Professional Documents
Culture Documents
Ministry of Agriculture
DEC, 2021
1|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
Summary
The livelihood, infrastructure and service subprojects to be implemented under the DRSLP-I are
likely to deliver significant social benefits, provided that they are planned in an inclusive
manner, and they are designed to ensure a distribution of benefits to vulnerable groups including
the old, youth, women, and the poor.
It is anticipated that implementation of the DRSLP-I for beneficial communities for it was bring
about improvements in livelihoods and in areas of access to basic services such as water, feeder
road, PTC, livestock market, and strengthen regional laboratory for livestock health
improvement. Degraded landscape rehabilitation through physical and biological conservation
structures (bunds, terraces, trenches, diversion canals, etc...), afforestation and reforestation on
communal and private lands have environmental and social benefits as well. Introduction of
sound natural resource management practices (including rangeland) have their own positive
impacts in the targeted areas and beyond.
Some of the project interventions have some localized but less sensitive, site specific and
perhaps reversible environmental impacts by developing ESMP. In some cases, there may be
risks of permanent or economic displacement of people, requiring a carefully planned and
implemented RAP. Some land acquisition or restriction of access include the following: rural
feeder roads; small and micro dams, water supply (ponds, shallow wells, cisterns, water pipe line
extension, spring development); rangeland management; livelihood diversification enterprises
(IGA).
Sub-projects were screened for the possible environmental and social impacts and appropriate
mitigation measures have been developed. The implementation of sub projects is expected to
fulfill the safeguard policies requirements stipulated in the ESMF, RMP, ESMP documents
prepared for this project. The staff assigned to implement the sub-projects at the grass root level
and communities receive training on social and environmental issues in order to properly
implement the safeguard policies and also carry out proper monitoring.
It was agreed to require reports with specific information provided on the status of
implementation of each ESMPs prepared on each subproject progress. The currently quarter
report is expected to be summarized to the Bank by 15 Jan, 2022.
Overall, the current status of environmental and social compliance report and mitigation
measures that has been implemented in compliance with DRSLP I in both Regions (part A-
Somali and part B- Afar), the proposed mitigation measures described in the Environmental and
social Management Plan (ESMP) (implemented, ongoing or none) and matrix of challenges and
action to be taken within each region presented below table.
2|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
A. Environmental and social safeguard Compliance Reporting Format
Ministry: -------MoA----------Region: Somali
Program/Project Type; (DRSLP I)
Type of Location
Qua Implementa
Sub ES Identified Mitigation measure
Wored rter taken to reverse
tion of
projects/A Zone Kebele MP impacts mitigation
a year
ctivities measure,
Component 1: Natural Resource Management
2021 Swamp
the pavement area
around the troughs and
around
Ararso water points at least 5 Completed
new trough &
m in each side
WP
borehole Jarar Waryugle constructed
new 2021 Soil Erosion SWC on the upper side Ongoing
Ararso Garbadinle
borehole Jarar of the BH
2021 the pavement area Completed
Swamp
around the troughs and
around
Ararso Dintaab water points at least 5
new trough &
m in each side
WP
borehole Jarar constructed
2021 Sedimentation Undertake tree planting Continuous
, and soil & water
Birkot Sankadane Clean dust
new conservation activities
from the solar
borehole Jarar panel in the catchment;
new 2021
Birkot Elhar Land of lowest value Completed
borehole Jarar
new Kora 2021 Land (non-cultivable and not
k/dahar Elhar used for grazing) should Completed
borehole hay Acquisition by
be allocated for the
new Kora 2021 Construction of
Marsin Gabo gabo Camp Sites and contractor’s camp and Completed
borehole hay quarry sites as much as
Reservoirs
new Kora 2021 possible;
Marsin Weylaguhid Completed
borehole hay
3|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
new 2021
Goljano Kodahle Completed
borehole Fafen
new 2021
Goljano Anane Completed
borehole fafen
new 2021
Goljano Dalatowga Completed
borehole Fafen
new 2021
Kubi Gara Completed
borehole Erar All the contractors’
new 2021 facilities should require
Hadagala Biyogara best practice management Completed
borehole Sitti
in terms of site
new 2021
Hadagala Harisa cleanliness, waste Completed
borehole Sitti
disposal and social
new 2021
management;
Sitti Hadagala Hore Completed
borehole
2021 Siltation Silt trap and SWC
Dawa Mubarek/ Hawan Completed
new ponds problem in catchment
2021 Siltation Silt trap and SWC
Dawa Mubarek/ Wal-walo Completed
new ponds problem in catchment
Dawa Mubarek/ Jare 2021
Completed
new ponds Siltation Silt trap and SWC
2021 problem in catchment
Dawa Mubarek/ Mubarek 02 Completed
new ponds
Borehole 2021
The contract
Rehabilitatio Fafan Goljano 01 kabale
is terminated
n
Borehole 2021 Open for Fencing to protect and
Rehabilitatio Sitti Hadagala 01 kabale human and repair by local completed,
n livestock Materials
2021
Flood
Protection from the completed,
problem from
flood by local material
Hand Dug Well Sitti Hadigala Waruf/ the river
Koraha Kebrideha 2021 Erosion completed,
SWC structures
Hand Dug Well y r/ Lasdarkele problem
2021 Siltation & Reduce silt by swc and completed,
Pond Jarar Ararso Waryugle/ lack of fence fencing
4|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
2021 Siltation
Reducing silt completed,
protecting catchment
problem
Pond Erer Kubbi Garaa/ area
2021 Siltation
Reducing silt completed,
protecting catchment
problem
Pond Erer Kubbi Fookdeer/ area
2021 Siltation
Reducing silt completed,
protecting catchment
problem
Pond Erer Kubbi Washako/ area
2021 The upper micro- completed,
catchment side
draining into the Birka,
Siltation
which is estimated to
problem
be about 5 ha, treat by
Koreha physical treatment like
Birka y Marsin Marsin/ level stone terraces
Koreha 2021 Siltation Construction of silt completed,
Birka y Marsin Nusdarik/ problem trap and cleaning
Koreha kabridaha 2021 Siltation Construction of silt completed,
Birka y r Maraato/ problem trap and cleaning
2021 About 10 hectares to completed,
be treated by level
Siltation stone terraces that
problem assist the water shed to
retain some of the soil
Birka Jarar Birkot/ Husaale erosion.
2021 Unprotected
Fencing to protect completed,
and maintain in
from livestock
time from the local
etc
Birka Dawa Mubarek/ War-walo materials
2021 SWC about 200m completed,
length on both flood
Siltation water entrance sides to
problem reduce the siltation
problems.
Birka Jarar Ararso Mooyaha
Birka Jarar Birkot/ Gomaar 2021 Lack of Upper catchment land Continuous
fence and is treated by hillside
siltation stone terraces &
5|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
fenced.
2021 Check dams of single completed,
brushwood types with
Siltation stone check dams
along the flood’s inlet
Birka Jarar Birkot/ Hilay directions constructed
2021 Stone check dames/or completed,
brush wood check
Siltation dams on (200m on
problem about five spots) along
Koraha the gentle slope of
Birka y Marsin Gabogabo these foot paths
2021 Check dams of single completed,
brushwood along the
Siltation
Koraha flood’s inlet directions
Birka y Marsin Weylaguhid constructed
2021 The strengthened the completed,
Weak fence using similar
fence & locally available
unprotect materials and
ed from constructed a cattle
livestock trough with size of
Koraha etc 4m*.50m*.30m size
Birka y Marsin Iskudonle outside the fence
2021 Swamp
the pavement area completed,
around the troughs and
around
water points at least 2
trough &
Koreha kabridaha m in each side
WP
Borehole y r Galdid constructed
2021 Open for completed,
livestock
Fencing an protect
and
Borehole Afder Raaso Raso/ human
2021 Open for completed,
livestock
Fencing an protect
and
Borehole 1 Dawa Mubarek/ Bidiru/ human
2021 Open for completed,
Fencing an protect
Borehole 2 Dawa Mubarek/ Ceenyabo livestock
6|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
and
human
Component 2: Market and Livestock Infrastructures
7|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
* Provide incinerator
Kebridahar 2021
Korah Kebridaha * * Construct market completed,
Town - 01 Environmenta toilets (separated
ay r
Kebele
l pollution between man and
2021 from market woman) completed,
Rehabilitatio waste
* Provide awareness
n of existing
LMC Cobosha * Hygiene and creation training on
Fafan Babile sanitation Sanitation
Kebele
problems * Providing proper
waste disposal and
sewerage facility
8|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
2021 completed,
Sitti Hadagala hadagalla
9|Page
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
B. Environmental and social safeguard Compliance Reporting Format
Ministry: -------MoA----------Region: Afar
Program/Project Type; (DRSLP I)
Location Qu
art Mitigation Implementati
Type of Sub
er/ Identified measure on of
projects/Activi Zon Wored Kebel Yr
ESMP impacts taken to mitigation
ties e a e 20 reverse measure
21
Component 1: Natural Resource Management
Woranso None
No mitigation
Borehole 420m Adaar and There is no impact
measure
hormati
No mitigation None
Borehole 450m Adaar Jeldi There is no impact
measure
No mitigation None
Borehole 362m Adaar Burka There is no impact
measure
Maintenance hand No mitigation None
Adaar Burka There is no impact
pump measure
Maintenance hand No mitigation None
Adaar Burka There is no impact
pump measure
Maintenance hand No mitigation None
Adaar Jeldi There is no impact
pump measure
Establish
Closing of rural road alternative
Micro dam Elidaar Suula between community access road Completed
and kebele for the
community
No mitigation None
Bor holle Elidaar Gewahe There is no impact
measure
No mitigation None
Bor holle Elidaar Elidaar There is no impact
measure
No mitigation None
Bireka Elidaar Elidaar There is no impact
measure
10 | P a g e
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
No mitigation None
Bireka Elidaar Suula There is no impact
measure
No mitigation None
Bireka Elidaar Manda There is no impact
measure
Water pipeline No mitigation None
Elidaar Suula There is no impact
distribution measure
No mitigation None
Borehole Erepti Albo There is no impact
measure
Erepti Anderg No mitigation None
Borehole There is no impact
alo measure
Erepti No mitigation None
Borehole Fi’ad There is no impact
measure
Erepti Fence round Completed
Contamination of
Pond Adu the pond,
water, silt deposition
clean silt trap
Erepti Fence round Completed
Contamination of
Pond Adu the pond,
water, silt deposition
clean silt trap
No mitigation None
Bore hole Hdelela Aftoha There is no impact
measure
Abake No mitigation None
Irrigation canal Hdelela There is no impact
bera measure
namagu No mitigation
Borehole Afdera There is no impact None
bi measure
Component 2: Market and Livestock Infrastructures
Construction of new Medical waste, solid
Animal Health Posts Siylu
waste such as Burn in time Completed and
Adaar and accumulation of by incinerator continuous
woki
paper
Service Completed and
Medical waste, continuous
schedules and
Adaar Burka increments of
burn within
livestock on area
incinerator
Erepti underga Weed invasive, Remove the Completed and
lo medical wastes weed, burn continuous
within
incinerator
11 | P a g e
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
Remove the Completed and
Weed invasive, weed, burn continuous
Hadelela Leleda medical wastes within
incinerator
Service Completed and
Medical waste, continuous
schedules and
Geloalo Diyara increments of
burn within
livestock on area
incinerator
Medical waste, solid Completed and
kusura waste such as Burn in time continuous
Afdera
wad
accumulation of by incinerator
paper
Construction of Weed invasive Remove
new PTCs problem, no water weed in time Ongoing and
Adaar Burka for demonstration and collect continuous
water for roof
Weed invasive Remove Completed
problem, scarcity of weed in time
Adaar Adaar water and collect
water for roof
Weed invasive Remove Completed
problem, scarcity of weed in time
Elidaar suulla water and collect
water for roof
Erepti Weed invasive Remove Ongoing and
problem, scarcity of weed in time continuous
Albo water and collect
water for roof
Erepti Weed invasive Remove Ongoing and
problem, scarcity of weed in time continuous
Erupt water and collect
water for roof
Weed invasive Remove Ongoing and
problem, scarcity of weed in time continuous
Hdelela Aftoha water and collect
water for roof
Hdelela Abake Weed invasive Remove Ongoing and
ber problem, scarcity of weed in time continuous
water and collect
12 | P a g e
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
water for roof
Weed invasive Remove Completed
kusura problem, scarcity of weed in time
Afdera
wad
water and collect
water for roof
Weed invasive Remove Ongoing and
problem, scarcity of weed in time continuous
Afdera Ayitura water and collect
water for roof
Burn within
Solid and Medical incinerator,
Animal health
Afdera Ayitura wastes, increments service Completed
center of livestock schedule
mode
Absence of drainage
structures in Flood
Construction of Su’ula- significant places of diversion is
Elidaar Completed
feeder road karbilo the road done through
Flood on road edge gabion work
and bridges. by WPCU
Bridge with 4 km Edaforo
Side ditch filled by Remove from
feeder road under Geloalo to silt the ditch
Ongoing
construction Subuli
Construction of Solid waste
Waste
new LMC disposal and
Hdelela Hdelela accumulation, lack
connect water
None
of water supply
to point line
Repair and
Shade roof has
Erebti replace wind-
Adu partially taken by
blown roof
None
wind.
part
Waste Ongoing and
Solid waste
accumulation
disposed and continues
Elidaar Elidaar cleared action
Afdera Afdera The market shade Repair and Ongoing and
roof partially taken replace wind- continues
by the wind. blown roof action
part
Solid waste Waste
13 | P a g e
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
disposed and
accumulation
cleared
Range land management
14 | P a g e
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
Note; On the above table fill the Implementation of mitigation measure, the current status of mitigation measure to overcome the
outstanding issues by (completed, ongoing or none) and minute related to the peace keeping agreement.
15 | P a g e
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021
Matrix of all the key challenges within DRSLP I both regions for E&S identified with possible actions
16 | P a g e
Current status of E &S compliance Report with its challenges DRSLP-I, Dec, 2021