Engineer
Instruction ROM No. Engineer Instruction Description ROM Submitted work Status Time impact Remarks
no
4
Water disinfection in water tanks & net ROM approved Not started Yes
works
5
Installation Brakets of Fiber cable on Return with JLL Work under progress Yes
boundary wall comments
6 Concentrate Resources N/A
8 water meter at villas & Duplexes ROM approved Not started Yes
9
Saving due Modification floor Return with JLL Work under progress
mounted handrail to wall mounted comments
10 Additional Switch drayer & washer Return with JLL work completed Yes
comments
11 GHF revised layment security Not submitted Not started Yes
12 Modification of Cigar lounge CBU12 Return with JLL Work under progress Yes
comments
13 Replacing light fixture W 1 to LL4 ROM approved P.O issed Yes
Pages: 1 /1
08/12/2020