Professional Documents
Culture Documents
Superpassage
EW Highway
Desilting Basin
Agaiya Kohalpur 41
Undersluice kM West
West Rapti River
Weir
Intake Site
Headworks Model of RJKIP,Kailali Before Construction (Mar 2011)
Reduced the cost about NRs. 6,00,00,000 (FY066/67) & 12,000 m3 RCC works
(about 200 manyear of SDEr)
Forebay Base Slab Optimization from 4m to 2m Thickness by providing pressure release system. Previously, it was designed as 4m
thickness PCC by gravity type for uplift force. In later, it was designed with raft concept and reduced thickness of floor PCC up to
2m RCC. Thus the concrete volume is reduced by about 12,000 cum with saving NRs.6,00,00,000 (FY 066/67).
Pressure released
with desilted water
Before providing valves
Chisapani, Karnali
Plan
Cantilever Counterfort
SN Particular Double Wall
Retaining Wall Retaining Wall
1 Concrete Quantity 33,789 m3 29,941m3 30,225 m3
2 Rebar Quantity 4,878 MT 3,885 MT 2,878 MT
3 Cost (RCC only) Rs. 1,043,418,155 Rs. 876,413,039 Rs. 769,925,647
4 Check of Stability (H/B=2.5) No need No need No need
5 RCC Design Normal Complex Simple
6 Risk to Failure More Normal Less
7 Construction Normal Difficult Simple
8 Construction Time Reqd. Normal More Less
4. Optimization of Foundation Design of Building
Comparison of Raft & Isolated Footing of Building
793.36
900
800
Raft Isolated Difference
622.79
700
600
398.37
394.99
500
312.72
310.07
400
300
171.64
86.19
200
85.46
100