Engineering Department

https://levinson.com.ph/

PROJECT: SAN PEDRO MIGRATION PROJECT (BASEPAD CONSTRUCTION AND CABINET INSTALLATION)
SUBJECT: IMPLEMENTATION TIMETABLE

- August
Item Activity days 15 16 17 18 19 20 21 22
1 Basepad Construction 2
2 Conduit laying 2
3 Concrete Pouring 1
4 Curing Time 7
5 Cabinet installation 1
6 Electrical wiring layout 1
OVERALL 12

PREPARED BY: NOTED BY:

DANIEL ANGELO ETINO REYNALDO PELAEZ JR


PROJECT ENGINEER PROJECT-HEAD
ABINET INSTALLATION)

August
23 24 25 26 27 28 29 30 31