AGRIBANK NYIKA

ARTISANS CONTRACTING PVT LTD


PROGRAM OF WORKS FOR THE EXTENSION AND CUSTOMISATION OF BANK
Project Start Date 11/12/2021 (Friday) Display Week 1.5 Week 1.5 Week 2.5 Week 3.5 Week 4.5 Week 5.5
Project Lead 12/15/2021 (Wednesday) 11 Nov 2021 18 Nov 2021 25 Nov 2021 2 Dec 2021 9 Dec 2021
11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
WORK
WBS TASK LEAD START END % DONE T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
DAYS
1 ELECTRICAL WORKS
Preliminaries and
1.1 Installation of Fri 11/12/21 Fri 11/26/21 60% 15
electricals
2 WALL PLASTERING AND FLOORING
External and Internal
2.1 Sat 11/13/21 Sat 11/20/21 15% 7
Wall Rendering

2.2 Grano Flooring Sat 11/20/21 Thu 11/25/21 0% 5

3 SKIMMING
Skimming of
3.1 Tue 11/23/21 Sun 11/28/21 0% 5
internal walls
4 PLUMBING FITTINGS
Fitting Plumbing
4.1 Wed 11/24/21 Mon 11/29/21 0% 5
Accessories
5 SUSPENDED CEILINGS
Fitting of Suspended
5.1 Sat 11/27/21 Sun 12/05/21 0% 9
Ceiling
6 TILING FOR WALLS AND FLOORS
6.1 Fitting tiles Thu 12/02/21 Fri 12/10/21 0% 8

7 WINDOW FRAMES AND GLAZING


Fitting of Window
7.1 Sun 12/05/21 Sat 12/11/21 0% 7
Frames
8 PAINTING
8.1 Apply paint to walls Mon 12/06/21 Wed 12/15/21 9

9 SITE CLEANING AND HANDOVER


cleaning of site and
9.1 0% 1
hand over