QUOTATION

Item of works Quantity UNIT Amount


EXCAVATION 12.00 CU. M. 19,568.64
EMBANKMENT 6.00 CU. M. 17,937.92
REINFORCED CONCRETING f 1.80 CU. M. 21,738.31
REINFORCED CONCRETING c 4.32 CU. M. 76,284.27
REINFORCED CONCRETING b 12.00 CU. M. 128,235.74
MASONRY 100.00 SQ. M 90,284.13
Caprentry and joinery 10.00 SQ. M 90,284.13
Plastering 10.00 SQ. M 3,220.67
Floor Finishing 40.00 SQM 13,567.59
TILE WORKS 80.00 SQ. M 123,499.86
PLUMBING FIXTURES 10.00 PCS 63,710.19
Painting works 80.00 SQ. M 68,544.72
Roofing 42.00 SQ. M 45,318.00
Truss and accessories 0.00 lght 39,312.00
Windows and frames 5.00 pcs 36,145.20
DOORS and DOOR FRAME 5.00 pcs 58,422.00
Electrical works 100.00 lngt 43,278.14
Septic tank 20.00 sqm 39,592.22
Pipes and Fittings 50.00 sqm 18,779.34
Railings 229.00 lngt 25,826.02
TOTAL 1,023,549.12

Materials PHP 614,129.47


Prepared by: ________________ Labor PHP 409,419.65
Total cost PHP 1,023,549.12
LABOR COST
Total Manpower Ave Rate/day DAYS Total Workers
4 PHP 400.00 5 PHP 7,827.46 1 foreman 3 helper
4 PHP 400.00 4 PHP 7,175.17 1 foreman 3 helper
6 PHP 600.00 2 PHP 8,695.33 1 steelman 2 mason
6 PHP 600.00 8 PHP 30,513.71 1 steelman 2 mason
6 PHP 600.00 14 PHP 51,294.30 1 steelman 2 mason
6 PHP 600.00 10 PHP 36,113.65 1 steelman 2 mason
4 PHP 500.00 18 PHP 36,113.65 2 carpenter 2 helper
4 PHP 450.00 1 PHP 1,288.27 2mason 2 helper
4 PHP 500.00 3 PHP 5,427.04 2mason 2 helper
6 PHP 450.00 18 PHP 49,399.94 2mason 4 helper
2 PHP 500.00 25 PHP 25,484.08 1plumber 1 helper
3 PHP 450.00 20 PHP 27,417.89 2 painter 1 helper
4 PHP 500.00 9 PHP 18,127.20 2 roofer 2 helper
3 PHP 500.00 10 PHP 15,724.80 2 welder 1 helper
3 PHP 450.00 11 PHP 14,458.08 2 installer 1 helper
2 PHP 450.00 26 PHP 23,368.80 1 carpenter 1 helper
3 PHP 500.00 12 PHP 17,311.26 2 electrician 1 helper
2 PHP 500.00 16 PHP 15,836.89 1 mason helper
3 PHP 450.00 6 PHP 7,511.74 2 plumber 1 helper
3 PHP 500.00 7 PHP 10,330.41 2 welder 1 helper
PHP 409,419.65
Workers

3 helper
3 helper
3 helper
3 helper
Name of Project
LOCATION
Name of Contractor

Structure Excavation Volume = 12

Quantity Unit Description Unit Cost Amount

12.00 Cu.m Excavation 800 ₱ 9,600.00


Materials ₱ 9,600.00
Labor ₱ 3,840.00
Direct Cost ₱ 13,440.00
Mark up ₱ 4,032.00
VAT ₱ 2,096.64
Total Cost ₱ 19,568.64

Structure Embankment volume = 6

Quantity Unit Description Unit Cost Amount

8.00 Cu.m Embankment PHP 1,100.00 ₱ 8,800.00


Materials ₱ 8,800.00
Labor ₱ 3,520.00
Direct Cost ₱ 12,320.00
Mark up ₱ 3,696.00
Vat ₱ 1,921.92
Total Cost ₱ 17,937.92

Christian Ace N. PradesGeneral Manager


Unit
Footings 6
Length 1
width 1
depth 0.3
Volume 1.8

Reinforced Concrete Volume = 1.80

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

13 Bags Cement 240.00 ₱ 3,024.00


2 Cu.m Sand 1,100.00 ₱ 2,217.60
1 Cu.m Gravel 1,600.00 ₱ 1,612.80
Pcs 16mm dia. X 6m 380.00 ₱ -
4 Pcs 12mm dia. X 6m 210.00 ₱ 756.00
14 Pcs 10mm dia. X 6m 160.00 ₱ 2,304.00
10 Kg #16 Tie wires 75.00 ₱ 750.00
Materials ₱ 10,664.40
Labor ₱ 4,265.76
Direct Cost ₱ 14,930.16
Mark up ₱ 4,479.05
VAT ₱ 2,329.10
Total Cost ₱ 21,738.31

Unit
Columns 6
Length 0.4
width 0.3
Height 6
Volume 4.32

Reinforced Concrete Volume = 4.32

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

30 Bags Cement 240.00 ₱ 7,257.60


5 Cu.m Sand 1,100.00 ₱ 5,544.00
3 Cu.m Gravel 1,600.00 ₱ 4,032.00
8 Pcs 16mm dia. X 6m 380.00 ₱ 3,040.00
80 Pcs 12mm dia. X 6m 210.00 ₱ 16,800.00
Pcs 10mm dia. X 6m 160.00 ₱ -
10 Kg #16 Tie wires 75.00 ₱ 750.00
Materials ₱ 37,423.60
Labor ₱ 14,969.44
Direct Cost ₱ 52,393.04
Mark up ₱ 15,717.91
VAT ₱ 8,173.31
Total Cost ₱ 76,284.27

Christian Ace N. PradesGeneral Manager


Unit
Beams 8
Length 15
width 0.4
Height 0.25
Volume 12

Reinforced Concrete Volume = 12.00

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

72 Bags Cement 240.00 ₱ 17,280.00


12 Cu.m Sand 1,100.00 ₱ 13,200.00
6 Cu.m Gravel 1,600.00 ₱ 9,600.00
Pcs 16mm dia. X 6m 380.00 ₱ -
32 Pcs 12mm dia. X 6m 210.00 ₱ 6,720.00
96 Pcs 10mm dia. X 6m 160.00 ₱ 15,360.00
10 Kg #16 Tie wires 75.00 ₱ 750.00
Materials ₱ 62,910.00
Labor ₱ 25,164.00
Direct Cost ₱ 88,074.00
Mark up ₱ 26,422.20
VAT ₱ 13,739.54
Total Cost ₱ 128,235.74

Masonry
Length 20
Width 5
Area 100

Masonry Area = 100

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

Pcs 6" CHB 20.00 ₱ -


1,300 Pcs 4" CHB 15.00 ₱ 19,500.00
67 Pcs 10mm dia. X 6m 160.00 ₱ 10,666.67
50 Bags Portland Cement 240.00 ₱ 12,000.00
1 Cu.m Sand 1,100.00 ₱ 1,100.00
1 Cu.m Gravel 1,600.00 ₱ 800.00
3 Kgs #16 Tie wires 75.00 ₱ 225.00
Materials ₱ 44,291.67
Labor ₱ 17,716.67
Direct Cost ₱ 62,008.33
Mark up ₱ 18,602.50
VAT ₱ 9,673.30
Total Cost ₱ 90,284.13

Christian Ace N. PradesGeneral Manager


Length 2
Width 5
Area 10
Carpentry And Joinery Area = 10

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

3 Pcs Ordinary Plywood 1/4"x 4" x 8" 450.00 ₱ 1,562.50


0 Pcs Marine Plywood 1/4"x 4" x 8" 550.00 ₱ -
30 bd.ft coco lumber 105.00 ₱ 3,150.00
6 kg Nails 100.00 ₱ 600.00
3 kg Gi. Wire 100.00 ₱ 300.00
Materials ₱ 5,612.50
Labor ₱ 2,245.00
Direct Cost ₱ 7,857.50
Mark up ₱ 2,357.25
VAT ₱ 1,225.77
Total Cost ₱ 11,440.52

Length 2
Width 5
Area 10

Plastering Area = 10

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

2 Bags Portland Cement PHP 240.00 480.00


1 Cu.m Sand PHP 1,100.00 1100.00

Materials ₱ 1,580.00
Labor ₱ 632.00
Direct Cost ₱ 2,212.00
Mark up ₱ 663.60
VAT ₱ 345.07
Total Cost ₱ 3,220.67

Christian Ace N. PradesGeneral Manager


Length 2
Width 5
Area 10

Floor Finishing Area = 40

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

16 Bags Portland Cement PHP 240.00 3840.00


3 Cu.m Sand PHP 1,100.00 2816.00
Materials ₱ 6,656.00
Labor ₱ 2,662.40
Direct Cost ₱ 9,318.40
Mark up ₱ 2,795.52
VAT ₱ 1,453.67
Total Cost ₱ 13,567.59

Length 2
Width 5
Area 10

Tile Work Area = 80

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

222 pcs Glazed Tiles 60x60 PHP 210.00 46666.67


16 Bags cement PHP 240.00 3840.00
16 Bags adhesive PHP 550.00 8800.00
16 Kg Grout PHP 80.00 1280.00
Materials ₱ 60,586.67
Labor ₱ 24,234.67
Direct Cost ₱ 84,821.33
Mark up ₱ 25,446.40
VAT ₱ 13,232.13
Total Cost ₱ 123,499.86

Christian Ace N. PradesGeneral Manager


PLUMBING FIXTURES PCS 10

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

3 pcs Water Closet 7,000.00 21000.00


2 pcs Urinal 2,300.00 4600.00
5 pcs LAVATORY 650.00 3250.00
37 pcs Floor Drain 65.00 2405.00
Materials ₱ 31,255.00
Labor ₱ 12,502.00
Direct Cost ₱ 43,757.00
Mark up ₱ 13,127.10
VAT ₱ 6,826.09
Total Cost ₱ 63,710.19

Painting Works area 80

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

24 Lites GLOSS LATEX 720.00 17281.73


16 liters PAINT FLAT LATEX 560.00 8960.00
13 Liters Masonry putty 165.00 2200.00
40 Liters Skimcoat 115.00 4600.00
1 PC PAINT ROLLER 520.00 520.00
1 PC PAINT BRUSH 4" 65.00 65.00
Materials ₱ 33,626.73
Labor ₱ 13,450.69
Direct Cost ₱ 47,077.42
Mark up ₱ 14,123.23
VAT ₱ 7,344.08
Total Cost ₱ 68,544.72

Christian Ace N. PradesGeneral Manager


Length 6
width 7
area 42

Corrugated Metal Roofing Area 42

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

21 Pcs Corrugated GI Sheet PHP 690.00 14490.00


2 Pcs GA # 26 PL. G.I. Gutter PHP 550.00 1100.00
4 kilo roofing nails PHP 90.00 360.00
2 tin Roof paint PHP 2,400.00 4800.00
Materials ₱ 20,750.00
Labor ₱ 10,375.00
Direct Cost ₱ 31,125.00
Mark up ₱ 9,337.50
VAT ₱ 4,855.50
Total Cost ₱ 45,318.00

truss and accessories Length

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

6 pcs 2" x 2" 1/4" Angle Bar TC and BC 850.00 5,100.00


6 pcs 2" x 2" 3/16" Angle Bar WM 530.00 3,180.00
2 pcs 10mm dia x 6m Sagrods 680.00 1,360.00
15 pcs 2" x 4" x 2mm C-Purlins 450.00 6,750.00
2 pcs 2" x 4" x 2mm C-Purlins(Fascia board) 450.00 900.00
2 pcs cross bracing 355.00 710.00
Materials ₱ 18,000.00
Labor ₱ 9,000.00
Direct Cost ₱ 27,000.00
Mark up ₱ 8,100.00
VAT ₱ 4,212.00
Total Cost ₱ 39,312.00

Christian Ace N. PradesGeneral Manager


Window Frames Pcs 5

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

4 pcs 1 x 2 Steel Casement Window Frame PHP 3,100.00 12400.00


1 pcs Steel Awning Window Frame PHP 4,150.00 4150.00
2 pcs Aluminum windows PHP 4,151.00 8302.00
Materials ₱ 16,550.00
Labor ₱ 8,275.00
Direct Cost ₱ 24,825.00
Mark up ₱ 7,447.50
VAT ₱ 3,872.70
Total Cost ₱ 36,145.20

Doors andDoor Frames pcs 5

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

5 pcs Door Knobs 550.00 2750


5 pcs Door Jamb 1,280.00 6400.00
5 pcs hinge 4x4 250.00 1250.00
2 pcs SWING DOOR 6,100.00 12200.00
2 pcs hollow core flush type 3,450.00 6900.00
1 pcs hollow core flush type cr 2,900.00 2900.00
Materials ₱ 26,750.00
Labor ₱ 13,375.00
Direct Cost ₱ 40,125.00
Mark up ₱ 12,037.50
VAT ₱ 6,259.50
Total Cost ₱ 58,422.00

Christian Ace N. PradesGeneral Manager


ELCTRICAL WORKS Length 100
CONDUITS BOXES AND FITTINGS
QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

4 PCS One Gang Switch 195.00 780.00


2 PCS Two Gang Switch 172.00 344.00
33 PCS Pvc Pipe 199.00 6633.33
8 PCS 1 x 40 watts F. Lamp with Accessories 450.00 3600.00
4 PCS 2 x 40 watts F. Lamp with Accessories 570.00 2280.00
1 PCS Panel Board 1,770.00 1770.00
6 PCS Circuit Breaker 500.00 3000.00
4 PCS Receptacle 60.00 240.00
35 PCS Utility Box 32.00 1120.00
1 PCS Meter electric 1,700.00 1700.00
300 meter Wire 3.5mm 29.00 8700.00
50 meter Wire 5.5mm 56.00 2800.00
Materials ₱ 21,467.33
Labor ₱ 10,733.67
Direct Cost ₱ 32,201.00
Mark-up ₱ 6,440.20
Vat ₱ 4,636.94
Total Cost ₱ 43,278.14

Christian Ace N. PradesGeneral Manager


SEPTIC TANK area 20.00

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

4 bags Cement 205.00 820.00


4 cu.m sand 650.00 2600.00
2 cu.m gravel 1,100.00 2200.00
260 PCS CHB 4" 10.50 2730.00
107 PCS REBARS (grade 60) 10mm Ф x 6m 102.00 10914.00
5 KG TIE WIRES 75.00 375.00
Materials ₱ 19,639.00
Labor ₱ 9,819.50
Direct Cost ₱ 29,458.50
Mark-up ₱ 5,891.70
Vat ₱ 4,242.02
Total Cost ₱ 39,592.22

Christian Ace N. PradesGeneral Manager


Pipes and fittings area 50.00

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

5 pcs PVC 75mmØ 535.00 2675.00


5 pcs PVC 100mmØ 735.00 3675.00
5 pcs PVC 50mmØ 335.00 1675.00
4 pcs GATE VALVE 319.75 1279.00
4 PCS CLEAN OUT PLUG 50.00 200.00
2 PCS P-TRAP 32mmØ 480.00 960.00
6 PCS GI PIPE SCHEDULE 40 1/2 x 20 ft 400.00 2400.00
4 PCS 1/4 BEND 75mmØ 50.00 200.00
2 PCS DOUBLE TEE 75mmØ (orange) 50.00 100.00
1 PCS TEE 75mmØ (orange) 119.75 119.75
3 PCS Elbow 20mm 20.00 60.00
16 PCS Elbow 75mm 60.00 960.00
4 PCS 100mm x 100mm wye (orange) 84.00 336.00
4 PCS 100mm x 75mm wye (orange) 119.75 479.00
4 PCS TEE 12mm 9.25 37.00
4 PCS TEE 20 mm 18.75 75.00
Materials ₱ 9,554.00
Labor ₱ 3,343.90
Direct Cost ₱ 12,897.90
Mark-up ₱ 3,869.37
Vat ₱ 2,012.07
Total Cost ₱ 18,779.34

railings length 229


QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

12.00 pcs GI Pipe 50mm x 6m SCH-40 PHP 380.00 4560.00


10.00 pcs SQR Bar 19mm PHP 375.00 3750.00
6.00 pcs GI Pipe 32mm x 6m SCH-40 PHP 300.00 1800.00
7.00 pcs 2 x 25 x 25 angular bar nosing PHP 400.00 2800.00
Materials ₱ 13,139.00
Labor ₱ 4,598.65
Direct Cost ₱ 17,737.65
Mark-up ₱ 5,321.30
Vat ₱ 2,767.07
Total Cost ₱ 25,826.02

Christian Ace N. PradesGeneral Manager


To Adjust based on you
MARK UP 30%
VAT 12%
Labor 40%

All Red to be fill up

Christian Ace N. PradesGeneral Manager


Note
Rebars depends on Plans/design

Note
Rebars depends on Plans/design

Christian Ace N. PradesGeneral Manager


Note
Rebars depends on Plans/design

Christian Ace N. PradesGeneral Manager