Contract ID:
Project Name: COMPLETION OF THE CONSTRUCTION OF 2-STOREY ACADEMIC BUILDING
Location: Davao del Norte
DETAILED ESTIMATE
VARIATION ORDER
Item No.:
Description: Waterproofing of Left Side and Right Side Exterior Walls
Qty.: 148.44 Output : 1.00
Unit: sqm No. of Days : 18.60
LABOR
NO. OF PERSON NO. OF DAYS RATE PER DAY AMOUNT
1 Construction Foreman 18.6 day P 700.00 P 13,020.00
2 Skilled Laborer 18.6 day P 550.00 P 10,230.00
4 Unskilled Laborer 18.6 day P 450.00 P 8,370.00
Total P 23,250.00
EQUIPMENT
NO. EQUIPMENT NAME NO. OF DAYS RATE PER DAY AMOUNT
Total P 1,162.50
MATERIALS
MATERIAL SPEC. QTY. UNIT UNIT COST AMOUNT
Total P 35,235.80
Item No.:
Description: Waterproofing of Front Side and Rear Side Exterior Walls
Qty.: 424.25 Output : 3.00
Unit: sqm No. of Days : 17.70
LABOR
NO. OF PERSON NO. OF DAYS RATE PER DAY AMOUNT
1 Construction Foreman 17.7 day P 700.00 P 12,390.00
2 Skilled Laborer 17.7 day P 550.00 P 9,735.00
4 Unskilled Laborer 17.7 day P 450.00 P 7,965.00
Total P 22,125.00
DAVAO DEL NORTE STATE COLLEGE
Contract ID:
Project Name: COMPLETION OF THE CONSTRUCTION OF 2-STOREY ACADEMIC BUILDING
Location: Davao del Norte
DETAILED ESTIMATE
VARIATION ORDER
EQUIPMENT
NO. EQUIPMENT NAME NO. OF DAYS RATE PER DAY AMOUNT
Total P 1,106.25
MATERIALS
MATERIAL SPEC. QTY. UNIT UNIT COST AMOUNT
Total P 34,221.60
PREARED BY: