Designation Person/s No. of Days Daily Rate Amount (Php)
Labor
a. Foreman 1 1 P 787.12 P 787.12
b. Skilled Laborer 1 1 P 569.36 P 569.36
c. Unskilled Laborer 2 1 P 439.84 P 879.68
Total: P 2,236.16
Total: P 3,335.00
No. of
Designation Personel Total days Daily Rate Amount (Php)
Labor
a. Health Personal (Part Time First Aider) 1 20.00 P 569.36 P 11,387.20
Total: P 11,387.20
Materials
a. Safety Helmet man-days 10 P 0.40 P 4.00
b. Safety Shoes man-days 10 P 2.76 P 27.61
c. Safety Vest man-days 10 P 2.30 P 23.03
d. Working Gloves man-days 10 P 7.68 P 76.80
e. Face Mask (Surgical/Cloth) man-days 20 P 10.00 P 200.00
f. Rubber Boots man-days 10 P 1.50 P 15.00
g. Eye Googles man-days - - -
h. Face Shield man-days - - -
i. Rain Coats man-days 4 P 0.48 P 1.92
j. COVID 19 Rapid Antibody Test each - - -
Antiseptics and Disinfectant - - -
k. Sanitizing Solution lit - P 100.00 -
l. Ethyl Alcohol lit - P 195.00 -
m. Disinfectant Spray can - P 1,000.00 -
n. Liquid Hand Soap lit - P 200.00 -
Total: P 348.36
No. of
Name and Capacity Units No. of Days Daily Rate Amount (Php)
Equipment
a. Dump Truck (10 cu. m.),290 Hp 1 0.5 P 11,360.00 P 5,680.00
b. Transit Mixer (5 m3 cap) 1 0.5 P 10,544.00 P 5,272.00
c. Backhoe SE 130Xlc-2 (0.80 m3) 1 0.0 P 15,984.80 P -
d. Motorized Road Grader 1 0.2 P 17,384.00 P 8,692.00
e. Vibratory Roller (10 M.T.)., SD100DC,125Hp 1 0.2 P 14,768.00 P 7,384.00
f. Concrete Vibrator 1 1.0 P 730.00 P 730.00
Total: P 27,758.00
No. of
Designation Person No. of Hours Hourly Rate Amount (Php)
Labor
a. Construction Foreman 1 1 P 98.39 P 98.39
b. Unskilled Laborer 2 1 P 54.98 P 109.96
Total: P 208.35
No. of
Name and Capacity Units No. of Hours Hourly Rate Amount (Php)
Equipment
a. Motorized Road Grader, G710A, 140Hp 1 1 P 2,173.00 P 2,173.00
b. Vibratory Roller (10 M.T.), SD100DC, 125Hp 1 1 P 1,846.00 P 1,846.00
Total: P 4,019.00