Professional Documents
Culture Documents
DEVELOPMENT CORPORATION
FEASIBILITY REPORT
JANUARY 2017
CHILLING-BASGO HEP Feasibility Report
CHAPTER-1
EXECUTIVE SUMMARY
1 CHAPTER-1:EXECUTIVE SUMMARY
1.0 Introduction
a 26 m high diversion dam across River Zanskar with FPL of 3150 & DSL at
3149.80 masl
a head-race tunnel of Modified Horse shoe, 4.8 m dia, 6.40 km long.
Pressure shaft of dia 4.0 m, 200 m long and penstocks of 2.0 m dia 3Nos of
50m each in length.
a semi-underground power house having an installation of 3 nos vertical shaft
Francis turbines, each unit having generation capacity of 8 MW each under
rated net head of 45 m.
a tail-race channel of rectangular shape and size 12X2.10m , 60m long.
The salient features of the project are given at Annex-1.1 and layout map at Drawing 3.
1.2 Hydrology
The river Zanskar drains a catchment area of about 15946 sq. km at proposed
diversion site. Approved discharge data for Nimoo-Bazgo HEP which is 11 km
downstream of Indus-Zanskar confluence (1977-2016) has been used for water
availability study. The average 10-daily water availability series at Chilling-Basgo H.E.
Project has been estimated from the above data by co-relation of observed data at
proposed site and Alchi. The design flood for 25 year return period and Standard Project
Flood(SPF) are estimated by statistical approach based on the observed maximum flood
peaks at Alchi and has been transposed to Chilling-Basgo diversion site using Deccons
formula. The design flood adopted so is 1400 cumec for SPF for spillway design. The
diversion flood ( 1 in 25 years) adopted is 850 cumec.
The Power potential studies of Chilling-Basgo HE Project has been made for 90%
dependable year based on 29 hydrological years, from 1977 to 2016. An installation of 24
MW comprising of 3 generating units of 8 MW each has been proposed in the first stage.
Annual energy generation at 24 MW with 95% machine dependability comes out to be
143.20 MU
The Power generated from the project is proposed to be distributed in the local
network as this area is power starved. In future, the excess power will be evacuated by
connecting to the transmission network passing through Leh via Kargil, Alistong-Srinagar
any other alternative route viable.
The project cost is Rs. 323.40 crores including IDC at January, 2017 price level.
The preliminary estimate has been prepared as per the guidelines of CEA/ CWC. The
breakdown of the cost estimate is given below.
1.9 Conclusion
ANNEXURE-1
CHILLING-BASGO HE PROJECT (3X8=24MW)
LOCATION
State : Jammu & Kashmir
District : Leh
River : Zanskar River/Indus
Diversion site : Downstream of Chilling village
Latitude : 3407'45.5"N
Longitude : 7714'32"E
Power House site : Opposite Bank of Bazgo Village
Latitude : 3411'19"N
Longitude : 7715'25"E
Nearest rail head : Jammu/Kiratpur
Nearest airport : Leh
HYDROLOGY
Catchment area : 15946 sq km
Location of catchment
Latitude : 32o 32' 12 to 34o 09 '43" N
Longitude : 76o 13' 11" to 78o 01 '30 E
Annual Yield in 90% dependable year : 2500 MCM
Average discharge in 90% dependable year : 79.29 m3/s
Annual average Yield : 3496 MCM
Annual average discharge : 110.86 m3/s
Flood discharge for river diversion (~Q25) : 850 m3/s
Design Flood for waterway (100 yr RP) : 1050 m3/s
Design flood for freeboard (SPF) : 1400 m3/s
DIVERSION STRUCTURE
Type : RCC Dam & Embankment
Top elevation of Dam : 3153 masl
Height of dam above Mean Bed Level : 26 m
Mean Bed Level : 3127 m asl
Length of dam including NOF, Embankment : 100 m
PONDAGE
Full Pond level (FPL) : 3150 m asl
Maximum water level (MWL) : 3150 m asl (SPF 1400cumec)
Dead Storage Level(DSL) : 3146.85 m asl
Gross storage
-at FPL : 4.70 MCM
-at DSL : 3.70 MCM
Pondage : 1.00 MCM
Area under Submergence at FRL : 41.95 ha
Normal Tail water level (TWL-PH) : 3094 m asl
SPILLWAY
Design flood (SPF) : 1400 cumecs
Design flood Level : 3131.30 m asl (TWL at Dam site)
Type : Orifice
Crest elevation : 3136.50 m asl
Top of spillway gate : 3144.50 m asl
Number & size of spillway opening : 4 Nos, 5.5 m X 8 m
Thickness spillway Pier : 7m
Length of spillway : 30.550 m (including pier)
Bucket Radius : 10 m
RIVER DIVERSION
Diversion flood : 850 cumec
Location : Right Bank
Top of upstream cofferdam : 3133.80 m asl
Top of downstream cofferdam : 3132.80 m asl
Size of Diversion Channel : Trapezoidal, bed width 16 m
Depth of flow : 3.60m
Side slopes : 1 H : 1.25 V
Length of diversion channel : 350m (c/l)
INTAKE
Crest level : 3142.50m asl
Number of gates : Two
Size of gate opening : 3.0m X 3.5m
Trash rack : Inclined type
Design discharge : 58.46 cumec
INTAKE TUNNEL
No. of Intake Tunnels : Two
Size of Intake Tunnel : 3.5 m
Invert level of tunnel : 3142.50 m
Design discharge : 58.46 cumec
Design Velocity : 3.04 m/s
HEAD-RACE TUNNEL
Excavated Shape : Modified Horse Shoe
Finished dia : 4.8 m Circular
Number : One
Length : 6.40 km
Velocity for normal discharge : 3.06 m/s
Design discharge : 58.46 cumec.
Thickness of concrete lining : 0.30 m
Invert level at the start of HRT: 3141.20 m asl.
SURGE SHAFT
No. & type : One No closed with Restricted Orifice
Diameter : 18.0 m
Vertical Shaft height : 30 m
Top Level : EL 3163 m
Bottom Level : EL 3138 m
Maximum up surge level : EL 3161.86 m asl
Minimum down surge level : EL 3140.96 m asl
PRESSURE SHAFT
Internal dia : 4.00m
Number : 1 NO
Length : 200 m
Shape : Circular
Velocity for normal discharge : 4.65 m/s
Design discharge : 58.46 cumec.
PENSTOCK (MANIFOLD)
Internal dia : 2m
Number : 3 No
Length : 50 m
Shape : Circular
Velocity for normal discharge : 6.9 m/s
Design discharge per each unit : 19.50 cumec
POWER HOUSE
Type : Semi-Under ground power house
Size of Machine Hall : 36(L)mX 18 (W)mX30 (H)m
Size of service bay : 12 m X 18 m
Installed capacity : 24 MW
Number of units : 3 Nos
Type of turbine : Vertical Francis
Turbine Axis Elevation : 3091.00 m asl
Maximum gross head : 56 m
Rated net head : 45 m
TAIL-RACE CHANNEL
Shape : Rectangular
Bed width & Depth of flow : 12X1.94m
Free board : 0.75
Length : 60m
Velocity for normal discharge : 2.31 m/s
Design discharge : 58.46 cumec.
Thickness of concrete lining : 0.30 m
ESTIMATED COST
Civil Works (including other works) (in crores) 63.60
Power Plant Civil works (in crores) 95.92
Electro-mechanical Works (in crores) 104.20
Total basic cost (in crores) 263.72
Interest During Construction (IDC) (in crores) 59.68
Total Project Cost (in crores) 323.40
Cost per MW installed (in crores) 13.47
POWER BENIFITS
Installed capacity MW 24 (3X8MW)
90% dep. energy GWh 148.33
90% dep. Energy with 95% plant availability GWh 143.20
Plant Load Factor 70.60 %
TARIFF
Initial : 5.05 /unit
Levelised : 4.40/unit
CONSTRUCTION PERIOD
Construction Period Months 60
(Including pre construction activities)