 06/08/21 20:00 Mek NPK
905 Pasang screen baru (mesh 6x6) 6 hrs 06/08/21 20:00 07/08/21 10:00 Mek NPK
906 Ganti baut arm screen 2 hrs 07/08/21 10:00 07/08/21 13:00 Mek NPK
907 Pasang baut adjuster screen baru 2 hrs 07/08/21 13:00 07/08/21 15:00 Mek NPK
908 Pasang cover screen 2 hrs 07/08/21 15:00 07/08/21 17:00 Mek NPK
909 Pasang rubber mounting vibrator baru 4 hrs 07/08/21 17:00 07/08/21 22:00 Mek NPK
910 Ganti kabel power dari MCC ke lapangan 2 hrs 07/08/21 15:00 07/08/21 17:00 List NPK
911 PM motor 1 hr 07/08/21 17:00 07/08/21 18:00 List NPK
912 Final check 1 hr 07/08/21 22:00 07/08/21 23:00 InsP NPK
913 CX-002-B (1st SCREEN) 9 days 03/08/21 07:00 11/08/21 23:00
914 Penggantian Support&Platform 200000201252 9 days 03/08/21 07:00 11/08/21 23:00
915 Pengamanan Area 2 hrs 03/08/21 07:00 03/08/21 09:00 Opr NPK-1
916 Bongkar support dan platform lama 1 day 03/08/21 07:00 03/08/21 23:00 Beng S2 NPK (8)
917 pasang support dan platform baru 3 days 08/08/21 07:00 10/08/21 23:00 Beng S2 NPK (8)
918 Finnishing 1 day 11/08/21 07:00 11/08/21 23:00 Mek NPK;Beng S2 NPK (8)
919 Optimalisasi 300000374849 8,64 days 03/08/21 13:00 11/08/21 23:00
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
920 Lepas cover screen 2 hrs 03/08/21 13:00 03/08/21 15:00 Mek NPK
921 Lepas baut adjuster screen 1 hr 03/08/21 15:00 03/08/21 16:00 Mek NPK
922 Lepas baut arm screen 1 hr 03/08/21 16:00 03/08/21 17:00 Mek NPK
923 Lepas screen 2 hrs 03/08/21 17:00 03/08/21 20:00 Mek NPK
924 Lepas rubber penjepit screen 1 hr 03/08/21 20:00 03/08/21 21:00 Mek NPK
925 Lepas rubber mounting vibrator 2 hrs 03/08/21 21:00 03/08/21 23:00 Mek NPK
926 Pasang rubber penjepit screen baru 4 hrs 10/08/21 15:00 10/08/21 20:00 Mek NPK
927 Pasang screen baru (mesh 6x6) 6 hrs 10/08/21 20:00 11/08/21 10:00 Mek NPK
928 Ganti baut arm screen 2 hrs 11/08/21 10:00 11/08/21 13:00 Mek NPK
929 Pasang baut adjuster screen baru 2 hrs 11/08/21 13:00 11/08/21 15:00 Mek NPK
930 Pasang cover screen 2 hrs 11/08/21 15:00 11/08/21 17:00 Mek NPK
931 Pasang rubber mounting vibrator baru 4 hrs 11/08/21 17:00 11/08/21 22:00 Mek NPK
932 Ganti kabel power dari MCC ke lapangan 2 hrs 11/08/21 15:00 11/08/21 17:00 List NPK
933 PM motor 1 hr 11/08/21 17:00 11/08/21 18:00 List NPK
934 Final check 1 hr 11/08/21 22:00 11/08/21 23:00 InsP NPK
935 CX-003-A (2nd SCREEN) 6 days 12/08/21 07:00 17/08/21 23:00
936 Penggantian Support&Platform 200000201417 6 days 12/08/21 07:00 17/08/21 23:00
937 Pengamanan Area 2 hrs 12/08/21 07:00 12/08/21 09:00 Opr NPK-1
938 Bongkar support dan platform lama 1 day 12/08/21 07:00 12/08/21 23:00 Beng S2 NPK (8)
939 pasang support dan platform baru 3 days 14/08/21 07:00 16/08/21 23:00 Beng S2 NPK (8)
940 Finnishing 1 day 17/08/21 07:00 17/08/21 23:00 Mek NPK;Beng S2 NPK (8)
941 Optimalisasi 300000374850 5,64 days 12/08/21 13:00 17/08/21 23:00
942 Lepas cover screen 2 hrs 12/08/21 13:00 12/08/21 15:00 Mek NPK
943 Lepas baut adjuster screen 1 hr 12/08/21 15:00 12/08/21 16:00 Mek NPK
944 Lepas baut arm screen 1 hr 12/08/21 16:00 12/08/21 17:00 Mek NPK
945 Lepas screen 2 hrs 12/08/21 17:00 12/08/21 20:00 Mek NPK
946 Lepas rubber penjepit screen 1 hr 12/08/21 20:00 12/08/21 21:00 Mek NPK
947 Lepas rubber mounting vibrator 2 hrs 12/08/21 21:00 12/08/21 23:00 Mek NPK
948 Pasang rubber penjepit screen baru 4 hrs 16/08/21 15:00 16/08/21 20:00 Mek NPK
949 Pasang screen baru (mesh 2.5x15) 6 hrs 16/08/21 20:00 17/08/21 10:00 Mek NPK
950 Ganti baut arm screen 2 hrs 17/08/21 10:00 17/08/21 13:00 Mek NPK
951 Pasang baut adjuster screen baru 2 hrs 17/08/21 13:00 17/08/21 15:00 Mek NPK
952 Pasang cover screen 2 hrs 17/08/21 15:00 17/08/21 17:00 Mek NPK
953 Pasang rubber mounting vibrator baru 4 hrs 17/08/21 17:00 17/08/21 22:00 Mek NPK
954 Pasang kabel kabel tray & support flow switch 2 hrs 17/08/21 15:00 17/08/21 17:00 List NPK
955 PM motor 1 hr 17/08/21 17:00 17/08/21 18:00 List NPK
956 Final check 1 hr 17/08/21 22:00 17/08/21 23:00 InsP NPK
957 CX-003-B (2nd SCREEN) 9 days 13/08/21 07:00 21/08/21 23:00
958 Penggantian Support&Platform 200000201419 9 days 13/08/21 07:00 21/08/21 23:00
959 Pengamanan Area 2 hrs 13/08/21 07:00 13/08/21 09:00 Opr NPK-1
960 Bongkar support dan platform lama 1 day 13/08/21 07:00 13/08/21 23:00 Beng S2 NPK (8)
961 pasang support dan platform baru 3 days 18/08/21 07:00 20/08/21 23:00 Beng S2 NPK (8)
962 Finnishing 1 day 21/08/21 07:00 21/08/21 23:00 Mek NPK;Beng S2 NPK (8)
963 Optimalisasi 300000374851 8,64 days 13/08/21 13:00 21/08/21 23:00
964 Lepas cover screen 2 hrs 13/08/21 13:00 13/08/21 15:00 Mek NPK
965 Lepas baut adjuster screen 1 hr 13/08/21 15:00 13/08/21 16:00 Mek NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
966 Lepas baut arm screen 1 hr 13/08/21 16:00 13/08/21 17:00 Mek NPK
967 Lepas screen 2 hrs 13/08/21 17:00 13/08/21 20:00 Mek NPK
968 Lepas rubber penjepit screen 1 hr 13/08/21 20:00 13/08/21 21:00 Mek NPK
969 Lepas rubber mounting vibrator 2 hrs 13/08/21 21:00 13/08/21 23:00 Mek NPK
970 Pasang rubber penjepit screen baru 4 hrs 20/08/21 15:00 20/08/21 20:00 Mek NPK
971 Pasang screen baru (mesh 2.5x15) 6 hrs 20/08/21 20:00 21/08/21 10:00 Mek NPK
972 Ganti baut arm screen 2 hrs 21/08/21 10:00 21/08/21 13:00 Mek NPK
973 Pasang baut adjuster screen baru 2 hrs 21/08/21 13:00 21/08/21 15:00 Mek NPK
974 Pasang cover screen 2 hrs 21/08/21 15:00 21/08/21 17:00 Mek NPK
975 Pasang rubber mounting vibrator baru 4 hrs 21/08/21 17:00 21/08/21 22:00 Mek NPK
976 Pasang kabel kabel tray & support flow switch 2 hrs 21/08/21 15:00 21/08/21 17:00 List NPK
977 PM motor 1 hr 21/08/21 17:00 21/08/21 18:00 List NPK
978 Final check 1 hr 21/08/21 22:00 21/08/21 23:00 InsP NPK
979 FURNACE 9,14 days 02/08/21 07:00 11/08/21 09:00
980 CF-001 (FURNACE) - Optimalisasi 300000372649 4 days 02/08/21 07:00 05/08/21 23:00
981 Ganti Ignition Electrode&HT lead kabel 3 hrs 02/08/21 07:00 02/08/21 10:00 InsT NPK
982 ganti UV flame detector 3 hrs 02/08/21 10:00 02/08/21 14:00 InsT NPK
983 Ganti Ignition electrode 3 hrs 02/08/21 14:00 02/08/21 17:00 InsT NPK
984 Ganti Linkage damper udara dan gas 3 hrs 02/08/21 17:00 02/08/21 21:00 InsT NPK
985 Ganti pressure switch udara 3 hrs 02/08/21 21:00 03/08/21 08:00 InsT NPK
986 Ganti pressure switch gas 3 hrs 03/08/21 08:00 03/08/21 11:00 InsT NPK
987 Cleaning dan greasing CAM assembly 2 hrs 03/08/21 11:00 03/08/21 14:00 InsT NPK
988 Cleaning&greasing rail combustion head 2 hrs 03/08/21 14:00 03/08/21 16:00 InsT NPK
989 Cleaning&kencangkan terminasi mainburn 2 hrs 03/08/21 16:00 03/08/21 18:00 InsT NPK
990 Cek dan cleaning Panel PLC Burner 2 hrs 03/08/21 19:00 03/08/21 21:00 InsT NPK
991 Cek dan stroke bukaan Damper udara C002 2 hrs 03/08/21 21:00 03/08/21 23:00 InsT NPK
992 Kalibrasi FT 104, CPT001, CTT001, XV201 2 hrs 04/08/21 07:00 04/08/21 09:00 InsT NPK
993 Kalibrasi CPT201, CTT002, CTT2201 2 hrs 04/08/21 09:00 04/08/21 11:00 InsT NPK
994 Test function gas leaktest system 2 hrs 04/08/21 11:00 04/08/21 14:00 InsT NPK
995 Bongkar Panel PLC burner lama 2 hrs 04/08/21 14:00 04/08/21 16:00 InsT NPK
996 Cleaning Transmitter dan PG field burner 2 hrs 04/08/21 16:00 04/08/21 18:00 InsT NPK
997 Pasang pressure transmitter PT104 2 hrs 04/08/21 19:00 04/08/21 21:00 InsT NPK
998 Pasang leaktest system gas burner 2 hrs 04/08/21 21:00 04/08/21 23:00 InsT NPK
999 Aktifkan interlock system Burner 2 hrs 05/08/21 07:00 05/08/21 09:00 InsT NPK
1000 Ganti Gas Multibloc (Leak test system) 3 hrs 05/08/21 09:00 05/08/21 13:00 InsT NPK
1001 Ganti Flexible hose 2 hrs 05/08/21 13:00 05/08/21 15:00 InsT NPK
1002 Ganti tubing CPT001 2 hrs 05/08/21 15:00 05/08/21 17:00 InsT NPK
1003 Ganti Filter gas 2 hrs 05/08/21 17:00 05/08/21 20:00 InsT NPK
1004 Ganti transformer burner 3 hrs 05/08/21 20:00 05/08/21 23:00 InsT NPK
1005 CF-001 (FURNACE) - Penggantian pipa line gas 300000396621 5,14 days 06/08/21 07:00 11/08/21 09:00
1006 LEPAS FT104 1 hr 06/08/21 07:00 06/08/21 08:00 InsT NPK
1007 LEPAS PRESSURE REGULATOR TK1 1 hr 06/08/21 08:00 06/08/21 09:00 InsT NPK
1008 LEPAS XV201 1 hr 06/08/21 09:00 06/08/21 10:00 InsT NPK
1009 LEPAS FILTER 1 hr 06/08/21 10:00 06/08/21 11:00 InsT NPK
1010 LEPAS PRESSURE REGULATOR TK2 1 hr 06/08/21 11:00 06/08/21 13:00 InsT NPK
1011 Penggantian Pipa 1,57 days 09/08/21 07:00 10/08/21 16:00
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1012 Bongkar Perpipaan Lama 4 hrs 09/08/21 07:00 09/08/21 11:00 Beng S2 NPK (2)
1013 Fabrikasi Perpipaan Baru 8 hrs 09/08/21 11:00 09/08/21 21:00 Beng S2 NPK (2)
1014 Pasang Perpipaan Baru 10 hrs 09/08/21 21:00 10/08/21 16:00 Beng S2 NPK (2)
1015 Cek inspeksi 2 hrs 10/08/21 14:00 10/08/21 16:00 InsP NPK
1016 PASANG FT104 1 hr 10/08/21 16:00 10/08/21 17:00 InsT NPK
1017 PASANG PRESSURE REGULATOR TK1 1 hr 10/08/21 17:00 10/08/21 18:00 InsT NPK
1018 PASANG XV201 1 hr 10/08/21 19:00 10/08/21 20:00 InsT NPK
1019 PASANG FILTER 1 hr 10/08/21 20:00 10/08/21 21:00 InsT NPK
1020 PASANG PRESSURE REGULATOR TK2 1 hr 10/08/21 21:00 10/08/21 22:00 InsT NPK
1021 PASANG PRESSURE TRANSMITTER 1 hr 10/08/21 22:00 10/08/21 23:00 InsT NPK
1022 PASANG PRESSURE SWITCH 1 hr 11/08/21 07:00 11/08/21 08:00 InsT NPK
1023 CEK DAN CAT FLEXIBLE HOSE 1 hr 11/08/21 08:00 11/08/21 09:00 InsT NPK
1024 SCREW FEEDER 1 day 22/08/21 07:00 22/08/21 23:00
1025 CM-007 (SCREW FEEDER PEWARNA) - Penggantian Gearbox 200000200407 1 day 22/08/21 07:00 22/08/21 23:00
1026 Pengamanan area 1 hr 22/08/21 07:00 22/08/21 08:00 Opr NPK-1
1027 Lepas power perkabelan listrik 1 hr 22/08/21 08:00 22/08/21 09:00 List NPK
1028 Turunkan screw feeder unit 2 hrs 22/08/21 09:00 22/08/21 11:00 Mek NPK
1029 Cleaning internal screw feeder 1 hr 22/08/21 11:00 22/08/21 13:00 Mek NPK
1030 Cek&greasing bearing screw feeder 1 hr 22/08/21 13:00 22/08/21 14:00 Mek NPK
1031 Lepas gearbox unit 2 hrs 22/08/21 14:00 22/08/21 16:00 Mek NPK
1032 Pasang gearbox unit baru 2 hrs 22/08/21 16:00 22/08/21 18:00 Mek NPK
1033 Angkat&pasang screw feeder unit 2 hrs 22/08/21 19:00 22/08/21 21:00 Mek NPK
1034 Pasang power perkabelan listrik 1 hr 22/08/21 21:00 22/08/21 22:00 List NPK
1035 Final check 1 hr 22/08/21 22:00 22/08/21 23:00 InsP NPK
1036 CM-007 (SCREW FEEDER PEWARNA) - Pemasangan Modul IO Vibrator 300000376905 0,64 days 22/08/21 07:00 22/08/21 17:00

1037 Pasang Modul IO vibrator 9 hrs 22/08/21 07:00 22/08/21 17:00 InsT NPK
1038 HOPPER 6 days 02/08/21 07:00 07/08/21 23:00
1039 CV-001-A (HOPPER) - Penggantian Hopper 300000376934 1 day 02/08/21 07:00 02/08/21 23:00
1040 Pasang Scafolding 1,5 hrs 02/08/21 07:00 02/08/21 08:30 Beng S3
1041 Bongkar & ukur Hopper Lama 3 hrs 02/08/21 08:30 02/08/21 11:30 Beng S2 NPK (9)
1042 Pasang Hopper Baru 8 hrs 02/08/21 12:30 02/08/21 21:30 Beng S2 NPK (9)
1043 Bongkar scaffolding 1,5 hrs 02/08/21 21:30 02/08/21 23:00 Beng S3
1044 CV-001-B (HOPPER) - Penggantian Hopper 300000376935 1 day 03/08/21 07:00 03/08/21 23:00
1045 Pasang Scafolding 1,5 hrs 03/08/21 07:00 03/08/21 08:30 Beng S3
1046 Bongkar & ukur Hopper Lama 3 hrs 03/08/21 08:30 03/08/21 11:30 Beng S2 NPK (9)
1047 Pasang Hopper Baru 8 hrs 03/08/21 12:30 03/08/21 21:30 Beng S2 NPK (9)
1048 Bongkar scaffolding 1,5 hrs 03/08/21 21:30 03/08/21 23:00 Beng S3
1049 CV-001-C (HOPPER) - Penggantian Hopper 300000376936 1 day 04/08/21 07:00 04/08/21 23:00
1050 Pasang Scafolding 1,5 hrs 04/08/21 07:00 04/08/21 08:30 Beng S3
1051 Bongkar & ukur Hopper Lama 3 hrs 04/08/21 08:30 04/08/21 11:30 Beng S2 NPK (9)
1052 Pasang Hopper Baru 8 hrs 04/08/21 12:30 04/08/21 21:30 Beng S2 NPK (9)
1053 Bongkar scaffolding 1,5 hrs 04/08/21 21:30 04/08/21 23:00 Beng S3
1054 CV-001-D (HOPPER) - Penggantian Hopper 300000374143 1 day 05/08/21 07:00 05/08/21 23:00
1055 Pasang Scafolding 1,5 hrs 05/08/21 07:00 05/08/21 08:30 Beng S3
1056 Bongkar & ukur Hopper Lama 3 hrs 05/08/21 08:30 05/08/21 11:30 Beng S2 NPK (9)
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1057 Pasang Hopper Baru 8 hrs 05/08/21 12:30 05/08/21 21:30 Beng S2 NPK (9)
1058 Bongkar scaffolding 1,5 hrs 05/08/21 21:30 05/08/21 23:00 Beng S3
1059 CV-001-E (HOPPER) - Penggantian Hopper 300000374146 1 day 06/08/21 07:00 06/08/21 23:00
1060 Pasang Scafolding 1,5 hrs 06/08/21 07:00 06/08/21 08:30 Beng S3
1061 Bongkar & ukur Hopper Lama 3 hrs 06/08/21 08:30 06/08/21 11:30 Beng S2 NPK (9)
1062 Pasang Hopper Baru 8 hrs 06/08/21 12:30 06/08/21 21:30 Beng S2 NPK (9)
1063 Bongkar scaffolding 1,5 hrs 06/08/21 21:30 06/08/21 23:00 Beng S3
1064 CV-001-F (HOPPER) - Penggantian Hopper 300000374147 1 day 07/08/21 07:00 07/08/21 23:00
1065 Pasang Scafolding 1,5 hrs 07/08/21 07:00 07/08/21 08:30 Beng S3
1066 Bongkar & ukur Hopper Lama 3 hrs 07/08/21 08:30 07/08/21 11:30 Beng S2 NPK (9)
1067 Pasang Hopper Baru 8 hrs 07/08/21 12:30 07/08/21 21:30 Beng S2 NPK (9)
1068 Bongkar scaffolding 1,5 hrs 07/08/21 21:30 07/08/21 23:00 Beng S3
1069 BAGGING MACHINE 11,29 days 08/08/21 07:00 19/08/21 11:00
1070 CX-004-A (BAGGING MACHINE) - Penggantian Platform&Hopper 300000376913 4 days 08/08/21 07:00 11/08/21 23:00
1071 Ukur & bongkar hopper lama 4 hrs 08/08/21 07:00 08/08/21 11:00 Beng S2 NPK (9)
1072 Fabrikasi hopper 10 hrs 08/08/21 11:00 08/08/21 23:00 Beng S2 NPK (9)
1073 Pemasangan hopper baru 1 day 09/08/21 07:00 09/08/21 23:00 Beng S2 NPK (9)
1074 Perkuat area penggedoran 10 hrs 10/08/21 07:00 10/08/21 18:00 Beng S2 NPK (9)
1075 Penguatan platform 12 hrs 10/08/21 19:00 11/08/21 16:00 Beng S2 NPK (9)
1076 Coating hopper & platform 6 hrs 11/08/21 16:00 11/08/21 23:00 Beng S3
1077 CX-004-A (BAGGING MACHINE) - Penggantian Air Cylinder 200000201767 3,29 days 12/08/21 07:00 15/08/21 11:00
1078 Ganti bearing rotary damper 10 hrs 12/08/21 07:00 12/08/21 18:00 Mek NPK
1079 Ganti bearing rotary gate 8 hrs 12/08/21 19:00 13/08/21 11:00 Mek NPK
1080 Lepas connection loadcell selama shtdown 1 hr 13/08/21 11:00 13/08/21 13:00 InsT NPK
1081 Ganti loadcell 2 hrs 13/08/21 13:00 13/08/21 15:00 InsT NPK
1082 Ganti proximity sensor discharge door 2 hrs 13/08/21 15:00 13/08/21 17:00 InsT NPK
1083 Ganti hand switch clamp bag 2 hrs 13/08/21 17:00 13/08/21 20:00 InsT NPK
1084 Ganti air cylinder clamp bag 2 hrs 13/08/21 20:00 13/08/21 22:00 InsT NPK
1085 Ganti air cylinder Discharge door 2 hrs 13/08/21 22:00 14/08/21 08:00 InsT NPK
1086 Ganti air cylinder dribble feed 2 hrs 14/08/21 08:00 14/08/21 10:00 InsT NPK
1087 Ganti air cylinder fine feed 2 hrs 14/08/21 10:00 14/08/21 13:00 InsT NPK
1088 Bersihkan pnel lokal slenoid valve&cek 1 hr 14/08/21 13:00 14/08/21 14:00 InsT NPK
1089 Bersihkan panel JB clamp bag dan bucket 1 hr 14/08/21 14:00 14/08/21 15:00 InsT NPK
1090 Kalibrasi zerro-span dg batu timbang 50K 1 hr 14/08/21 15:00 14/08/21 16:00 InsT NPK
1091 Aktifkan loadcell dan controller 1 hr 14/08/21 16:00 14/08/21 17:00 InsT NPK
1092 Ganti rubber stopper rotary damper 1 hr 14/08/21 17:00 14/08/21 18:00 InsT NPK
1093 Ganti plastic brush 1 hr 14/08/21 19:00 14/08/21 20:00 InsT NPK
1094 Ganti sealing rubber 1 hr 14/08/21 20:00 14/08/21 21:00 InsT NPK
1095 GANTI Bearing support discharge door 2 hrs 14/08/21 21:00 14/08/21 23:00 InsT NPK
1096 Ganti regulator udara Juction box soleno 2 hrs 15/08/21 07:00 15/08/21 09:00 InsT NPK
1097 Ganti solenoid valve + manifold JB solen 2 hrs 15/08/21 09:00 15/08/21 11:00 InsT NPK
1098 Cleaning panel control 1 hr 12/08/21 07:00 12/08/21 08:00 List NPK
1099 PM motor 1 hr 12/08/21 08:00 12/08/21 09:00 List NPK
1100 CX-004-B (BAGGING MACHINE) - Penggantian Platform&Hopper 300000376914 4 days 12/08/21 07:00 15/08/21 23:00
1101 Ukur & bongkar hopper lama 4 hrs 12/08/21 07:00 12/08/21 11:00 Beng S2 NPK (9)
1102 Fabrikasi hopper 10 hrs 12/08/21 11:00 12/08/21 23:00 Beng S2 NPK (9)
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1103 Pemasangan hopper baru 1 day 13/08/21 07:00 13/08/21 23:00 Beng S2 NPK (9)
1104 Perkuat area penggedoran 10 hrs 14/08/21 07:00 14/08/21 18:00 Beng S2 NPK (9)
1105 Penguatan platform 12 hrs 14/08/21 19:00 15/08/21 16:00 Beng S2 NPK (9)
1106 Coating hopper & platform 6 hrs 15/08/21 16:00 15/08/21 23:00 Beng S3
1107 CX-004-B (BAGGING MACHINE) - Penggantian Air Cylinder 200000201885 3,29 days 16/08/21 07:00 19/08/21 11:00
1108 Ganti bearing rotary damper 10 hrs 16/08/21 07:00 16/08/21 18:00 Mek NPK
1109 Ganti bearing rotary gate 8 hrs 16/08/21 19:00 17/08/21 11:00 Mek NPK
1110 Lepas connection loadcell selama shtdown 1 hr 17/08/21 11:00 17/08/21 13:00 InsT NPK
1111 Ganti loadcell 2 hrs 17/08/21 13:00 17/08/21 15:00 InsT NPK
1112 Ganti proximity sensor discharge door 2 hrs 17/08/21 15:00 17/08/21 17:00 InsT NPK
1113 Ganti hand switch clamp bag 2 hrs 17/08/21 17:00 17/08/21 20:00 InsT NPK
1114 Ganti air cylinder clamp bag 2 hrs 17/08/21 20:00 17/08/21 22:00 InsT NPK
1115 Ganti air cylinder Discharge door 2 hrs 17/08/21 22:00 18/08/21 08:00 InsT NPK
1116 Ganti air cylinder dribble feed 2 hrs 18/08/21 08:00 18/08/21 10:00 InsT NPK
1117 Ganti air cylinder fine feed 2 hrs 18/08/21 10:00 18/08/21 13:00 InsT NPK
1118 Bersihkan pnel lokal slenoid valve&cek 1 hr 18/08/21 13:00 18/08/21 14:00 InsT NPK
1119 Bersihkan panel JB clamp bag dan bucket 1 hr 18/08/21 14:00 18/08/21 15:00 InsT NPK
1120 Kalibrasi zerro-span dg batu timbang 50K 1 hr 18/08/21 15:00 18/08/21 16:00 InsT NPK
1121 Aktifkan loadcell dan controller 1 hr 18/08/21 16:00 18/08/21 17:00 InsT NPK
1122 Ganti rubber stopper rotary damper 1 hr 18/08/21 17:00 18/08/21 18:00 InsT NPK
1123 Ganti plastic brush 1 hr 18/08/21 19:00 18/08/21 20:00 InsT NPK
1124 Ganti sealing rubber 1 hr 18/08/21 20:00 18/08/21 21:00 InsT NPK
1125 GANTI Bearing support discharge door 2 hrs 18/08/21 21:00 18/08/21 23:00 InsT NPK
1126 Ganti regulator udara Juction box soleno 2 hrs 19/08/21 07:00 19/08/21 09:00 InsT NPK
1127 Ganti solenoid valve + manifold JB solen 2 hrs 19/08/21 09:00 19/08/21 11:00 InsT NPK
1128 Cleaning panel control 1 hr 16/08/21 07:00 16/08/21 08:00 List NPK
1129 PM motor 1 hr 16/08/21 08:00 16/08/21 09:00 List NPK
1130 INSTRUMENTASI 3,14 days 10/08/21 11:00 13/08/21 14:00
1131 CFT-205-NPK1 (FLOW TRANSMIT LINE WATER R-001) - Preventive Maintenance 0,5 days 10/08/21 11:00 10/08/21 20:00
300000401579
1132 Lepas kabel&koneksi tubing transmitter 1 hr 10/08/21 11:00 10/08/21 13:00 InsT NPK
1133 Flushing sisi High dan Low transmitter 1 hr 10/08/21 13:00 10/08/21 14:00 InsT NPK
1134 Cleaning , cek dan kalibrasi 2 hrs 10/08/21 14:00 10/08/21 16:00 InsT NPK
1135 Pasang transmitter beserta aksesorisnya 2 hrs 10/08/21 16:00 10/08/21 18:00 InsT NPK
1136 Cek indikasi di lokal transmitter&HMI 1 hr 10/08/21 19:00 10/08/21 20:00 InsT NPK
1137 CFT-207-NPK1 (FLOW TRANSMIT LINE STEAM R-001) - Preventive Maintenance 0,5 days 10/08/21 20:00 11/08/21 11:00
300000401578
1138 Lepas kabel&koneksi tubing transmitter 1 hr 10/08/21 20:00 10/08/21 21:00 InsT NPK
1139 Flushing sisi High dan Low transmitter 1 hr 10/08/21 21:00 10/08/21 22:00 InsT NPK
1140 Cleaning , cek dan kalibrasi 2 hrs 10/08/21 22:00 11/08/21 08:00 InsT NPK
1141 Pasang transmitter beserta aksesorisnya 2 hrs 11/08/21 08:00 11/08/21 10:00 InsT NPK
1142 Cek indikasi di lokal transmitter&HMI 1 hr 11/08/21 10:00 11/08/21 11:00 InsT NPK
1143 CIJP-X-004-A (INK JET PRINT FOR X-004-A) - Cleaning 300000395231 0,29 days 11/08/21 11:00 11/08/21 16:00
1144 Cleaning Printhead 1 hr 11/08/21 11:00 11/08/21 13:00 InsT NPK
1145 Cleaning Main board dan Casing AX150 1 hr 11/08/21 13:00 11/08/21 14:00 InsT NPK
1146 Cleaning stand dan bracket IJP Domino 1 hr 11/08/21 14:00 11/08/21 15:00 InsT NPK
1147 Cleaning filter udara IJP Domino AX15 1 hr 11/08/21 14:00 11/08/21 15:00 InsT NPK
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1148 Ganti tinta dan make up 1 hr 11/08/21 15:00 11/08/21 16:00 InsT NPK
1149 CIJP-X-004-B (INK JET PRINT FOR X-004-B) - Cleaning 300000395230 0,29 days 11/08/21 16:00 11/08/21 21:00
1150 Cleaning Printhead 1 hr 11/08/21 16:00 11/08/21 17:00 InsT NPK
1151 Cleaning Main board dan Casing AX150 1 hr 11/08/21 17:00 11/08/21 18:00 InsT NPK
1152 Cleaning stand dan bracket IJP Domino 1 hr 11/08/21 19:00 11/08/21 20:00 InsT NPK
1153 Cleaning filter udara IJP Domino AX15 1 hr 11/08/21 19:00 11/08/21 20:00 InsT NPK
1154 Ganti tinta dan make up 1 hr 11/08/21 20:00 11/08/21 21:00 InsT NPK
1155 COWS-PLC-NPKG-1 (PC HMI NPKG1) - Pemasangan&Optimalisasi 300000376049 0,43 days 11/08/21 21:00 12/08/21 11:00
1156 Pemasangan Indicator Ampere Elevator HMI 1 hr 11/08/21 21:00 11/08/21 22:00 InsT NPK
1157 Pemasangan Indicator Ampere Conveyor HMI 1 hr 11/08/21 22:00 11/08/21 23:00 InsT NPK
1158 Penambahan Modul IO HMI 1 hr 12/08/21 07:00 12/08/21 08:00 InsT NPK
1159 Pemasangan Flow Switch di Weigher BB NPK 1 hr 12/08/21 08:00 12/08/21 09:00 InsT NPK
1160 Pemasangan Start-Stop Vibrator di HMI 1 hr 12/08/21 08:00 12/08/21 09:00 InsT NPK
1161 Cleaning PC dan Monitor OWS1&OWS2 1 hr 12/08/21 09:00 12/08/21 10:00 InsT NPK
1162 Ganti battery keyboard dan mouse PC OWS1 1 hr 12/08/21 09:00 12/08/21 10:00 InsT NPK
1163 Penambahan Equipment yang bisa dikontrol 1 hr 12/08/21 10:00 12/08/21 11:00 InsT NPK
1164 CPLC-NPKG-1 (PLC FOR NPKG1) - Optimalisasi 300000401180 0,29 days 12/08/21 11:00 12/08/21 16:00
1165 Cleaning PC dan Monitor OWS1&OWS2 1 hr 12/08/21 11:00 12/08/21 13:00 InsT NPK
1166 Ganti battery keyboard dan mouse PC OWS1 1 hr 12/08/21 13:00 12/08/21 14:00 InsT NPK
1167 Penambahan Equipment yang bisa dikontrol 1 hr 12/08/21 14:00 12/08/21 15:00 InsT NPK
1168 Cleaning Panel PLC front dan back panel 1 hr 12/08/21 14:00 12/08/21 15:00 InsT NPK
1169 Cek dan kencangkan terminasi 1 hr 12/08/21 15:00 12/08/21 16:00 InsT NPK
1170 CTT-2201 (TEMP TRANSMIT FOR R-002) - Preventive Maintenance 300000396622 0,43 days 12/08/21 16:00 12/08/21 23:00
1171 CEK DAN KENCANGKA TERMINASI TEMPERATURE 1 hr 12/08/21 16:00 12/08/21 17:00 InsT NPK
1172 LEPAS KONEKSI PERKABELAN DAN TEMPERATURE 1 hr 12/08/21 17:00 12/08/21 18:00 InsT NPK
1173 KALIBRASI TEMP.TRANSMITTER CTT2201 2 hrs 12/08/21 19:00 12/08/21 21:00 InsT NPK
1174 PASANG TEMP.TRASMITTER CTT2201 1 hr 12/08/21 21:00 12/08/21 22:00 InsT NPK
1175 AKTIFKAN DAN MONITORING INDIKASI DI HMI 1 hr 12/08/21 22:00 12/08/21 23:00 InsT NPK
1176 CTI-2201-NPKG-1 (TEMP INDICATOR FOR INLET R-002) - Preventive Maintenance 0,43 days 13/08/21 07:00 13/08/21 14:00
300000396623
1177 CEK DAN KENCANGKA TERMINASI TEMPERATURE 1 hr 13/08/21 07:00 13/08/21 08:00 InsT NPK
1178 LEPAS KONEKSI PERKABELAN DAN TEMPERATURE 1 hr 13/08/21 08:00 13/08/21 09:00 InsT NPK
1179 KALIBRASI TEMP.TRANSMITTER CTT2201 2 hrs 13/08/21 09:00 13/08/21 11:00 InsT NPK
1180 PASANG TEMP.TRASMITTER CTT2201 1 hr 13/08/21 11:00 13/08/21 13:00 InsT NPK
1181 AKTIFKAN DAN MONITORING INDIKASI DI HMI 1 hr 13/08/21 13:00 13/08/21 14:00 InsT NPK
1182 PIPING, STRUKTUR 10 days 12/08/21 07:00 21/08/21 23:00
1183 Penggantian Pipa Service - 200000202152 8 days 14/08/21 07:00 21/08/21 23:00
1184 Ganti line steam 3 days 14/08/21 07:00 16/08/21 23:00 Beng S2 NPK (1)
1185 Ganti line service water 2 days 17/08/21 07:00 18/08/21 23:00 Beng S2 NPK (1)
1186 Ganti line natural gas 3 days 19/08/21 07:00 21/08/21 23:00 Beng S2 NPK (1)
1187 Pengecatan Struktur&Rotary Drum - 911000051863 10 days 12/08/21 07:00 21/08/21 23:00
1188 PENGECATAN STRUKTUR 2 days 12/08/21 07:00 13/08/21 23:00 Beng S3
1189 PENGECATAN DRUM R-001 2 days 14/08/21 07:00 15/08/21 23:00 Beng S3
1190 PENGECATAN DRUM R-002 2 days 16/08/21 07:00 17/08/21 23:00 Beng S3
1191 PENGECATAN DRUM R-003 2 days 18/08/21 07:00 19/08/21 23:00 Beng S3
1192 PENGECATAN DRUM R-004 2 days 20/08/21 07:00 21/08/21 23:00 Beng S3
JADWAL PELAKSANAAN
TA-NPK1-07-2021
Departemen Perencanaan Pemeliharaan & Keandalan
Bagian Perta
31 JULI - 24 AGUSTUS 2021 Rev. 0
ID Task Name Duration Start Finish 25 Jul '21 01 Aug '21 08 Aug '21 15 Aug '21 22 Aug '21
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
1193 JASA PEMELIHARAAN 21 days 02/08/21 07:00 22/08/21 23:00
1194 Jasa Fabrikasi&Pasang Dedusting NPK-1 200000271571 21 days 02/08/21 07:00 22/08/21 23:00
1195 Jasa Fabrikasi&Pasang Dedusting NPK-1 21 days 02/08/21 07:00 22/08/21 23:00 Vendor
1196 Jasa Perbaikan Sidding Atap&Talang NPK-1 200000272191 21 days 02/08/21 07:00 22/08/21 23:00
1197 Jasa Perbaikan Sidding Atap&Talang NPK-1 21 days 02/08/21 07:00 22/08/21 23:00 Vendor
1198 CCUB-X002-A (CUBICAL FOR #1 SCREEN) - Jasa Perbaikan Kabel 200000269679 4 days 02/08/21 07:00 05/08/21 23:00
1199 Jasa Perbaikan kabel X002 AB& X003 AB 4 days 02/08/21 07:00 05/08/21 23:00 Vendor;List NPK
1200 CM-004 (SCRUBBER POOL MIXER) - Jasa Perbaikan Gearbox Mixer 200000203234 4 days 06/08/21 07:00 09/08/21 23:00
1201 Jasa Perbaikan Gear Box Mixer M-004 4 days 06/08/21 07:00 09/08/21 23:00 Vendor;Mek NPK
1202 COWS-PLC-NPKG-1 (PC HMI NPKG1) - Jasa Modifikasi Sistem PLC, HMI NPKG-1 4 days 10/08/21 07:00 13/08/21 23:00
500000004133
1203 JASA MODIFIKASI SYSTEM PLC, HMI NPKG-1 4 days 10/08/21 07:00 13/08/21 23:00 Vendor;InsT NPK
1204 CP-003-M (MOTOR FOR SCRUBBER CIRC PUMP) - Jasa Panel MCC&Dist P-003-B 4 days 14/08/21 07:00 17/08/21 23:00
200000270135
1205 Jasa Panel MCC&Distribusi P-003-B NPK1 4 days 14/08/21 07:00 17/08/21 23:00 Vendor;List NPK
1206 CIA-TR-12 (DIST TRANSFORMER 1000KVA) - Pasang MCC Baru&Modif Panel 4 days 18/08/21 07:00 21/08/21 23:00
500000006411
1207 PASANG MCC BARU&MODIF PANEL DIST. TR12 4 days 18/08/21 07:00 21/08/21 23:00 Vendor;List NPK
1208 CIA-TR-12 (DIST TRANSFORMER 1000KVA) - Jasa BDV DGA&Purifikasi Oli TR-12 & 15 4 days 10/08/21 07:00 13/08/21 23:00
200000269327
1209 Jasa BDV DGA&Purifikasi Oli TR 12 & 15 4 days 10/08/21 07:00 13/08/21 23:00 Vendor;List NPK
1210 CIA-TR-15 (DIST TRANSFORMER 1250KVA) - Jasa Penggantian Kabel Tray 4 days 14/08/21 07:00 17/08/21 23:00
200000205545
1211 Jasa Penggantian Kabel Tray NPK 1 4 days 14/08/21 07:00 17/08/21 23:00 Vendor;List NPK
1212 CPC-BAG-MACHINE (PANEL CONTR BAG MACHINE) - Jasa Perbaikan Kabel Tray 5 days 18/08/21 07:00 22/08/21 23:00
NPK-1 200000269334
1213 Jasa Perbaikan Kabel Tray NPK-1 5 days 18/08/21 07:00 22/08/21 23:00 Vendor;List NPK
1214 COMMISIONING 1 day 23/08/21 07:00 23/08/21 23:00
1215 START UP 1 day 24/08/21 07:00 24/08/21 23:00
1216 Pengisian scrubber pool (50% level) 6 hrs 24/08/21 07:00 24/08/21 14:00 Opr NPK-1
1217 Start CM-004 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1218 Start CX-001 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1219 Start all elevator & Conveyor (bertahap) 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1220 Start CC-003 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1221 Start CC-004 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1222 Start CC-005 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1223 Start CC-006 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1224 Start dan aktifkan furnace 7 ehrs 24/08/21 14:00 24/08/21 21:00 Opr NPK-1
1225 Start screen 1 & 2 (A/B) 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1226 Start CM-003 A/B 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1227 Start CR-003 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1228 Start CR-002 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1229 Start CR-001 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1230 Pengisian hooper bahan baku 1 ehr 24/08/21 14:00 24/08/21 15:00 Opr NPK-1
1231 Aktifkan feeding system 3 ehrs 24/08/21 14:00 24/08/21 17:00 Opr NPK-1
1232 Analisa produk 4 ehrs 24/08/21 17:00 24/08/21 21:00 Opr NPK-1
1233 Start CR-004 & baging machine (finishing system 1 ehr 24/08/21 21:00 24/08/21 22:00 Opr NPK-1
1234 Produk kirim ke baging machine 1 ehr 24/08/21 22:00 24/08/21 23:00 Opr NPK-1