Professional Documents
Culture Documents
Develop the following schedule in MS Project using @Risk for finding out
Probabilistic Total Duration for the project and Probabilistic Finish date.
1 A 12 -
2 B 10 1
3 C 20 2
4 D 7 1
5 E 15 4
6 F 25 1
7 G 14 3,5,6
STEPS:
D (5, 7, 10)
E (12,15,20)
F (20,30)UNIFORM
G (10,14,18)
IV
Red bars:The range between earliest possible start date and latest possible
finish date
Select Produced cell ranges and set it 0<= 5000 and make the group recipe
(method for a set of variables which can change independently. Budget
method used for when the total of adjustable variables must be kept
constant.
Hard constraints means the Risk Optimizer will only retain solutions
where resources are available