a. Hanger 150.38 sqm. ₱ 30.00 ₱ 4,511.40 60% ₱ 2,706.84 30% ₱ 1,353.42 90.00% ₱ 4,060.26
b. Flat Framing 150.38 sqm. ₱ 50.00 ₱ 7,519.00 15% ₱ 1,127.85 35% ₱ 2,631.65 50.00% ₱ 3,759.50
b. Board-up 150.38 sqm. ₱ 40.00 ₱ 6,015.20 ₱- 0% ₱ - ₱-
b. Flat Framing 21.87 sqm. ₱ 60.00 ₱ 1,312.20 100% 1,312.20 0% ₱ - 100.00% ₱ 1,312.20
b. Board-up 21.87 sqm. ₱ 60.00 ₱ 1,312.20 0% 0% ₱ - ₱-
3 Walk in Chiller
TOTAL ₱ 20,670.00
OVERALL
C. DEDUCTIONS
1. RETENTION(10%) = ₱ 913.20
Note:
Ceiling dropwalls & walk in chiller dry wall are excluded from computation
Date: 23-May-19
SUBCONTRACTOR ACCOMPLISHMENT/BILLING REQUEST
a. Hanger 150.38 sqm. ₱30.00 ₱4,511.40 90% ₱4,060.26 0% ₱0.00 90.00% ₱4,060.26
b. Flat Framing 150.38 sqm. ₱50.00 ₱7,519.00 50% ₱3,759.50 40% ₱3,007.60 90.00% ₱6,767.10
b. Board-up 150.38 sqm. ₱40.00 ₱6,015.20 ₱0.00 0% ₱0.00 ₱0.00
3 Walk in Chiller
4 Ceiling Design
TOTAL ₱ 20,670.00
OVERALL
C. DEDUCTIONS
1. RETENTION(10%) = ₱1,213.96
Note:
Ceiling dropwalls & walk in chiller dry wall are excluded from computation
Date: 16-May-19 Perimeter Height
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST TOTAL COST ACCOMPLISHMENT
TOTAL COST
(%) BY ACCOMPLISHMENT
ACCOMPLISHMENT
TOTAL COST
(%) BY ACCOMPLISHMENT
ACCOMPLISHMENT
TOTAL COST
(%) BY ACCOMPLISHMENT
a. Hanger 150.38 sqm. ₱ 30.00 ₱ 4,511.40 60% ₱ 2,706.84 30% ₱ 1,353.42 90.00% ₱ 4,060.26
b. Flat Framing 150.38 sqm. ₱ 50.00 ₱ 7,519.00 15% ₱ 1,127.85 35% ₱ 2,631.65 50.00% ₱ 3,759.50
b. Board-up 150.38 sqm. ₱ 40.00 ₱ 6,015.20 ₱- 0% ₱ - ₱-
0.309136853
2 Drop wall (Front) Sub-total: ₱ 2,624.40
b. Flat Framing 21.87 sqm. ₱ 60.00 ₱ 1,312.20 100% ₱ 1,312.20 0% ₱ - 100.00% ₱ 1,312.20
b. Board-up 21.87 sqm. ₱ 60.00 ₱ 1,312.20 0% ₱ - 0% ₱ - ₱-
3 Walk in Chiller
TOTAL ₱ 20,670.00
OVERALL
C. DEDUCTIONS
1. RETENTION(10%) #ERROR! ₱ 913.20
Note:
Ceiling dropwalls & walk in chiller dry wall are excluded from computation