Cost Estimate Summary

Work Cost (Rs)


1 Site Clearance 14,861,288.55
2 Earthwork 2,034,926,434.48
3 GSB & WMM 2,278,079,408.26
4 Bituminous Course 2,079,320,578.39
5 Toe Wall ,RCC Drain & Retaining Wall 604,137,081.26
6 Road Furniture 146,699,387.52
7 Kerb ,Railing & Metal beam crash barrier 65,507,275.92
8 Toll Plaza 173,006,312.23

9 Minor Bridges 108,824,000.00


10 Box Culverts 205,382,602.00
11 Pipe Culvert 40,002,093.00
12 VUP 322,766,089.00
Total Cost for project road length of 212.107 km
8,073,512,550.61
Total Cost per km 3.806 Cr
Total cost of Road work per km (excluding VUP, Toe wall, RCC drain
and Retaining wall) 3.369 Cr