BOBOWASI ISLAND, BLOCK E


STRUCTURAL SKYLINE
Tuesday, August 25, 2020

Prepared For Structural Skyline

Identified 22 Issues
BLOCK E, UNIT 1, GRD FLR , LIVING ROOM
WINDOW
Assigned To Structural Skyline
Window dressing not in square
Correction Order: Dress to squareness

UNIT1, GRD FLR, VISITOR'S TOILET


Assigned To Structural Skyline
Opened wall for piping

UNIT1, GRD FLR, KITCHEN


Patch up & dress neatly

Page 2 of 9
UNIT1, GRD FLR, KITCHEN WINDOW REVEAL
Not completely dressed

UNIT 1, GRD FLR , KITCHEN STORE


Patch & dress

UNIT 1, GRD FLR, KITCHEN


Patch & dress

Page 3 of 9
UNIT 1, 1ST FLR, FAMILY LOUNGE
Patch & dress to approval

UNIT 1, 1ST FLR, BACK BEDROOM TOILET


To be dressed

UNIT 1, 1ST FLR, BACK BEDROOM TOILET


Bury pipe & redress neatly

Page 4 of 9
UNIT 1, 1ST FLR, BACK BEDROOM TOILET
Unfinished wall plastrering & dressing after
installation of mixer

UNIT1, 1ST FLR, FRONT BEDROOM TOILET


Work still in progress here

UNIT 1, STAIRCASE AREA,FROM 1ST FLR TO


2ND FLR
Redress to squareness

Page 5 of 9
UNIT1, 2ND FLR, FRONT BEDROOM.
Patch & redress neatly

UNIT1, 2ND FLR, BACK BEDROOM TOILET


Dress wall neatly

UNIT2, GRD FLR, LIVING ROOM WINDOW


Not in square

Page 6 of 9
UNIT2, GRD FLR, VISITOR'S TOILET ENTRANCE
Patch & redress

UNIT2, GRD FLR, IIVING ROOM @ STAIRCASE


AREA
Patch & dress to approval

UNIT2, GRD FLR, KITCHEN STORE


Build the wall completely & dress to approval

Page 7 of 9
UNIT2, GRD FLR, KITCHEN
Patch & dress to approval all places chiseled
out in the kitchen

UNIT2, 1ST FLR, FAMILY LOUNGE EXIT DOOR


Patch & dress to approval

UNIT2, 1ST FLR,BACK BEDROOM TOILET


Patch & dress to approval all the chiseled out
walls

Page 8 of 9
UNIT 1& 2, 2ND FLR, FRONT BEDROOM TOILET
Patch & dress to approval

Page 9 of 9