Professional Documents
Culture Documents
actual construction contractor’s rate and some were supplemented from various
average rates and costs listed on the internet. The estimates for the tank were
based on the results from STAAD RCDC, while the estimates for the piping layout
which entails identifying and organizing project information and tasks. This
comprises site preparation and tank construction, such as the foundation, tank
walls, tank cover, pipe layout, and post-construction. This insight guarantees that
the researchers are ready to create dependencies and connect tasks in the phases
ahead. The critical path method (CPM) and the PERT formula were used to
estimate the entire project time frame. The critical path is the longest sequence of
tasks that must be done in order for a project to be finished effectively. In order to
estimate the shortest overall project duration, the aim is to determine the longest
81
Table of the Activities:
1 Gathering of Materials 2
2 Transportation of Materials 1
3 site inspection 1
4 Node Marking 1
Protection/Relocation of existing
5 Trees 2
Foundation
7 Gravel bedding 1
8 Rebars 2
9 Formworks 2
10 Concrete pouring 2
11 Curing 3
12 Soil backfill 1
82
Tank walls
13 Rebars 3
14 Formworks 2
15 Concrete pouring 3
16 Curing 3
17 Surface finishing 1
18 Waterproofing 1
Tank Cover
19 Rebars 2
20 Formworks 2
21 Concrete pouring 2
22 Curing 3
23 Surface finishing 1
24 Excavation 8
25 Installation of pipes 6
83
26 Pipes fitting 5
27 Valves installation 5
28 Pump installation 1
29 Soil backfill 6
Post construction
30 Waterfilling 1
31 Inspection 1
32 Test run 1
33 Clean up 3
84
Table 3. PERT/CPM
PATHS:
PATH A: START-1-2-6-7-8-9-10-11-12-13-14-15-16-17-18-19-20-21-22-23-30-
31-32-33-END
PATH B: START-1-2-24-25-26-27-28-29-30-31-32-33-END
85
PATH C: START-3-4-24-25-26-27-28-29-30-31-32-33-END
PATH D: START-3-5-24-25-26-27-28-29-30-31-32-33-END
22-23-30-31-32-33-END
A 44 0
B 37 7
C 43 1
D 44 0
86
Figure 24. GANTT Chart
Table 2, illustrates the early start to early finish as well as the late start to a
that cannot be delayed. The other activity, on the other hand, can occur at any
time. Figure 2 illustrates the project's Gantt Chart. On the left side of the chart,
you'll find a list of the activities, and at the top, you'll find a suitable time scale. To
summarize, a Gantt chart shows what must be done (activities) and when it must
be completed (the schedule). The non-critical activities are shown by the shaded
red row, which indicates how many days they can be delayed.
87
4.5 Resource Requirements
88