PARA WISE COMPLIANCE WITH THE RECOMMENDATIONS OF M&E

ON THE “IMPROVEMENT OF ROAD ALONG CANALS AND DRAINS IN


KHYBER PAKHTUNKHWA. ADP NO: 1293/140540”

SUBHEAD: IMPROVEMENT OF CANAL PATROL ROAD ON DIFFERENT CANALS & DRAINAGE


SYSTEM IN PK-32 (SHAGAI MINOR RD 4000- TO TAIL IN REACHES).

FINDINGS, OBSERVATIONS, ANALYSIS & RECOMMENDATIONS BY M&E AND


COMPLIANCE BY SWABI IRRIGATION DIVISION-1
S.No Observations/Findings by DMO Mardan Compliance by Swabi irrigation
Division-1, Swabi
1 The road was found damaged at some The scheme has been completed on
portion at Shagai minor RD: 4000 to tail. 31.05.2016. A small patch /
It shows poor execution by the Irrigation damaged portion as mentioned by
M&E office resulted in previous
Division Swabi. heavy flood in Shagai Nullah. The
department taken hands its
restoration / rectification by
Contractor shortly. The same can
be verified by M&E in its follow-up
visits please. Pictures are attached
for ready reference.
PARA WISE COMPLIANCE WITH THE RECOMMENDATIONS OF M&E
ON THE “IMPROVEMENT AND CONSTRUCTION OF IRRIGATION
FACILITIES I.E FPWS, CANAL PATROL ROADS AND DRAINS IN U/C
CHAKNODA, SHEIKH JANA, KSK, ASOTA, PARMOLI, SHEWA,
NARANJI, KALU KHAN, ADEENA, TURLANDI AND TARAKAI SWABI
ADP NO: 2278/190474”

SUBHEAD-1: REVAMPING AND CONSTRUCTION/IMPROVEMENT OF FLOOD PROTECTION WORK


ALONG SHAGAI NULLAH & ITS TRIBUTARIES FOR THE PROTECTION OF
AGRICULTURAL LANDS AND VILLAGE ABADIES IN U/C TURLANDI, VILLAGE
DAGAI, VILLAGE YAR HUSSAIN AND VILLAGE TARAKAI ADJOINING AREAS OF
DISTRICT SWABI
SUBHEAD-2: REVAMPING AND CONSTRUCTION/IMPROVEMENT OF FLOOD PROTECTION WORK
ALONG NARNAJI NULLAH & ITS TRIBUTARIES FOR THE PROTECTION OF
AGRICULTURAL LANDS AND VILLAGE ABADIES AT VILLAGE ISMAILA U/C ADINA,
U/C KARNAL SHER KILLI DISTRICT SWABI

FINDINGS, OBSERVATIONS, ANALYSIS & RECOMMENDATIONS BY M&E AND


COMPLIANCE BY SWABI IRRIGATION DIVISION-1
S.No Observations/Findings by DMO Compliance by Swabi
Mardan irrigation Division-1, Swabi
1 Pace of work was observed slow. Scheme The observations raised by the
already resulted in time overrun. M&E team is true. However,
due to financial constraints the
scheme over run. Contractor is
onboard for accelerating the
pace of work, please.
2 Work stopped on the schemes by the Same as above, subjected to
contractor due to lack of funds release of fund however
contractor is directed to gear
up construction activities at
site and accelerate the pace of
work.
PARA WISE COMPLIANCE WITH THE RECOMMENDATIONS OF M&E
ON THE “OPERATION & MAINTENANCE OF IRRIGATION CANALS,
T/WELLS, DUG WELLS, LIFT IRR: SCHEMES, FLOOD AND DRAINAGE
INFRASTRUCTURES OF SWABI IRRIGATION DIVISION-I SWABI
DURING 2022-23”

SUBHEAD-1: SILT CLEARANCE OF KALU KHAN DISTY AND ITS SUB SYSTEM FROM RD: 00-TAIL
IN REACHES.

SUBHEAD-2: SILT CLEARANCE OF NAWAN KILLI MINOR & SARBANDI MINOR RD: 00-TAIL IN
REACHES.

FINDINGS, OBSERVATIONS, ANALYSIS & RECOMMENDATIONS BY M&E AND


COMPLIANCE BY SWABI IRRIGATION DIVISION-1
S.No Observations/Findings by DMO Compliance by Swabi
Mardan Irrigation Division-1, Swabi
1 Pace of work was observed slow. Progress achieved and work
completed at site
2 Silt was deposed of in nearby plot On own request of land owner the
among houses that could cause dust a silt has been dumped in nearly by
spared infection in dry season open plot / land. Silty soil is
usually more fertile than other
type of soils, meaning it is good
for growing crops. The same has
been allowed for leveling and
filling of low-lying areas to avoid
standing of rain water.
3 De-siltation of Nawa killi Minor, True up to the extent that the
Shagai Minor and Sarbandi Minor were activity was carried out manually
carried out manually and was dumped but the same has been removed
along the banks of Minor which may from canal side banks and
slide again to the canal minors dispose off.
4 The Irrigation did not share the MB The quantity of work has been
book with the M&E team to quantify assured by the field formation of
the work carried out at site absence of Irrigation staff regular visited by
MB makes the execution of work Superintending Engineer Swabi
questionable regarding quantum of silt circle also by the silt monitoring
removed from the minors team. MBs, Estimates and
Agreements are ready for
submission to M&E team for
compliance please.