ESTIMATED COST OF DIFFERENT TYPES OF BRIDGE STRUCTURE PER LINEAR METER (PhP)
as of January 2022
Table 6

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
ITEM TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
NCR CAR REGION I
I. NEW CONSTRUCTION
A. CONCRETE BRIDGE STRUCTURE
PSC GIRDER BRIDGE WITH BORED PILE
1.) 568,360.02 1,061,071.40 604,094.65 1,066,159.42 583,491.17 1,137,239.39
FOUNDATION
PSC GIRDER BRIDGE WITH R. C. PILE
2.) 498,070.29 990,781.67 527,218.02 989,282.79 512,285.04 1,066,033.25
FOUNDATION
3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 475,361.49 1,007,437.13 523,871.33 1,023,769.10 448,019.75 1,043,519.55
SINGLE SPAN RCDG BRIDGE WITH R. C. PILE
4.) 496,538.98 811,706.99 531,597.57 823,446.32 468,598.86 836,348.01
FOUNDATION
without with structural without with structural without with structural
craneway steel craneway craneway steel craneway craneway steel craneway
B. STEEL BRIDGE STRUCTURE
STEEL TRUSS WITH BORED PILE
1.) 910,137.30 1,346,419.98 899,333.87 1,306,908.88 949,146.00 1,442,188.20
FOUNDATION
2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 867,963.47 1,304,246.14 853,207.90 1,260,782.91 906,422.32 1,399,464.52
STEEL GIRDER WITH BORED PILE
3.) 815,924.62 1,312,277.16 839,672.66 1,305,094.68 824,405.46 1,381,540.63
FOUNDATION
STEEL GIRDER WITH R. C. PILE
4.) 745,633.14 1,241,730.95 762,794.29 1,227,961.57 753,197.58 1,310,078.01
FOUNDATION
C. CONCRETE FLYOVER
CONCRETE FLYOVER, PSCG TYPE IV, L
1.) 525,377.25 570,704.81 546,335.33
=30M/35M PER SPAN
II. REPLACEMENT/RECONSTRUCTION
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR
1.) BRIDGE RETROFITTING
a. Retrofitting of Superstucture 456,859.72 453,637.47 442,256.70
Retrofitting of Substructure and
b. 645,445.42 656,533.42 623,396.46
Superstucture
2.) REPLACEMENT OF SUPERSTRUCTURE 431,211.75 443,851.05 466,962.08
3.) REDECKING 244,877.30 257,833.73 237,977.85

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
ITEM TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION II REGION III REGION IV-A
I. NEW CONSTRUCTION
A. CONCRETE BRIDGE STRUCTURE
PSC GIRDER BRIDGE WITH BORED PILE
1.) 633,234.40 1,242,345.07 590,698.22 1,140,240.53 542,707.92 1,041,488.27
FOUNDATION
PSC GIRDER BRIDGE WITH R. C. PILE
2.) 557,615.69 1,166,726.36 515,546.84 1,065,089.15 479,175.18 977,955.53
FOUNDATION
3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 502,247.24 1,155,788.64 463,521.68 1,054,324.78 448,330.22 986,384.94
SINGLE SPAN RCDG BRIDGE WITH R. C. PILE
4.) 522,687.99 934,463.50 489,075.87 854,872.94 465,388.18 788,747.48
FOUNDATION
without with structural without with structural without with structural
craneway steel craneway craneway steel craneway craneway steel craneway
B. STEEL BRIDGE STRUCTURE
STEEL TRUSS WITH BORED PILE
1.) 1,027,110.62 1,571,228.63 963,632.09 1,453,375.76 892,650.45 1,334,687.60
FOUNDATION
2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 981,739.39 1,525,857.40 918,541.27 1,408,284.93 854,530.80 1,296,567.96
STEEL GIRDER WITH BORED PILE
3.) 900,066.10 1,512,563.72 843,029.33 1,396,026.43 787,648.55 1,289,815.46
FOUNDATION
STEEL GIRDER WITH R. C. PILE
4.) 824,445.65 1,436,688.53 767,876.20 1,320,618.57 724,114.07 1,226,026.24
FOUNDATION
C. CONCRETE FLYOVER
CONCRETE FLYOVER, PSCG TYPE IV, L
1.) 588,369.56 545,890.93 509,582.56
=30M/35M PER SPAN
II. REPLACEMENT/RECONSTRUCTION
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR
1.) BRIDGE RETROFITTING
a. Retrofitting of Superstucture 451,522.73 445,440.64 442,187.04
Retrofitting of Substructure and
b. 649,163.80 631,957.65 620,137.81
Superstucture
2.) REPLACEMENT OF SUPERSTRUCTURE 486,332.02 455,477.48 426,417.26
3.) REDECKING 250,625.55 238,633.25 237,323.96

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
ITEM TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION IV-B REGION V REGION VI
I. NEW CONSTRUCTION
A. CONCRETE BRIDGE STRUCTURE
PSC GIRDER BRIDGE WITH BORED PILE
1.) 671,343.35 1,186,875.37 635,187.78 1,180,468.26 583,051.37 1,070,173.82
FOUNDATION
PSC GIRDER BRIDGE WITH R. C. PILE
2.) 577,444.93 1,092,976.95 564,607.86 1,109,888.33 512,956.87 1,000,079.32
FOUNDATION
3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 563,278.03 1,121,474.50 515,101.29 1,102,838.15 476,852.18 1,002,992.59
SINGLE SPAN RCDG BRIDGE WITH R. C. PILE
4.) 606,351.38 932,637.62 537,482.14 893,152.32 508,063.65 819,451.48
FOUNDATION
without with structural without with structural without with structural
craneway steel craneway craneway steel craneway craneway steel craneway
B. STEEL BRIDGE STRUCTURE
STEEL TRUSS WITH BORED PILE
1.) 1,003,922.49 1,457,168.58 974,662.64 1,458,162.87 913,335.80 1,344,257.76
FOUNDATION
2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 947,583.43 1,400,829.52 932,314.68 1,415,814.91 871,279.11 1,302,201.07
STEEL GIRDER WITH BORED PILE
3.) 928,487.55 1,447,340.23 873,358.92 1,422,056.05 817,607.29 1,308,189.88
FOUNDATION
STEEL GIRDER WITH R. C. PILE
4.) 834,587.38 1,353,185.32 802,777.24 1,351,219.64 747,511.05 1,237,838.90
FOUNDATION
C. CONCRETE FLYOVER
CONCRETE FLYOVER, PSCG TYPE IV, L
1.) 598,928.31 585,174.38 530,935.96
=30M/35M PER SPAN
II. REPLACEMENT/RECONSTRUCTION
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR
1.) BRIDGE RETROFITTING
a. Retrofitting of Superstucture 451,986.72 456,450.50 447,849.70
Retrofitting of Substructure and
b. 667,426.87 654,328.40 633,399.62
Superstucture
2.) REPLACEMENT OF SUPERSTRUCTURE 458,020.31 484,913.87 443,017.98
3.) REDECKING 255,804.83 253,082.57 241,581.72

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
ITEM TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION VII REGION VIII REGION IX
I. NEW CONSTRUCTION
A. CONCRETE BRIDGE STRUCTURE
PSC GIRDER BRIDGE WITH BORED PILE
1.) 628,837.28 1,131,536.61 608,721.18 1,191,606.92 615,981.32 1,141,298.32
FOUNDATION
PSC GIRDER BRIDGE WITH R. C. PILE
2.) 551,495.19 1,054,194.53 563,143.74 1,146,029.48 530,787.59 1,056,104.59
FOUNDATION
3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 544,525.99 1,088,647.78 551,822.35 1,179,877.15 520,263.67 1,089,348.08
SINGLE SPAN RCDG BRIDGE WITH R. C. PILE
4.) 569,469.82 887,134.45 584,210.78 967,647.00 552,228.38 882,908.70
FOUNDATION
without with structural without with structural without with structural
craneway steel craneway craneway steel craneway craneway steel craneway
B. STEEL BRIDGE STRUCTURE
STEEL TRUSS WITH BORED PILE
1.) 954,873.08 1,397,380.41 1,011,869.51 1,528,445.86 968,948.04 1,430,200.74
FOUNDATION
2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 908,467.83 1,350,975.16 984,523.04 1,501,099.40 917,831.81 1,379,084.50
STEEL GIRDER WITH BORED PILE
3.) 881,201.70 1,387,280.99 891,102.03 1,477,299.49 880,979.23 1,409,609.31
FOUNDATION
STEEL GIRDER WITH R. C. PILE
4.) 803,857.86 1,309,682.42 845,522.84 1,431,465.56 795,783.75 1,324,159.10
FOUNDATION
C. CONCRETE FLYOVER
CONCRETE FLYOVER, PSCG TYPE IV, L
1.) 573,350.75 536,951.18 563,975.04
=30M/35M PER SPAN
II. REPLACEMENT/RECONSTRUCTION
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR
1.) BRIDGE RETROFITTING
a. Retrofitting of Superstucture 458,115.70 459,523.70 452,020.80
Retrofitting of Substructure and
b. 664,108.25 652,643.35 657,575.34
Superstucture
2.) REPLACEMENT OF SUPERSTRUCTURE 449,801.16 436,216.37 438,076.28
3.) REDECKING 258,381.57 248,893.56 251,872.47

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP DRY OR LOW HIGH OR DEEP
ITEM TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL WATER LEVEL
REGION X REGION XI REGION XII
I. NEW CONSTRUCTION
A. CONCRETE BRIDGE STRUCTURE
PSC GIRDER BRIDGE WITH BORED PILE
1.) 634,417.07 1,242,910.90 719,426.56 1,265,557.43 722,478.57 1,341,010.72
FOUNDATION
PSC GIRDER BRIDGE WITH R. C. PILE
2.) 557,538.30 1,166,032.13 628,928.86 1,175,059.73 619,103.68 1,237,635.82
FOUNDATION
3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 549,324.87 1,204,609.47 468,620.09 1,056,821.65 520,940.38 1,186,902.41
SINGLE SPAN RCDG BRIDGE WITH R. C. PILE
4.) 583,318.53 984,906.26 488,168.42 846,783.56 549,515.57 959,599.04
FOUNDATION
without with structural without with structural without with structural
craneway steel craneway craneway steel craneway craneway steel craneway
B. STEEL BRIDGE STRUCTURE
STEEL TRUSS WITH BORED PILE
1.) 1,056,075.71 1,595,781.26 959,094.06 1,444,079.10 1,055,796.58 1,604,450.39
FOUNDATION
2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 1,009,948.45 1,549,653.99 904,795.43 1,389,780.48 993,771.64 1,542,425.46
STEEL GIRDER WITH BORED PILE
3.) 941,349.25 1,553,219.15 853,541.35 1,403,098.49 944,919.03 1,566,789.78
FOUNDATION
STEEL GIRDER WITH R. C. PILE
4.) 864,468.73 1,476,083.90 763,041.91 1,312,344.30 841,542.38 1,463,158.40
FOUNDATION
C. CONCRETE FLYOVER
CONCRETE FLYOVER, PSCG TYPE IV, L
1.) 572,838.91 679,758.94 676,829.22
=30M/35M PER SPAN
II. REPLACEMENT/RECONSTRUCTION
1.) RCD GIRDER BRIDGE add 15% to the New Construction of Bridge
2.) STEEL BRIDGE add 15% to the New Construction of Bridge
III. BRIDGE REPAIR
1.) BRIDGE RETROFITTING
a. Retrofitting of Superstucture 457,518.84 449,039.59 449,235.33
Retrofitting of Substructure and
b. 661,687.54 646,925.06 668,757.84
Superstucture
2.) REPLACEMENT OF SUPERSTRUCTURE 449,541.36 595,893.24 544,944.50
3.) REDECKING 257,287.70 243,358.42 250,988.12

BRIDGE SITE CONDITION


DRY OR LOW HIGH OR DEEP
ITEM TYPE OF BRIDGE STRUCTURE
WATER LEVEL WATER LEVEL
REGION XIII
I. NEW CONSTRUCTION
A. CONCRETE BRIDGE STRUCTURE
PSC GIRDER BRIDGE WITH BORED PILE
1.) 689,289.56 1,278,153.82
FOUNDATION
PSC GIRDER BRIDGE WITH R. C. PILE
2.) 593,609.32 1,182,473.59
FOUNDATION
3.) RCDG BRIDGE WITH R. C. PILE FOUNDATION 544,630.21 1,180,134.49
SINGLE SPAN RCDG BRIDGE WITH R. C. PILE
4.) 577,669.50 959,883.92
FOUNDATION
without with structural
craneway steel craneway
B. STEEL BRIDGE STRUCTURE
STEEL TRUSS WITH BORED PILE
1.) 1,044,747.87 1,564,949.21
FOUNDATION
2.) STEEL TRUSS WITH R. C. PILE FOUNDATION 987,339.73 1,507,541.07
STEEL GIRDER WITH BORED PILE
3.) 944,458.03 1,536,634.01
FOUNDATION
STEEL GIRDER WITH R. C. PILE
4.) 848,776.05 1,440,697.30
FOUNDATION
C. CONCRETE FLYOVER
CONCRETE FLYOVER, PSCG TYPE IV, L
1.) 622,788.77
=30M/35M PER SPAN
II. REPLACEMENT/RECONSTRUCTION
add 15% to the New Construction
1.) RCD GIRDER BRIDGE
of Bridge
add 15% to the New Construction
2.) STEEL BRIDGE
of Bridge
III. BRIDGE REPAIR
1.) BRIDGE RETROFITTING
a. Retrofitting of Superstucture 457,357.25
Retrofitting of Substructure and
b. 670,781.54
Superstucture
2.) REPLACEMENT OF SUPERSTRUCTURE 497,055.35
3.) REDECKING 256,861.36

Note:
1.) The cost estimate for dry/low water level condition includes Embankment Craneway and Embankment T-Platform, while the cost estimate for
high/deep water level condition includes Structural Steel Craneway, Structural Steel T-Platform and Cofferdamming of the footing foundation.

2.) Cost of Replacement/Reconstruction work may be increased by 15% of the new construction cost due to removal of existing bridge structure
and provision of detour and traffic management.

3.) The price of construction materials are based on the regional average prices plus 15% mark-up for the hauling cost (4th Quarter of CY
2022), equipment rates are based from the latest ACEL Rates (26th Edition) & Department Order No. 63, Series of 2022, authorizing the use
of operated dry rental rates plus updated fuel price & other petroleum products and labor rates are based on the approved labor rates
(December 2022).

4.) The estimated unit cost was derived from the assumed typical design of Bridge Structure and may vary depending on the actual design.
5.) The retrofitting works is assumed to be designed using glass fiber reinforcement on girders.

Notes:

1.) Bridge data provided are as of 17 November 2022.

2.) The unit of measure for Bridge Data is linear meters.

3.) Further Assessment refers to Bridges that are either under the circumstances of on-going construction, under major maintenance work or washed-out.

4.) National Bridges are classified into:

Permanent Bridges - are bridges that are composed of concrete and steel.

Temporary Bridges - are bridges consisting of timber and bailey.

For questions regarding this website contact feedback@dpwh.gov.ph

Last updated: 04/12/23.

Disclaimer

You might also like