2.Loan/Grant Number : NA
Bids for Construction of ring road at ward no. 2, IFB No. LAL/W/NCB/079/080-06 were invited through a
public notice on 28-02-2023 16:00 hours with submission date of 30-03-2023 12:00 hours under NCB
Competitive Bidding with Single Stage Two Envelope Procedures. The date and time for the submission of
bids were not required to be extended and the receiving of bids was closed at 30-03-2023 12:00 hours as
scheduled in the Invitation for Bids.
1.2 Submission of Bids
The following sole and joint venture associations of the contractors submitted their bids within the bid
submission deadline as stated in 1.1 above
SN Bidder Name
2 Amrit Construction
3 AANSHU-KIRAN J/V
7 Narshing/Balichandra/Chandgroup J.V.
Technical Bids were opened as specified in the bidding documents at 30-03-2023 14:00 hours by the Bid
Opening Committee in the presence of representatives of bidders who choose to attend the bid opening. The
bidders' names, withdrawal/modification/substitutions, alternative proposals, the presence or absence bid
security and Price Bid were announced and recorded. Letter of Technical Bids were initialed by representatives
of the Employer attending the opening. The Record of Technical Bid Opening was prepared soon after the bids
were announced and a copy of the Record of Bid Opening is forwarded to the ADB. A copy of the Technical
Bid Opening is attached as Appendix -A.
1.4 Bid Evaluation Committee
The detail criteria for the bid evaluation are listed in Appendix B .
The following technical bids are considered for evaluation of the technical bids.
SN Bidder Name
2 Amrit Construction
3 AANSHU-KIRAN J/V
7 Narshing/Balichandra/Chandgroup J.V.
As per approved criterions following bidders have complied with all the requirements of eligibility test
1 Amrit Construction
2 Narshing/Balichandra/Chandgroup J.V.
4 AANSHU-KIRAN J/V
As per approved criterions following bidders have complied with all the requirements of completeness test
SN Bidder Name Remarks (if any)
1 Amrit Construction
2 Narshing/Balichandra/Chandgroup J.V.
5 AANSHU-KIRAN J/V
As per approved criterions following bidders have complied with all the requirements of technical test
1 Amrit Construction
2 Narshing/Balichandra/Chandgroup J.V.
4 AANSHU-KIRAN J/V
As per approved criterions following bidders have complied with all the requirements of qualification test
1 Amrit Construction
3 AANSHU-KIRAN J/V
1 Nationality Complied
1 Nationality Complied
1 Nationality Complied
1 Nationality Complied
1 Nationality Complied
1 Nationality Complied
1 Nationality Complied
1 Nationality Complied
1 Nationality Complied
NRs. 50 million**
10 Financial Resources
3 Narshing/Balichandra/Chandgroup J.V.
3. Technical Evaluation Committee's final Recommendation
Based on above evaluation, the technical evaluation committee recommends the followings
ok
Appendix A
Bid Opening Report
Appendix B
Detail Technical Evaluation Criteria
Test of Eligibility:
SN Sub-Criteria Description
Document required: Letter of Technical Bid Forms ELI –1; ELI –2 with
attachments.
2 Conflict of Interest No conflicts of interest in accordance with ITB Sub- Clause 4.3.
6 Bidder’s Running Contracts Bidder's Running Contracts not more than five (5) as described in ITB Sub-
Clause 4.9.
Completeness Test:
SN Sub-Criteria Description
Technical Test:
SN Sub-Criteria Description
1 Adequacy of Technical Proposal Evaluation of the Bidder's Technical Proposal will include an assessment of
the Bidder's technical capacity, to mobilize key equipment and personnel for
the contract consistent with its proposal regarding work methods, scheduling,
and material sourcing in sufficient detail and fully in accordance with the
requirements stipulated in Section VI (Works Requirements).
Non-compliance with equipment and personnel requirements described in
Section VI (Works Requirements) shall not be grounds for bid rejection and
such non-compliance will be subject to clarification and rectification prior to
contract award.
2 Adequacy of Technical Proposal Evaluation of the Bidder's Technical Proposal will include an assessment of
the Bidder's technical capacity, to mobilize key equipment and personnel for
the contract consistent with its proposal regarding work methods, scheduling,
and material sourcing in sufficient detail and fully in accordance with the
requirements stipulated in Section VI (Works Requirements).
Non-compliance with equipment and personnel requirements described in
Section VI (Works Requirements) shall not be grounds for bid rejection and
such non-compliance will be subject to clarification and rectification prior to
contract award.
3 Adequacy of Technical Proposal Evaluation of the Bidder's Technical Proposal will include an assessment of
the Bidder's technical capacity, to mobilize key equipment and personnel for
the contract consistent with its proposal regarding work methods, scheduling,
and material sourcing in sufficient detail and fully in accordance with the
requirements stipulated in Section VI (Works Requirements).
Non-compliance with equipment and personnel requirements described in
Section VI (Works Requirements) shall not be grounds for bid rejection and
such non-compliance will be subject to clarification and rectification prior to
contract award.
4 Adequacy of Technical Proposal Evaluation of the Bidder's Technical Proposal will include an assessment of
the Bidder's technical capacity, to mobilize key equipment and personnel for
the contract consistent with its proposal regarding work methods, scheduling,
and material sourcing in sufficient detail and fully in accordance with the
requirements stipulated in Section VI (Works Requirements).
Non-compliance with equipment and personnel requirements described in
Section VI (Works Requirements) shall not be grounds for bid rejection and
such non-compliance will be subject to clarification and rectification prior to
contract award.
5 Alternative Technical Solutions Alternative technical solutions, if permitted under ITB 13.4, will be evaluated
as follows:
[insert project specific requirements]
6 Alternative Technical Solutions Alternative technical solutions, if permitted under ITB 13.4, will be evaluated
as follows:
[insert project specific requirements]
7 Alternative Technical Solutions Alternative technical solutions, if permitted under ITB 13.4, will be evaluated
as follows:
[insert project specific requirements]
8 Alternative Technical Solutions Alternative technical solutions, if permitted under ITB 13.4, will be evaluated
as follows:
[insert project specific requirements]
9 Multiple Contracts Multiple Contracts, if permitted under ITB 35.4, will be evaluated as follows:
Award Criteria for Multiple Contracts [ITB 35.4]:
Bidders have the option to Bid for any one or more Contracts. Bids will be
evaluated taking into account discounts offered, if any, for combined
contracts. The contract(s) will be awarded to the Bidder or Bidders offering
the lowest evaluated cost to the Employer for combined contracts, subject to
the selected Bidder(s) meeting the required qualification criteria for
combination of multiple contracts as the case may be.
Qualification Criteria for Multiple Contracts:
The criteria for qualification shall be the sum of the minimum requirements
for respective individual contracts as specified under items 2.3.2, 2.3.3, 2.4.2
SN Sub-Criteria Description
10 Multiple Contracts Multiple Contracts, if permitted under ITB 35.4, will be evaluated as follows:
Award Criteria for Multiple Contracts [ITB 35.4]:
Bidders have the option to Bid for any one or more Contracts. Bids will be
evaluated taking into account discounts offered, if any, for combined
contracts. The contract(s) will be awarded to the Bidder or Bidders offering
the lowest evaluated cost to the Employer for combined contracts, subject to
the selected Bidder(s) meeting the required qualification criteria for
combination of multiple contracts as the case may be.
Qualification Criteria for Multiple Contracts:
The criteria for qualification shall be the sum of the minimum requirements
for respective individual contracts as specified under items 2.3.2, 2.3.3, 2.4.2
b, 2.5 and 2.6.
With respect to the Contracts of Similar Size and Nature under item 2.4.2(a).
of Section III, the evaluation shall be done as below:
N is the minimum number of contracts required as per Specific Construction
Experience (2.4.2(a)).
V is the minimum value of a single contract as per Note (2), (3) or (4) of
2.4.2 Specific Construction Experience
11 Multiple Contracts Multiple Contracts, if permitted under ITB 35.4, will be evaluated as follows:
Award Criteria for Multiple Contracts [ITB 35.4]:
Bidders have the option to Bid for any one or more Contracts. Bids will be
evaluated taking into account discounts offered, if any, for combined
contracts. The contract(s) will be awarded to the Bidder or Bidders offering
the lowest evaluated cost to the Employer for combined contracts, subject to
the selected Bidder(s) meeting the required qualification criteria for
combination of multiple contracts as the case may be.
Qualification Criteria for Multiple Contracts:
The criteria for qualification shall be the sum of the minimum requirements
for respective individual contracts as specified under items 2.3.2, 2.3.3, 2.4.2
b, 2.5 and 2.6.
With respect to the Contracts of Similar Size and Nature under item 2.4.2(a).
of Section III, the evaluation shall be done as below:
N is the minimum number of contracts required as per Specific Construction
SN Sub-Criteria Description
12 Multiple Contracts Multiple Contracts, if permitted under ITB 35.4, will be evaluated as follows:
Award Criteria for Multiple Contracts [ITB 35.4]:
Bidders have the option to Bid for any one or more Contracts. Bids will be
evaluated taking into account discounts offered, if any, for combined
contracts. The contract(s) will be awarded to the Bidder or Bidders offering
the lowest evaluated cost to the Employer for combined contracts, subject to
the selected Bidder(s) meeting the required qualification criteria for
combination of multiple contracts as the case may be.
Qualification Criteria for Multiple Contracts:
The criteria for qualification shall be the sum of the minimum requirements
for respective individual contracts as specified under items 2.3.2, 2.3.3, 2.4.2
b, 2.5 and 2.6.
With respect to the Contracts of Similar Size and Nature under item 2.4.2(a).
of Section III, the evaluation shall be done as below:
N is the minimum number of contracts required as per Specific Construction
Experience (2.4.2(a)).
V is the minimum value of a single contract as per Note (2), (3) or (4) of
2.4.2 Specific Construction Experience
13 In case other than Multiple Bidders have the option to Bid for any one or more Contracts. The contracts
Contracts will be awarded to the Bidder or Bidders offering the lowest evaluated cost to
the Employer, subject to the selected Bidder(s) meeting the required
qualification which shall be the sum of the minimum requirements for
respective individual contracts. Under this case, Contract shall be awarded
based on Least Cost Combination to the Employer.
14 In case other than Multiple Bidders have the option to Bid for any one or more Contracts. The contracts
Contracts will be awarded to the Bidder or Bidders offering the lowest evaluated cost to
the Employer, subject to the selected Bidder(s) meeting the required
qualification which shall be the sum of the minimum requirements for
respective individual contracts. Under this case, Contract shall be awarded
based on Least Cost Combination to the Employer.
15 In case other than Multiple Bidders have the option to Bid for any one or more Contracts. The contracts
Contracts will be awarded to the Bidder or Bidders offering the lowest evaluated cost to
the Employer, subject to the selected Bidder(s) meeting the required
qualification which shall be the sum of the minimum requirements for
respective individual contracts. Under this case, Contract shall be awarded
based on Least Cost Combination to the Employer.
SN Sub-Criteria Description
16 In case other than Multiple Bidders have the option to Bid for any one or more Contracts. The contracts
Contracts will be awarded to the Bidder or Bidders offering the lowest evaluated cost to
the Employer, subject to the selected Bidder(s) meeting the required
qualification which shall be the sum of the minimum requirements for
respective individual contracts. Under this case, Contract shall be awarded
based on Least Cost Combination to the Employer.
17 Personnel Personnel
18 Equipment Equipment
Qualification Test:
SN Sub-Criteria Description
1 Pending Litigation and Arbitration All pending litigation shall be treated as resolved against the Bidder and so
shall in total not represent more than 50 percent of the Bidder's net worth.
Note:
(1) The percentage should normally be within the range of 50% to 100% of
the Bidder's net worth.
For Single Entity : must meet requirement by itself or as partner to past or
existing JV
For joint Venture :Each partner must meet requirement by itself or as partner
to past or existing JV. All partner combined and one partner -> not
applicable.
Documents Submission Requirements : Form LIT - 1
2 General Construction Experience Experience under construction contracts in the role of contractor,
subcontractor, or management contractor for at least the last 5 (Five) years
prior to the applications submission deadline.
5 Contracts of Similar Size and of at least NRs ….. (4)…. that have been successfully or are substantially
Nature completed and that are similar to the proposed works
(iii) For complex works with value For One Partner: Must meet requirement
up to NRs. 50 million** Documents Submission Requirements : Form EXP – 2(a)
6 Contracts of Similar Size and Participation as Prime contractor, management contractor, or subcontractor,
Nature in at least One (1) Contract within the last ten (10)) years, with a value of at
(iv) For complex works with value least NRs …..(3) …. that have been successfully or are substantially
above NRs. 50 million** completed and that are similar to the proposed works. The similarity shall be
based on the physical size, complexity, methods, technology or other
characteristics as described in Section VI, Works Requirements.
Only the net amount shall be calculated after deducting the amount for VAT
and such amount shall be adjusted to present value by applying wholesale
SN Sub-Criteria Description