You are on page 1of 7

ANTARA COMPOUND PROJECT -MAIN WORKS PACKAGE

DAILY SITE PROGRESS REPORT


Report No.: 743 Work Done On: 05-Jul-20 Date of Report: 06-Jul-20
Project Duration and Dates: Temperature:
Project Start 2-Jan-18 Project Duration 820 Project Finish 31-Mar-20 Max. Temperature 41◦C Min. Temperature 28◦C
Forecasted Finishing date
Project Updating: Weather and Humidity:
Daily Update as % of Project Duration Weekly Update as % of Cost Daily Direct Manpower WEATHER: ü SUNNY CLOUDY ü RAINY
Actual Duration % Remaining Duration % Planned Actual Variance Planned Actual Variance 310 HIGH MEDIUM LOW

820 100% -96 -12% 0.00% 0 0 0

01. CONSTRUCTION OF INFRASTRUCTURE WORKS:


Percentage Resources
Zone Building Activity
Name Today Yest. Name Today Yest. Name Today Yest. Var.
* Wooden Door frame fixing work in Ground Floor Villa VC7/2 Electrician Helper Labor
* Lighting fixing work in Basement Sport Building Mason Helper Labor
* Ducting fixing work in Ground Floor Villa DC1/5 Carpenter Helper Labor
* Gypsum Ceiling board fixing work in First Floor Employee House Mason Helper Labor
Zone # 2
* Stair riser work in Out side Employee House Mason Helper Labor
* Water tank block work in Roof area Villa DC1/5 Electrician Helper Labor
* Toilet water hiter fixing work in First Floor Employee House Mason Helper Labor
* First coat color paint work in First Floor Carpenter Helper Labor
AA5 * First Floor ceiling tiles work Mason Helper Labor
AA5 * Ground Floor Kitchen marble work Mason Helper Labor
AA6 * Ground Floor paint work Painter Helper Labor
AB2/1 * Second Floor Gypsum board work Mason Helper Labor
DC1/2 * Paint work Plumber Helper Labor
DC2/3 * Structure on Stair Electrician Helper Labor
DC2/5 * Plumber work Carpenter Helper Labor
DC1/2 * Silicon full bath tub Electrician Helper Labor
DC2/1 * Granite fixing on Stair Mason Helper Labor
Zone # 3 DC2/4 * Paint work Steel Fixer Helper Labor
DC3/1 * Granite fixing on Stair Steel Fixer Helper Labor
VC13/3 * Fixing Light Mason Helper Labor
VC8/5 * Tiles work Electrician Helper Labor
VC13/1 * Hand rail work Mason Helper Labor
VC8/5 * Closing for Gypsum board Mason Helper Labor
VC8/1 * Steel frame clay tiles roof Electrician Helper Labor
VC8/1 * Paint work Plumber Helper Labor
VC1/2 * Plumber work Plumber Helper Labor
VC2/3 * A/C work in Roof area Plumber Helper Labor
* Tiles Grouting for Swimming Pool Carpenter Helper Labor
VC12/3 * Electrical work Electrician Helper Labor
VC12/3 * Suspension system for Gypsum board work Carpenter Helper Labor
Zone # 4
VC4/1 * Tiles work for Kitchen Plumber Helper Labor
V5/2 * Paint work for ceiling Mason Helper Labor
VC4/1 * Aluminium Door work Mason Helper Labor
03.  SUMMARY OF USED EQUIPMENT:
QTY
Staff Day Shift Night Shift Direct Labor Day Shift Night Shift Direct Labor Day Shift Night Shift S.N. Description Night
Prev. Day Prev. Night Day Shift
Shift
Project Manager 1 Labor 160 Bus 0 0
Deputy Project Manager 0 Mason 158 Compressor 3 3
Construction Manager 4 Diesel Trank 5 5
QA/QC Engineer 4 Mason Helper 19 Dyna Truck 2 2
Mason Tiler 33 Generator (Large) 5 5
Procurement Engineer 1 Steel Fixer 51 Mobile Crane (30/50 TON) 1 1
Site Engineer (Civil) 4 Steel Fixer Helper 2 Plate Compactor 2 2
Senior Civil Engineer 1 HSE Helper 3 Roller Compactor 1 1
Site Engineer (Arch) 0 Sewage Tank 7 7
Mechanical Engineer 2 Carpenter 14 Skid Roller (Bobcat) 4 4
Senior Planning Engr. 1 Plumber 30 Steel Cutting/Bending machine 6 6
Document Controller 2 Electrician Helper 9 Vibrator 13 13
Electrical Engineer 3 Electrician 53 Water Tank (Large) 19 19
Scaffolding Foreman 1 Sh. Carpenter 70 Water Tank (Small) 6 6
Auto Cad Operator 3 Carpenter Helper 2 Welding Machine 3 3
QS Engineer 2 Plumber Helper 7
Purchaser 2 Finishing Carpenter 16
HSE Manager/Supervisor/Assis. 11 Painter 45
Land Surveyor 1
External Work Manager 1 Driver 1
MEP Manager 0 Store Keeper 2
Senior Architect 0 Erector/Welder 5
Electrical Foreman 2 Equipment Operator 8
Mechanical Foreman 3
Cost Control Engineer 0
Civil Foreman 7
Finishing Foreman 2 Rental 0
Technical Manager Plumber (CFD) 21
Sub-Contractor 51
Security Guard 4
Nures 0
Subtotal: 62 0 Subtotal: 760 0 Subtotal: 0 0 SUBTOTALS: 77 0 77 0
Total Manpower: 822
PROGRESS PHOTOGRAPHS
Photo Description Location: Date:
Cleaning on trench area and application of putty prior
#1 epoxy painting SEC Room 1/12/2017
Photo Description Location: Date:
#2 MV stair work - forms installation and rebar installation SEC Room 1/12/2017
prior for concreting
Photo Description Location: Date:
#3 Electrical works - continuous cleaning of the pull boxes SEC Room 1/12/2017
Photo Description Location: Date:
#4 Concrete pouring for the roof deck slab and parapet SEC Room 1/12/2017
Photo Description Location: Date:
#5 Concrete pouring for the perimeter wall - last lift. SEC Room 1/12/2017
02.   MANPOWER:
Day Night
Day Shift Night Shift
Staff Staff Shift Shift
Project Manager 1 Structural Engineer 0
Deputy Project Manager 0 Electrical Engineer 3
Technical Manager 0 Site Engineer (Civil) 4
Construction Manager 4 Scaffoding Foreman 1
HSE Manager/Supervisor/Assis. 11 Mechanical Foreman 3
Sr. Planning Engineer 1 Mechanical Engineer 2
QA/QC Engineer 4 Auto Cad 3
Procurement Engineer 1 Surveyor 1
Logistic 2 Cost Control Engineer 0
MEP Manager Document Controller 2
0 Electrical Foreman 2
External Work Manager 1 Site Engineer (Arch) 0
0 Senior Civil Engineer 1
0 Security 4
Quantity Surveyor 2 Finishing Foreman 2
Foreman 7
Male Nurse 0

Total Staff 62

Day Night
Labor Day Shift Sub-Contractor
Shift Shift
Labor 160
Mason 158
Mason Helper 19
Mason Tiler 33
Steel Fixer 51
Steel Fixer Helper 2
Plumber (CFD) 21
HSE Helper 3
Electrician Helper 9
Electrician 53
Plumber 30
Carpenter 14
Sh. Carpenter 70
Carpenter Helper 2
Finishing Carpenter 16
Painter 45
Plumber Helper 7
Driver 1
Erector/Welder 5
Store Keeper 2
Equipment Operator 8
Sub-Contractor 51
Rental 0
Total Direct 760 Total Sub-Contractor
Overall Total 822
03. SUMMARY OF USED EQUIPMENT: 32
24
QTY
S.N. Description Unit of Measure Yesterday (Day Yesterday Day Night
Shift) (Night Shift) Shift Shift
1 Bus 15 0 0
2 Compressor Number 3 3
3 Diesel Trank Number 5 5
4 Dyna Truck Number 2 2
5 Generator (Large) Number 5 5
6 Mobile Crane (30/50 TON) Number 1 1
7 Plate Compactor Number 2 2
8 Roller Compactor Number 1 1
9 Sewage Tank Number 7 7
10 Skid Roller (Bobcat) Number 4 4
11 Steel Cutting/Bending mac Number 6 6
12 Vibrator Number 13 13
13 Water Tank (Large) Number 19 19
14 Water Tank (Small) Number 6 6
15 Welding Machine Number 3 3
16 Number
TOTAL 77 77

QUALITY TODAY CUMULATIVE

Received Closed Open Received Closed Open

NCR 0 0 0 156 136 20

SON 0 0 0 375 306 69

SAFETY TODAY CUMULATIVE

SAFETY
0 0
INDUCTION

INCIDENT 0 1

220

04.OTHER ACTIVITIES

05.DELIVERED MATERIALS

06.VISITOR

You might also like