ESTIMATED COST OF DIFFERENT TYPES OF BRIDGE STRUCTURE PER LINEAR METER (PESOS)

as of December 2019

Table 6

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
NCR CAR REGION I
I. NEW CONSTRUCTION
CONCRETE BRIDGE STRUCTURE

1.) PSC GIRDER BRIDGE WITH BORED PILE FOUNDATION 530,848.02 957,635.91 530,568.07 969,982.19 541,914.04 996,777.09

2.) PSC GIRDER BRIDGE WITH R. C. PILE FOUNDATION 475,072.91 901,860.80 469,667.30 909,081.42 482,538.25 937,401.30

3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 445,066.23 905,533.24 441,110.83 915,529.70 410,911.18 901,186.50

SINGLE SPAN RCDG BRIDGE WITH R. C. PILE FOUNDATION 475,100.04 751,536.25 464,587.45 749,824.15 434,609.44 733,675.61

STEEL BRIDGE STRUCTURE

1.) STEEL TRUSS WITH BORED PILE FOUNDATION 850,997.10 1,230,349.57 854,065.88 1,243,404.68 850,566.38 1,254,698.57

2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 817,532.03 1,196,884.50 817,525.42 1,206,864.22 814,940.90 1,219,073.10

3.) STEEL GIRDER WITH BORED PILE FOUNDATION 756,034.49 1,186,406.37 759,215.46 1,201,925.29 740,746.28 1,198,903.10

4.) STEEL GIRDER WITH R. C. PILE FOUNDATION 700,257.64 1,130,374.78 698,312.94 1,140,768.04 681,368.74 1,139,270.82

CONCRETE FLYOVER

1.) CONCRETE FLYOVER, PSCG TYPE IV, L =30M/35M PER SPAN 487,815.86 492,816.61 511,648.23

II. REPLACEMENT/RECONSTRUCTION      
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR      
1.) BRIDGE RETROFITTING      

Retrofitting
a. of Superstucture 439,975.44 428,411.33 424,056.41

Retrofitting
  b. of Substructure and Superstucture 608,868.54 598,119.01 587,165.00

2.) REPLACEMENT OF SUPERSTRUCTURE 410,643.09 408,758.20 445,692.34

3.) REDECKING 226,497.39 224,813.32 219,226.61

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION II REGION III REGION IV-A
I. NEW CONSTRUCTION
CONCRETE BRIDGE STRUCTURE

PSC GIRDER BRIDGE WITH BORED PILE FOUNDATION 572,426.28 1,153,428.83 553,592.54 1,035,246.39 540,659.16 1,006,900.28

PSC GIRDER BRIDGE WITH R. C. PILE FOUNDATION 511,692.47 1,092,695.02 492,601.63 974,255.48 484,040.05 950,281.16

RCDG BRIDGE WITH R. C. PILE FOUNDATION 444,099.64 1,066,362.55 438,130.10 956,260.92 454,417.25 956,502.09

SINGLE SPAN RCDG BRIDGE WITH R. C. PILE FOUNDATION 471,391.01 873,054.59 463,791.89 784,814.46 483,220.59 791,864.41

STEEL BRIDGE STRUCTURE

1.) STEEL TRUSS WITH BORED PILE FOUNDATION 980,533.75 1,501,501.44 892,832.23 1,322,253.85 887,281.76 1,302,127.37

2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 944,093.47 1,465,061.15 856,237.69 1,285,659.30 853,310.29 1,268,155.90

3.) STEEL GIRDER WITH BORED PILE FOUNDATION 833,099.80 1,417,425.52 780,112.27 1,265,172.19 782,891.57 1,252,440.72

4.) STEEL GIRDER WITH R. C. PILE FOUNDATION 772,364.24 1,356,435.23 719,119.61 1,203,924.80 726,270.71 1,195,565.12

CONCRETE FLYOVER

1.) CONCRETE FLYOVER, PSCG TYPE IV, L =30M/35M PER SPAN 534,733.62 515,858.45 496,869.99

II. REPLACEMENT/RECONSTRUCTION      
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR      
1.) BRIDGE RETROFITTING      

Retrofitting
a. of Superstucture 429,847.91 431,928.86 429,482.55

Retrofitting
  b. of Substructure and Superstucture 602,020.47 601,828.27 600,103.31

2.) REPLACEMENT OF SUPERSTRUCTURE 457,460.90 438,120.39 412,933.82

3.) REDECKING 225,991.74 224,876.08 225,627.10

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION IV-B REGION V REGION VI
I. NEW CONSTRUCTION
CONCRETE BRIDGE STRUCTURE

1.) PSC GIRDER BRIDGE WITH BORED PILE FOUNDATION 560,693.97 1,005,799.50 557,960.74 1,040,935.55 554,120.81 987,844.73

2.) PSC GIRDER BRIDGE WITH R. C. PILE FOUNDATION 497,290.90 942,396.43 505,878.42 988,853.23 496,878.72 930,602.64

3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 459,501.10 939,398.03 436,578.23 956,451.13 458,249.73 926,896.92

SINGLE SPAN RCDG BRIDGE WITH R. C. PILE FOUNDATION 498,480.21 790,422.41 464,386.65 785,850.39 497,909.63 777,374.84

STEEL BRIDGE STRUCTURE      


1.) STEEL TRUSS WITH BORED PILE FOUNDATION 887,143.56 1,282,458.49 887,102.02 1,316,887.42 868,094.26 1,252,016.31

2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 849,101.72 1,244,416.65 855,852.63 1,285,638.03 833,749.01 1,217,671.06

3.) STEEL GIRDER WITH BORED PILE FOUNDATION 787,697.46 1,236,067.24 770,065.62 1,256,289.06 773,038.82 1,210,137.94

4.) STEEL GIRDER WITH R. C. PILE FOUNDATION 724,292.64 1,172,407.68 717,981.56 1,203,950.26 715,794.99 1,152,639.37

CONCRETE FLYOVER

1.) CONCRETE FLYOVER, PSCG TYPE IV, L =30M/35M PER SPAN 506,072.07 517,667.08 501,446.00

II. REPLACEMENT/RECONSTRUCTION      
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR  
1.) BRIDGE RETROFITTING  

Retrofitting
a. of Superstucture 428,423.59 426,911.85 431,685.60

Retrofitting
  b. of Substructure and Superstucture 600,026.80 588,487.69 601,862.40

2.) REPLACEMENT OF SUPERSTRUCTURE 422,693.61 454,921.20 422,949.88

3.) REDECKING 225,511.67 223,560.88 225,009.52

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION VII REGION VIII REGION IX
I. NEW CONSTRUCTION
CONCRETE BRIDGE STRUCTURE

1.) PSC GIRDER BRIDGE WITH BORED PILE FOUNDATION 558,584.52 1,026,948.62 562,669.25 1,033,272.81 556,646.17 988,445.69

2.) PSC GIRDER BRIDGE WITH R. C. PILE FOUNDATION 498,137.80 966,501.90 505,408.16 976,011.72 494,695.91 926,495.43

3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 474,077.90 978,903.05 482,608.30 989,679.86 468,028.92 933,730.86

SINGLE SPAN RCDG BRIDGE WITH R. C. PILE FOUNDATION 502,730.88 810,911.92 517,267.25 827,965.54 506,319.78 788,548.04

STEEL BRIDGE STRUCTURE

1.) STEEL TRUSS WITH BORED PILE FOUNDATION 897,700.17 1,313,722.63 912,412.93 1,330,555.76 879,223.91 1,262,641.95

2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 861,432.14 1,277,454.59 878,056.28 1,296,199.11 842,053.76 1,225,471.80

3.) STEEL GIRDER WITH BORED PILE FOUNDATION 800,701.90 1,272,397.14 809,991.62 1,283,866.33 787,362.50 1,222,418.90

4.) STEEL GIRDER WITH R. C. PILE FOUNDATION 740,253.43 1,211,693.93 752,728.79 1,226,348.76 725,410.50 1,160,212.17

CONCRETE FLYOVER  

1.) CONCRETE FLYOVER, PSCG TYPE IV, L =30M/35M PER SPAN 513,174.18 512,230.93 500,374.27
II. REPLACEMENT/RECONSTRUCTION  
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR  
1.) BRIDGE RETROFITTING  

Retrofitting
a. of Superstucture 435,798.47 432,550.99 431,131.15

Retrofitting
  b. of Substructure and Superstucture 612,850.35 610,771.81 602,433.73

2.) REPLACEMENT OF SUPERSTRUCTURE 420,183.38 417,376.98 414,782.16

3.) REDECKING 231,348.21 232,170.22 227,132.79

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION X REGION XI REGION XII
I. NEW CONSTRUCTION
CONCRETE BRIDGE STRUCTURE

1.) PSC GIRDER BRIDGE WITH BORED PILE FOUNDATION 580,350.77 1,155,247.67 613,744.76 1,088,996.70 663,933.79 1,196,664.73

2.) PSC GIRDER BRIDGE WITH R. C. PILE FOUNDATION 519,822.33 1,094,719.23 527,386.61 1,002,638.56 602,249.02 1,134,979.96

3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 499,904.42 1,117,277.01 457,207.35 970,617.92 481,590.68 1,056,074.70

SINGLE SPAN RCDG BRIDGE WITH R. C. PILE FOUNDATION 540,273.55 931,064.02 476,577.00 784,621.67 514,196.06 865,988.87

STEEL BRIDGE STRUCTURE

1.) STEEL TRUSS WITH BORED PILE FOUNDATION 1,011,951.08 1,524,835.04 896,597.19 1,316,873.15 949,195.76 1,420,971.76

2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 975,634.02 1,488,517.98 844,782.31 1,265,058.26 912,184.90 1,383,960.90

3.) STEEL GIRDER WITH BORED PILE FOUNDATION 879,849.84 1,458,051.28 810,627.88 1,289,256.39 835,120.53 1,371,101.46

4.) STEEL GIRDER WITH R. C. PILE FOUNDATION 819,319.66 1,397,266.36 724,267.99 1,202,641.76 773,434.02 1,309,160.21

CONCRETE FLYOVER      

1.) CONCRETE FLYOVER, PSCG TYPE IV, L =30M/35M PER SPAN 521,563.22 584,843.37 614,178.98

II. REPLACEMENT/RECONSTRUCTION      
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR      
1.) BRIDGE RETROFITTING      

Retrofitting
a. of Superstucture 434,791.52 433,209.14 431,939.21

Retrofitting
  b. of Substructure and Superstucture 612,185.32 623,846.76 610,980.30

2.) REPLACEMENT OF SUPERSTRUCTURE 422,111.90 477,360.99 536,084.83


3.) REDECKING 232,494.15 233,251.11 229,581.71

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP
TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL
REGION XIII
I. NEW CONSTRUCTION
CONCRETE BRIDGE STRUCTURE

1.) PSC GIRDER BRIDGE WITH BORED PILE FOUNDATION 614,959.10 1,192,023.20

2.) PSC GIRDER BRIDGE WITH R. C. PILE FOUNDATION 549,369.04 1,126,433.14

3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 487,168.58 1,106,639.45

SINGLE SPAN RCDG BRIDGE WITH R. C. PILE FOUNDATION 524,413.55 917,852.91

STEEL BRIDGE STRUCTURE  

1.) STEEL TRUSS WITH BORED PILE FOUNDATION 1,007,507.51 1,522,596.45

2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 968,153.47 1,483,242.41

3.) STEEL GIRDER WITH BORED PILE FOUNDATION 873,727.26 1,454,055.62

4.) STEEL GIRDER WITH R. C. PILE FOUNDATION 808,135.45 1,388,209.07

CONCRETE FLYOVER  

1.) CONCRETE FLYOVER, PSCG TYPE IV, L =30M/35M PER SPAN 559,224.87

II. REPLACEMENT/RECONSTRUCTION  

1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge

2.) STEEL BRIDGE add 15% to the New Construction of Bridge

III. BRIDGE REPAIR


1.) BRIDGE RETROFITTING

Retrofitting
a. of Superstucture 435,108.84  

Retrofitting
  b. of Substructure and Superstucture 615,385.29  

2.) REPLACEMENT OF SUPERSTRUCTURE 467,961.10  

3.) REDECKING 230,980.86  

The cost estimate for dry/low water level condition includes Embankment Craneway and Embankment T-Platform, while the cost estimate for high/deep water level condition
includes Structural Steel Craneway, Structural Steel T-Platform and Cofferdamming of the footing foundation.

Cost of Replacement/Reconstruction work may be increased by 15% of the new construction cost due to removal of existing bridge structure and provision of detour and traffic
management.
The price of construction materials are based on the regional average prices plus 15% mark-up for the hauling cost (3rd Quarter of CY 2019), equipment rates are based from the
latest ACEL Rates (25th Edition) and labor rates are based on the approved labor rates (January 2020).

The estimated unit cost was derived from the assumed typical design of Bridge Structure and may vary depending on the actual design. 

The retrofitting works is assumed to be designed using glass fiber reinforcement on girders.

Notes:
 

1.)  Bridge data provided are as of  27 December 2019.

2.)  The unit of measure for Bridge Data is linear meters.

3.) Further Assessment  refers to Bridges that are either under the circumstances of on-going construction, under major maintenance work or washed-out.

4.)  National Bridges are classified into:

              Permanent Bridges -  are bridges that are composed of concrete and steel.

              Temporary Bridges -  are bridges consisting of timber and bailey.