You are on page 1of 6

Field Inspection and Supervision Activities, and other related activities

Contract Package No. 2

Item Location Description Result


Additional Outlet Found Sta. 11+740 (Left Additional Outlet Concept Design will be
on Sta. 11+740 (Left Bank) provided by the Consultant
Bank)
SSP Driving Sta 6+700 RB (R1) Inspection of SSP driving at R1 66 piles driven. Pile driving to
resume at the end of the month.
Temporary Loading Jetty Sta 7+772 – Sta Excavation & pile driving Ongoing
7+799 works at Jetty Area
Temporary Loading Jetty Sta 7+772 – Sta Demolition works at Jetty Area Done
7+799
Temporary Unloading Disposal Area Jet grouting works Ongoing
Jetty
Additional Dredging Sta 4+250 – Sta Dredging works Sta 4+275 – Sta 4+325 turned
Works 6+700 over by Contractor Ongoing
dredging works at Sta 4+400
Additional Foundation Sta 8+440 LB Joint Inspection w/ UPMO, Borehole #3 at
Investigation Sta 8+520 LB CTI Sta 8+640 LB to start on July
Sta 8+640 LB 18, 2022
Verification of Trees for Sta 6+700 – Sta Joint Inspection w/ DENR- Done
cutting 9+300 RB NCR, UPMO, TOYO
Additional Foundation Sta. 8+640 LB Inspection of Boring work Done
Investigation
Additional Dredging Sta. 4+325 – Sta. Partial Turnover Done
Works 4+375
Additional Dredging Sta. 4+250 – Sta. Dredging Works Ongoing at Sta. 4+600
Works 6+700
Temporary Loading Jetty Sta. 7+772 – Sta. Pile Driving works Ongoing
7+799
Temporary Unloading Disposal Area Jet grouting works Ongoing
Jetty
Additional Trial Piling Sta. 8+422 LB Inspection of Trial Piling Setup 1 reached 6m elevation,
not reaching design elevation.
Setup 2 reached design
elevation of -2m.
Field Inspection and Supervision Activities, and other related activities
Contract Package No. 3
Item Location Description Result
Walkthrough Inspection NCR Road Dike Walkthrough with Marikina LGU Done
with Marikina LGU at NCR regarding adjustment of SSP
Road Dike Alignment
Meeting with PLDT Manggahan Office Meeting with PLDT Rep. Done
Representatives regarding their existing Telecom
Lines under Marcos Bridge, R/B.
Concrete Pouring of NOAH (Roadside) Inspection of Concrete Pouring Ongoing
Inclined Wall along M.H. (Lean, Base, 1st Lift & 2nd Lift)
Del Pilar St. @ NOAH of Inclined Wall along M.H. Del
Area Pilar St. @ NOAH Area
Sheet Piling Works at L14, L14, L13 & L15 Inspection of Sheet Piling Works Ongoing
L13 & L15 conducted at L14, L13 & L15
Demolition Works NOAH, L13, L15 Inspection of demolition of Done
existing structures (Inclined Wall,
CHB Wall and Pile coping
Inspection of Existing L15 Inspection of existing drainage Done
Drainage @ L15 excavated @ L15
Inspection of Cross- L 14 Inspection of cross section survey Pending survey plans from
sectional Survey between done between SSP and existing the Contractor
SSP and existing coping for coping prior to free draining
backfilling backfill
Inspection of Horizontal NOAH Area along Inspection of inclined wall Ongoing
and Vertical Alignment of M.H. Del Pilar alignment prior to concrete
Inclined Wall pouring of inclined wall along
M.H. Del Pilar
Accomplishment for L14, L13 Along L13 area: Ongoing
Permanent piles driven 106 SSP w/H-Beam driven:
L=16.5m, H-700x200x12
Along L14 area:
88 SSP w/ H-Beam driven:
L=16.5m, H-700x200x12
Walkthrough Inspection Padua Church to Walkthrough Inspection with Done
with Marikina LGU for existing NCR Marikina LGU for SSP
SSP Alignment Road Dike Alignment near NCR Road Dike
Concrete Pouring of NOAH (Roadside) Inspection of Concrete Pouring Done
Inclined Wall along M.H. (Base, 1st Lift & 2nd Lift) of
Del Pilar St. @ NOAH Inclined Wall along M.H. Del
Area Pilar St. @ NOAH Area

Sheet Piling Works L13, L13, L14 & L15 Inspection of Sheet Piling Works On-going
L14 & L15 conducted at L13, L14 & L15
Accomplishment for L13, L14 & L15 Along L13 area: On-going
Permanent piles driven Total piles driven as of July 19,
2022- 116 pcs/L=16.5m
H-700x200x12

Along L14 area:


Total piles driven as of July 25,
2022- 88 pcs/L=16.5m
H-700x200x12

Along L15 area:


Total piles driven as of July 25,
2022- 34 pcs/L=15.5m
H-600x200x12
Demolition Works NOAH, L13, L15 Inspection of demolition of Done
existing structures (Inclined Wall
and existing pavement)
Item Location Description Result
Inspection of Cross- L12a Inspection of cross-sectional On-going
sectional Survey prior to survey prior to excavation and
Excavation and Backfilling backfilling at L12a @ Elev.
+13.0m (STA 11+100 – 11+180)
Inspection for Backfilling NOAH (Roadside) Inspection of backfilling of base On-going
of inclined wall with MSG and
Mountain Soil.
Inspection of backfilling at
permanently driven SSP @ L14
with free-draining backfill
Inspection of Cross- L14 Inspection of cross section survey Pending survey plans from
sectional Survey between done between SSP and existing the Contractor
SSP and existing coping coping prior to free draining
backfill

Inspection of Relocation Sta. 10+980 to Sta. The contractor’s proposed The proposed site for the
Area for the Trees to be 12+300 relocation area/site for the trees to relocation of affected trees
Earth-Balled at L6-L7 be removed at L6-L7 was at L6-L7 is approved by the
inspected by the River Parks RPA. The contractor will
Authority officers together with prepare the layout plan for
the representative from the the relocation site.
UPMO and our local
environmentalist
Quality Control Management
Contract Package No. 2
Item Location Description Result
Steel piles Grandspan Routine inspection of fabrication of Checked DFT of Prime Coat,
Fabrication Shop steel piles for R2 - #204 to #471 Body
Binangonan, Rizal (welding & painting)/ (7/01 & Coat and Finish Coat.
06/2022)
Concrete samples E. B. Testing Center Compression test of trial mix Passed specification
concrete samples for Classes A, B, requirements
C & F @ 7 days from Tokwing
Batching Plant (7/05/2022)

Riprap samples Disposal Site Weighing of Rocks samples for Ranges of Riprap for:
Office, Brgy. Sta. Riprap Classes B, C & D Class B- 30 to 70 kg.
Ana, Taytay, Rizal (7/05/2022) Class C- 60 to 100 kg.
Class D- 100 to 200kg.

Pile Driving Station 6+700 R/B Inspection of driven piles (R1 - #1 to Pile #1, 8, 9 were not driven to
(Circulo Verde #66) designed elevation.
Area) (7/06/2022) Damage paint in some piles.
Unsuitable materials were
backfilled at the back of steel
piles.
Concrete Agg. Package 3, Lab., at Testing of Coarse Agg. (G-1, G-3/4, For site mix concrete.
Noah Stockyard, G-3/8) from Millex, Montalban,
Calumpang, Rizal. (7/07/2022)
Marikina
Steel Piles Grandspan Routine inspection of fabrication of Checked DFT of Prime Coat and
Fabrication Shop steel piles for R2 - #204 to #471 Finish Coat.
Binangonan, Rizal (welding & painting)/ (7/08/2022) Checked quality of weld joints
using MPT (Magnetic Particle
Test)
Concrete Samples E. B. Testing Center Compression test of trial mix Passed specification
concrete samples for Classes A, B, requirements
C & F @ 14 days from Tokwing
Batching Plant (7/12/2022)
Steel Piles Grandspan Routine inspection of fabrication of Checked DFT of Primer and Top
Fabrication Shop steel piles for R2 - #204 to #471 and Coat for R2 steel piles.
Binangonan, Rizal L1- #1 to #62 (welding & painting)/ Checked weld joints for L1 -
(7/13/2022) #25 to #28 steel piles using
MPT
Concrete Aggregates Temporary Jetty Sampling of Vibro Sand from Porac, For Quality Test
Stockyard, Sta Ana, Pampanga (Byant Quarry)/
Taytay, Rizal (7/18/2022)
Material Testing Sta. 6+700 R/B, Sampling of Soil, covering sta. Subject for Quality Test
Circulo-Verde Area 6+700 to 6+785 R/B along driven
Steel Piles (7/19/2022)
Steel Piles Grandspan Fab. Shop Routine inspection of fabrication of Checked DFT of Body Coat and
steel piles R2 - #204 to #471 & L1
Binangonan, Rizal Top Coat for R2 steel piles.
- #1 to #62 (welding and painting)/
(7/20,22/2022) Checked DFT of Body Coat for
L1 steel piles
Concrete Samples E.B. Testing Center Compression test of trial mix Passed specification
concrete samples for Class A, B, C requirements
& F @ 28 days from Tokwing
Batching Plant (7/26/2022)
Quality Control Management
Contract Package No. 3
Item Location Description Result
a. Magnetic Particle - Noah Stockyard, NDT for welded/fabricated SSPs Passed Specs.
Test (on-going) Marikina City and H- Beams
b. Weld Thickness Test - Grandspan, Total to date: 07.14.2022
c. DFT for Corrosion Binangonan. 1. 527 + (Phil. Inspect)
Paint Rizal 2. 456 + (Grandspan)

Compressive Strength QC Laboratory at Concrete Class A Passed Specs.


Test (CST) Noah Stockyard 28 days; 3- cylinders samples
Marikina Structure: L-Type Retaining wall
Date: 7.05.2022
Vol. =10.015 cu. m

Witnessed Tensile EB Testing Center MS Plate (Machine Specimen) Date Passed Specs.
Strength Test of Steel 7.05.2022
Plate Specimen (SSP)

CST QC Laboratory at Concrete Class A Passed Specs


Noah Stockyard 7 days; 3- cylinders samples
Marikina Structure: Inclined wall Span 2 (1st
lift)
Date: 7.06 2022, Vol. =9.051 cu.m
Concrete Class A
28 days; 3- cylinders samples
Structure: L-Type Retaining wall,
Span 2
Date: 7. O8.2022, Supplier:
Omnicrete, Vol. = 16.247 cu. m
Concrete Class A
7 days; 3- cylinders samples
Structure: Inclined wall, 2nd Lift,
Span 2
Date: 7. 12.2022, Supplier:
Omnicrete, Vol. = 6.058 cu. m
Concrete Class F
28 days; 3- cylinders samples
Structure: Levelling Concrete,
Inclined wall, Span1 & 2
Date: 7. 13.2022, Supplier:
Omnicrete,Vol. = 2.20 cu. m
Concrete Class A 7 days; 3-
cylinders samples
Structure: Base of Inclined wall,
Span 5
Date: 7. 13.2022, Supplier:
Omnicrete, Vol. = 8.245 cu.m
Concrete Class A 28 days; 3-
cylinders samples
Structure: L-Type Retaining Wall,
Span 3
Date: 7. 13.2022, Supplier:
Omnicrete, Vol. = 10.475 cu.m
Concrete Class F
27 days; 3- cylinders samples
Structure: Levelling Concrete of
Inclined Wall, Span 3 & 4
Date: 7.14.2022, Site Mix, Vol. =
1.204 cu. m
Item Location Description Result
Concrete Class F
6 days; 3- cylinders samples
Structure: Inclined Wall, 2nd Lift,
Span 2
Date: 7.14.2022, Supplier:
Omnicrete, Vol. = 5.995 cu. m
Magnetic Particle Test - Noah Stockyard, NDT for welded/fabricated SSPs Passed Specs.
a. Weld Thickness Marikina City and H- Beams
Test - Grandspan, Total to date: 07. 26..2022
b. DFT for Corrosion Binangonan. Final Coat
Paint (On – going) Rizal 1. 460 + - Noah 2. 382+
(Grandspan)
CST QC Laboratory at Concrete Class A Passed Specs.
Noah Stockyard 28 days; 3- cylinders samples
Marikina Structure: Base of Inclined wall,
Span1 Date: 7.18.2022
Vol. = 8.417 cu. m
CST QC Laboratory at Concrete Class A Passed Specs.
Noah Stockyard 7 days; 3- cylinders samples
Marikina Structure: Inclined Wall, Span 4
Date: 7.19.2022
Vol. = 18 cu. m

Quarry Visit/ Inspection 1. Mendoza Quarry, Proposed additional Sources for: Samples were taken for
Angilan, San a. S1 Quality tests.
Isidro, b. G1
Montalban, Rizal c. MSG
2. Allan Quarry San d. Base Course
Isidro, Date: 7. 22.2022
Montalban, Rizal Supplier: Almario Trading & FSI
Trial Mix for PCD BF Corporation Proposed Pumpcrete Mix Design TBS
Batching Plant, Date:7.25.2022
Kalumpang,
Marikina City
CST QC Laboratory at Concrete Class A Passed Specs.
Noah Stockyard 28 days; 3- cylinders samples
Marikina Structure: Inclined Wall, 1st Lift,
Span 1
Supplier: Omnicrete
Date: 7.25.2022
Vol. = 9.064 cu. m
RS Bars 12 mm Ø EB Testing Center Physical & Mechanical tests (2 Passed Specs.
Pasig City samples)
Supplier: Pag Asa Steel
Date: 7.26.2022

You might also like