Professional Documents
Culture Documents
Sheet Piling Works L13, L13, L14 & L15 Inspection of Sheet Piling Works On-going
L14 & L15 conducted at L13, L14 & L15
Accomplishment for L13, L14 & L15 Along L13 area: On-going
Permanent piles driven Total piles driven as of July 19,
2022- 116 pcs/L=16.5m
H-700x200x12
Inspection of Relocation Sta. 10+980 to Sta. The contractor’s proposed The proposed site for the
Area for the Trees to be 12+300 relocation area/site for the trees to relocation of affected trees
Earth-Balled at L6-L7 be removed at L6-L7 was at L6-L7 is approved by the
inspected by the River Parks RPA. The contractor will
Authority officers together with prepare the layout plan for
the representative from the the relocation site.
UPMO and our local
environmentalist
Quality Control Management
Contract Package No. 2
Item Location Description Result
Steel piles Grandspan Routine inspection of fabrication of Checked DFT of Prime Coat,
Fabrication Shop steel piles for R2 - #204 to #471 Body
Binangonan, Rizal (welding & painting)/ (7/01 & Coat and Finish Coat.
06/2022)
Concrete samples E. B. Testing Center Compression test of trial mix Passed specification
concrete samples for Classes A, B, requirements
C & F @ 7 days from Tokwing
Batching Plant (7/05/2022)
Riprap samples Disposal Site Weighing of Rocks samples for Ranges of Riprap for:
Office, Brgy. Sta. Riprap Classes B, C & D Class B- 30 to 70 kg.
Ana, Taytay, Rizal (7/05/2022) Class C- 60 to 100 kg.
Class D- 100 to 200kg.
Pile Driving Station 6+700 R/B Inspection of driven piles (R1 - #1 to Pile #1, 8, 9 were not driven to
(Circulo Verde #66) designed elevation.
Area) (7/06/2022) Damage paint in some piles.
Unsuitable materials were
backfilled at the back of steel
piles.
Concrete Agg. Package 3, Lab., at Testing of Coarse Agg. (G-1, G-3/4, For site mix concrete.
Noah Stockyard, G-3/8) from Millex, Montalban,
Calumpang, Rizal. (7/07/2022)
Marikina
Steel Piles Grandspan Routine inspection of fabrication of Checked DFT of Prime Coat and
Fabrication Shop steel piles for R2 - #204 to #471 Finish Coat.
Binangonan, Rizal (welding & painting)/ (7/08/2022) Checked quality of weld joints
using MPT (Magnetic Particle
Test)
Concrete Samples E. B. Testing Center Compression test of trial mix Passed specification
concrete samples for Classes A, B, requirements
C & F @ 14 days from Tokwing
Batching Plant (7/12/2022)
Steel Piles Grandspan Routine inspection of fabrication of Checked DFT of Primer and Top
Fabrication Shop steel piles for R2 - #204 to #471 and Coat for R2 steel piles.
Binangonan, Rizal L1- #1 to #62 (welding & painting)/ Checked weld joints for L1 -
(7/13/2022) #25 to #28 steel piles using
MPT
Concrete Aggregates Temporary Jetty Sampling of Vibro Sand from Porac, For Quality Test
Stockyard, Sta Ana, Pampanga (Byant Quarry)/
Taytay, Rizal (7/18/2022)
Material Testing Sta. 6+700 R/B, Sampling of Soil, covering sta. Subject for Quality Test
Circulo-Verde Area 6+700 to 6+785 R/B along driven
Steel Piles (7/19/2022)
Steel Piles Grandspan Fab. Shop Routine inspection of fabrication of Checked DFT of Body Coat and
steel piles R2 - #204 to #471 & L1
Binangonan, Rizal Top Coat for R2 steel piles.
- #1 to #62 (welding and painting)/
(7/20,22/2022) Checked DFT of Body Coat for
L1 steel piles
Concrete Samples E.B. Testing Center Compression test of trial mix Passed specification
concrete samples for Class A, B, C requirements
& F @ 28 days from Tokwing
Batching Plant (7/26/2022)
Quality Control Management
Contract Package No. 3
Item Location Description Result
a. Magnetic Particle - Noah Stockyard, NDT for welded/fabricated SSPs Passed Specs.
Test (on-going) Marikina City and H- Beams
b. Weld Thickness Test - Grandspan, Total to date: 07.14.2022
c. DFT for Corrosion Binangonan. 1. 527 + (Phil. Inspect)
Paint Rizal 2. 456 + (Grandspan)
Witnessed Tensile EB Testing Center MS Plate (Machine Specimen) Date Passed Specs.
Strength Test of Steel 7.05.2022
Plate Specimen (SSP)
Quarry Visit/ Inspection 1. Mendoza Quarry, Proposed additional Sources for: Samples were taken for
Angilan, San a. S1 Quality tests.
Isidro, b. G1
Montalban, Rizal c. MSG
2. Allan Quarry San d. Base Course
Isidro, Date: 7. 22.2022
Montalban, Rizal Supplier: Almario Trading & FSI
Trial Mix for PCD BF Corporation Proposed Pumpcrete Mix Design TBS
Batching Plant, Date:7.25.2022
Kalumpang,
Marikina City
CST QC Laboratory at Concrete Class A Passed Specs.
Noah Stockyard 28 days; 3- cylinders samples
Marikina Structure: Inclined Wall, 1st Lift,
Span 1
Supplier: Omnicrete
Date: 7.25.2022
Vol. = 9.064 cu. m
RS Bars 12 mm Ø EB Testing Center Physical & Mechanical tests (2 Passed Specs.
Pasig City samples)
Supplier: Pag Asa Steel
Date: 7.26.2022