CONSTRUCTION OF SPUR IN UNION COUNCIL

BAIT BAET WALA MAUZA BAIT CHIN D.G. KHAN

DATED: 20-12-2022

(ADP No. 3477)


Cost: 631.65 Million

D.G KHAN IRRIGATION ZONE,


MUZAFFARGARH CANAL CIRCLE, MULTAN
MUZAFFARGARH CANAL DIVISION MUZAFFARGARH
NAME OF WORK: CONSTRUCTION OF SPUR IN UNION COUNCIL BAIT
BAET WALA MAUZA BAIT CHIN D.G. KHAN.

Sponsoring Agency: Government of the Punjab

Executing Agency: Punjab Irrigation Department

Location: The project area is located in Tehsil Kot Chutta, District D.G Khan

Approval Status: Un-Approved

Cost (Rs million): Rs. 631.65 Million

Source of Financing: Govt. of the Punjab under ADP 2022-23.

Allocation (2021-22): Rs. 75.00 Million

Implementation Period: 14 Months (01.01.2023 to 29.02.2024)


GOOGLE MAP
GOOGLE MAP
SURVEY PLAN
SURVEY PLAN
NECESSITY

 To protect irrigation infrastructure like Cheen wala Minor and main Muzaffargarh
Canal. The distance between Cheen wala minor and River edge is just 2500 ft and
intensive continuous erosion is reducing the distance with every passing day.
 To protect other Govt. infrastructure like roads, schools, police check posts, hospitals
and allied abadies like Bhindi Suleman Shah, Bait Cheen wala, Bait bait wala,
Kaleem chowk ect.
 To check continuous leftward erosion of precious agricultural lands, orchards etc.

Background:
 D/S of Ghazi Ghat Bridge, Ghazi Ghat D/S Flood Bund from RD:0+000 to
RD:75+554 was constructed to check continuous erosion of River Indus and to
protect Abadies like Basti Rind Adda, Ghazi Ghat town and Mauza Maitla in
addition to irrigation infrastructure and other Govt infrastructure.
BACK GROUND

 Zilla council constructed Flood Bund from RD:0+000 to RD:12+000 in continuation


of D/S Ghazi Ghat Flood Bund to protect Abadies, fertile agricultural lands, Cheen
wala Minor and other infrastructure from River inundation.
 Cheen wala Minor and allied abadies D/S of Zilla Council Flood Bund are exposed to
River inundation as there is no any flood bund.
 Continuous erosion of River near Ameen Chowk and Kaleem Chowk has engulfed
houses, road infrastructures, orchards and fertile agricultural lands.
 Due to leftward drifting of river Indus the distance between River edge and main
Muzaffargarh Canal is reducing with every passing day.
 During current flood year 2022 River inundation not overtopped the right bank of
Cheen wala Minor but remained in toe of bank.
 During exceptionally high flood 2010 River water overtopped Cheen Wala Minor and
rushed to the right bank of Muzaffargarh Canal.
PROPOSAL

1. Construction of Inverted Hockey Spur at RD:9+000 of Cheen wala Flood Bund.

2. Construction of Solid Sloping Spur No.1 U/S of proposed Inverted Hockey Spur.

3. Construction of Solid Sloping Spur No.2 D/S of proposed Inverted Hockey Spur.

4. Raising / Strengthening of District Council Flood Bund from RD:0+000 to

RD:12+600.

These structures have been provided as per recommendations of Model Study

and Departmental Expert Committee guidelines.


GENERAL ABSTRACT OF COST

Sr.
Description. Amount
No.
CONSTRUCTION OF SPUR IN BAIT CHEEN WALA
1 332088360
(PACKAGE-A)

CONTROLLING EROSIVE ACTION OF RIVER INDUS


& INUNDATION HAZARDS ARROUND BAIT CHEEN
2 WALA BY CONSTRUCTING CHEEN WALA FLOOD 177755395
BUND (TIE BUND)
(Package "B")

  TOTAL COST OF CIVIL WORKS 509843759


3 LAND ACQUISITION 72862435
4 ADD 2% WORK CHARGE CONTINGENCY 10196875
  ADD 6.5% PRICE ESCALATION ON 40% on 2nd Year 13255938
  ADD 5% PRA Tax on Item Works 25492188
     
  Total :- 631651195
  Say Rs. In Million. 631.65
PICTURES
PICTURES
PICTURES
PICTURES
PICTURES
PICTURES
PICTURES
PICTURES
PICTURES
PICTURES
PICTURES
REPLY OF OBSERVATIONS
Sr.
Observations Reply
No.
The Sponsor have made the provision of Rs. 14.125
Million for reserve stock of stone for the proposed
Compliance has been made by attaching the
i interventions. Sponsor may provide the yard stick
approved yard stick of reserve stock limit.
approved by the Competent Authority and the same may
be attached with the document.
The Sponsor have made the provision of construction of 1
No. inverted hockey spur & 2 No. sloping spurs while in The provisions in PC-I have been made as per
the model study report it is mentioned that in case of recommendations of Model Study and then
ii
medium & high flood stages, these proposed interventions accordingly the guidelines by Departmental
will become ineffective. Sponsor may justify the same Expert Committee meeting held on 16.09.2022.
without conducting new model study.
Viewing into the alarming site situation and for
It was suggested in model study report No. 1388 that to
timely completion of project to avoid further loss
determine the suitable training works at medium & high
of time, the matter was referred to Departmental
iii flood discharges fresh model study may be required while
Expert Committee. This PC-I has been framed on
the proposed project has been framed on old model study
the recommendations of Model Study and
report.
Departmental Expert Committee guidelines.
As the whole project area fall in the Chakbandi
The Sponsor have made the provision of earth work lead of Bait Cheen Wala Minor and consists of
1.0 mile for all earth filling while the structure is being precious fertile agricultural lands, so 1.00 mile
iv
constructed in the river bed and local earth can be used lead is provided as per site condition duly
and 1.0 mile lead may be rationalized. checked and verified by NESPAK ADP
Consultants.
REPLY OF OBSERVATIONS
Sr.
Observations Reply
No.
L-Sections of the inverted hockey spur is not approved by the
v Competent Authority. Sponsor may attach approved copy of Compliance has been made.
L-Section with the document.
The Sponsor have referred the minutes of experts committee
meeting dated 19-09-2022 while the copy of minutes have Compliance has been made by appending the
vi
not been attached with the document. Sponsor may make it same.
part of document.
The lead diagrams for carriage of stone and transportation of
earth are not approved by the competent authority. Sponsor Compliance has been made by appending the
vii
may attach approved copy of lead diagrams with the same.
document.
Lead provided in inverted hockey 1.00 Mile
The lead diagram for transportation of earth for inverted and 2.00 Mile. 2.00 Mile lead is provided for
viii hockey spur lead 2.0 miles has been erroneously calculated. good earth to protect the top of the shank
Sponsor may correct the same. length of 6200 Ft, which was duly checked
and verified by NESPAK ADP Consultants.
As the whole project area fall in the
Chakbandi of Bait Cheen Wala Minor and
The Sponsor have made the provision of item borrowpit
consists of fertile agricultural land, so 1.00
excavation lead 1.0 & 2.0 miles for earth filling for
ix mile and 2.00 mile lead provided is minimum
construction of Cheen Wala flood bund. Sponsor may explore
as per availability of earth and site condition
the nearest borrow area and rationalize the lead.
and duly checked and verified by NESPAK
ADP Consultants.
REPLY OF OBSERVATIONS

Sr.
Observations Reply
No.

The Sponsor have made the borrowed earth for construction Lead is provided as per availability of earth
of bund, which is being transported from 1.0 mile lead which after visiting the whole project area, after
x
should be good one so provision of good earth cover may be vetting and verification of NESPAK ADP
justified. Consultants.

Ploughing and leveling is provided because


the proposed flood bund passes through
The Sponsor is acquiring 78 acres land and crop
fertile agricultural lands. Ploughing and
compensation for 380 acres has been provided while
xi leveling of fields after earth is taken from
ploughing and leveling has been provided for 665 acres.
fields is necessary. Without this, farmers
Sponsor may justify the ploughing and leveling area.
don’t allow to take free of cost earth from
field.

The X-Sections of sloping spurs are showing that the both


This matter is already agreed with the
structures are being constructed in dry conditions and are
consultants that this observation will be
xii solid stone structures. The excavation of river bed under solid
address during the technical sanction of
stone spurs is unjustified. Sponsor may delete the same and
estimate.
similarly adjust the quantities of stone.

As per Manual of Irrigation Practice (MIP


The Sponsor have kept the top level of solid stone spurs
revised 2017, Volume-II), top level of the
xiii higher than the river edge which is not justifiable. Sponsor
sloping stone spur should be kept equal to
may review the proposal.
high flood level i.e. 383.18 for this scheme.
THANKS