RIDF PROJECTS UNDER
IMPLEMENTATION IN
THIRUVANANTHAPURAM DISTRICT

PRESENTED BY
Asst. Executive
Engineer(Agri)
THIRUVANANTHAPURAM
LIST OF PROJECTS
Sl. Tranche Name of project Amount
No. (Rs in lakhs)

1 XX Construction of Ware House and upgradation of 175


road in Rural wholesale Market at Nedumangad

2 XXI Infrastructural work at Pallippuram Ela in 105.9


Andoorkonam KB

3 XXII Infrastructural Development work at DAF & BN 300


Peringammala.

4 XXII Infrastructural Development work at Vellayani 350


Kayal Padasekharam
RIDF Progress Report
Tranche Name of project TFO RIDF(Lo Release GAP/ GAP/
(in an) (in lakhs) Balance as Balance as
lakhs) (in on on
lakhs) 30/11/20 31/12/20

XX Construction of Ware 175 166.25 35.6 130.64 130.64


House and upgradation
of road in Rural
wholesale Market at
Nedumangad
XXI Infrastructural work at 105.9 100.60 100.6 100.6
Pallippuram Ela in
Andoorkonam KB
XXII Infrastructural 300 285 137.44 147.56 147.56
Development work at
DAF & BN
Peringammala.
XXII Infrastructural 350 332.5 110.84 221.66 221.66
Development work at
Vellayani Kayal
RIDF XX-Construction of Ware House and
upgradation of road in Rural wholesale
Market at Nedumangad
Components
• Upgradation of Road at ARWM, Nedumangad
• Construction of Ware House at ARWM, Nedumangad
Target Achievement

Physical 1.Upgradation of road 1.Work completed.

2.Constuction of a new 2.Work entrusted with PWD Buildings,


Ware house NDD sub division as per order of
Director (Agriculture).Funds not
received for transferring to PWD.
Financial 175 Lakhs 35.60 Lakhs

(Contd...)
RIDF XX-Construction of Ware House and
upgradation of road in RAWM at NDD

Upgradation of road in RAWM at Nedumangad


(Contd...)
RIDF XX-Construction of Ware House and
upgradation of road in RAWM at NDD
Problem in Construction of Ware House
Orginal Estimate was prepared for constructing the ware house in hard soil area in side
the market. At the time of work starting, the site earmarked for the original estimate was
changed to a new location by the market authorities. When the excavation for
foundation started in the newly allocated site, it was seen that this site had been a filled
up, marshy & water logged area where construction as per the approved estimate was
not technically feasible. Thus the Director terminated the contract and the work has been
entrusted with PWD. PWD then demanded an amount of Rs..2.67 lakhs for Total station
survey, Soil structure analysis and soil investigation. This fund has not yet been released.
RIDF XXI-Infrastructural work at
Pallippuram Ela in Andoorkonam KB
Components
• Rennovation of existing pond
• Strengthening of bund and channal deepening

Target Achievement

Physical Rennovation of pond and Initial contract was


strengthening of bund and terminated.EE(agri) instructed to
deepening thodu for 1000m revise the estimate . Soil strength
analysis is to be done for revised
design which is entrusted to CET
who requires funds. Funds
requested and not received yet.
Financial 105.9 NIL.
RIDF XXII-Infrastructural work at DAF
& BN Peringammala.
Components
• Surfacing of Farm road using interlock tiles at
BN,Peringamala & DAF, Peringamala
• Rennovation of pond in block no.9 of BN, peringamala
• Construction of pump house, Installation of 5hp
pumpset and rennovation of existing pipe line at BN
• Construction of Superintendent and A.O. Quarters at
DAF

(Contd...)
RIDF XXII-Infrastructural work at DAF &
BN Peringammala
Target Achievement

Physical 1.Surfacing of Farm road 1. Completed the works at BN Peringamala.


using interlock tiles at Testing of samples at KHRI passed and the
BN,Peringamala & contractor started the work at DAF,
DAF,Peringamala Peringamala
2. Rennovation of pond in 2. Work completed.
block no.9 of BN,peringamala
3. Construction of pump 3.No participation of contractors for 3
house, Installation of 5hp consecutive tenders. Then retendered as
pumpset and rennovation of a combined work . Single bid received and
existing pipe line at BN the work was awarded and the work
4. Construction of inprogress
Superintendent and A.O. 4. The work and fund was transferred to PWD
Quarters at DAF & work in progress(90% completed)
Financial 300 Lakhs 137.44 Lakhs
(Contd...)
RIDF XXII-Infrastructural work at DAF &
BN Peringammala

Surfacing of Farm road using interlock tiles at BN,Peringamala


(Contd...)
RIDF XXII-Infrastructural work at DAF &
BN Peringammala

Renovation of pond in block no.9 of BN,peringamala


RIDF XXII-Infrastructural work at DAF &
BN Peringammala

Construction of Quarters at DAF Peringamala


(Contd...)
RIDF XXII-Infrastructural work at DAF
& BN Peringammala
Work proposed for GAP FILLING
1.Construction of officers’ quarters at BN,
peringamala
2.Extension of resurfacing of road in both the
farms.
RIDF XXII- Infrastructural Development
work at Vellayani Kayal Padasekharam
Components
• Supplying and installing 7Nos of vertical turbine pumps
• Raising of bund road at Pandarakkari padasekharam
• Strengthening and raising of bund road at kanjirathadi
padasekharam
• Construction of leading canal at Pandarakkari padasekharam
• Construction of leading canal at kanjirathadi padasekharam
• Construction of leading canal at Mangilikkari padasekharam
• Enhancing capacity of existing transformers
• Providing addl. Strengthening works for submersible pumps
installed at various padasekharams
(Contd...)
RIDF XXII- Infrastructural Development
work at Vellayani Kayal Padasekharam
Target Achievement
Physical 1.Supplying and installing 7 Nos of vertical 1. Completed
turbine pumps
2. Rising of bund road at Pandarakkari 2.&3. No participation in tender
padasekharam even after 3 tenders. Now re-e-
3. Strengthening and rising of bund road at tendered as a combined work.
kanjirathadi padasekharam No participation in re-e-tender
4. Construction of leading canal at Pandarakkari also.
padasekharam 4. work completed.
5. Construction of leading canal at kanjirathadi 5. Agreement executed .Not
padasekharam started.
6. Construction of leading canal and side 6. 90% of side protection
protection of thodu at Mangilikkari padasekharam completed
7. Enhancing capacity of existing transformers 7.Fund transferred to KSEB
8.Providing addl. Strengthening works for 8. Agreement executed.
Submersible pumps installed at vellayani
padasekharams
Financial 350 Lakhs 110.84 Lakhs (Contd...)
RIDF XXII- Infrastuctural Development
work at Vellayani Kayal Padasekharam

Supplying and installation of vertical turbine pumps


(Contd...)
RIDF XXII- Infrastuctural Development
work at Vellayani Kayal Padasekharam

Construction of leading canal at Pandarakkari


padasekharam
(Contd...)
RIDF XXII- Infrastuctural Development
work at Vellayani Kayal Padasekharam

Construction of leading canal at Manglikary


padasekharam
RIDF XXII- Infrastuctural Development
work at Vellayani Kayal Padasekharam
Work proposed for GAP FILLING
1.Extension of Canal construction after getting
approval from padasekhara samati meeting
which is scheduled on 7/1/2021