Professional Documents
Culture Documents
Energy Uplift: Sudan hydro facilities can more than double plant
factors and result in huge economic benefit
Turbines:11x400MW
+2x375MW
5150MW (planned)
Annual generation
15692GWh(planned)
Filling Schedule: (4-7 years filling plan) • The repeated narrative of Egypt and Sudan that Ethiopia
unilaterally filled the dam in the rainy season of 2020 is not true.
Stage-based filling plan formulated by National Independent The three countries have agreed that the stage-based construction
Scientific Research Group (NISRG) composed of 5 experts from each of the dam is inseparable from the staged based filling according
of the three countries of Egypt, Ethiopia and Sudan. to Principle 5 of the DoP. The three countries have also agreed on
the schedule of filling and there is no requirement for additional
agreement. The second phase filling retaining additional 13.5BCM
will proceed in July and August of 2021 accordingly.
5. CONSULTATION PROCESSES & CHALLENGES • The Sudanese modeling team, which includes the current water
Affairs minister of Sudan, conformed that the filling of GERD in July
Phase 1: International Panel of Experts (May 2012-May 2013)
and August will have no impact for any of Water supply and
Established in May 2012 and submitted its report in May 2013
management of Sudan. GERD fulfills all safety standards and is
appreciated by the experts of the two downstream countries.
Phase 2: Tripartite National Committee 2013-2016 (DOP 2015) 12
members; 4 members from each of the three countries established
by water affairs ministers
7. WAY FORWARD
Phase 3- Nine ministers party and national scientific research group
(2017-2018) Submission of filling and operation plan by Ethiopia Ethiopia respects the agreement on Declaration of Principles (DOP)
[2017]; Establishment of NISRG [15 members 5 from each of the and is also committed to conclude the trilateral negotiation under
three countries]; Submission of study results to water affairs the auspices of the African Union. The GERDP is financed by the
ministers in September 2018 [Egypt refused to accept the people and government of Ethiopia for the benefit of Ethiopians and
recommendations of the NISRG]; Egypt submitted on 1st August 2019 the region. Unfair claim of the entire Nile water, and protecting the
new proposal-rejected by Ethiopia and later Egypt withdrew its unfair status quo caused significant harm on Ethiopia’s quest for
proposal. development. Ethiopia negotiates for equitable and reasonable
utilization without causing significant harm to its downstream
Phase 4: Third Party Involvement (Nov. 2019-Feb. 2020)-12 meetings neighbours.
Egypt appealed at the 74th UN GA for the involvement of the
international community; Egypt Requested the US and the WB to
mediate, Ethiopia accepted to participate on condition US & WB 640 FSL
participate as observers
• Sudan’s claim that the first stage filling causes risk to its
population is not substantiated. To the contrary GERD protected
the Sudanese population from more floods of 2020 and in future
provides more resilient and flood managed Sudan.