Professional Documents
Culture Documents
Introduction
Govt of UP has entrusted implementation of 24 MW Dhukwan Small Hydro
Project to THDCIL. Project is located near village Sukhwan-Dhukwan in Tehsil
Babina, in Jhansi district of Uttar Pradesh on river Betwa. Implementation
agreement was signed between GOUP and THDCIL on 2nd Sep09.
The construction to be under taken shall comprise of () 1433m long head race
channel, 4nos of RCC Intake barrels, Forebay, Penstock three numbers of 4.0 m
dia each, Surface Power house with three units of 8 MW capacity vertical
Kaplan turbine and a () 961m long Tail race Channel.. The estimated
generation from this project at 46.53% load factor is 97.82 Million units.
The project does not involve any R&R works. 39 Ha forest land is required for
Project works. Stage-I Forest clearance for the same has been accorded by
MoEF on 27.11.12. Final(2nd Stage) Forest diversion has been cleared by
Central Nodal Forest Officer, Lucknow and letter has been sent to Principal
Secretary (Forest), Govt of UP on 17th Sep-13for further necessary action. The
project can be implemented within a time period of approx. 30months.
F.S.L. : 273.70m
Shape : Trapezoidal
F.S.L. : 273.50 m
Forebay : 145.40 X 39 m
Length : 63 m
Power House : 64 x 25 m
No. Of Machines : 03
Capacity : 8 x 3 = 24 MW
Shape : Trapezoidal
Shape : Trapezoidal
Switchyard : 11/132 kV
No. of Bays : 3
Infrastructural works
Office Building
Field Hostel
15.1 GENERAL
a. The HRC will be constructed, partially with the excavated material and
balance from the borrowed material from the near by borrow area. The
quantities from excavation of different structures like, approach channel,
Penstock, Power House etc will be used for filling for HRC. Therefore, the
lead has been considered 2.00 Km for the item of common excavation of
these structures.
b. Rates for various components of civil structures have been adopted on the
basis of CWC guidelines and prevailing market price for the items which
are not included in the schedule. The worked out rates of civil works are
given in part III of this volume.
ii. Audit and accounts charges at the rate of 1 percent of the cost
of works.
iii. Losses on stock at the rate of 0.25 percent of the cost of civil
works.
d. Cost of electromechanical units including generator and control panels etc.
and cost of other equipments such as switchyard equipment, crane,
ventilation system equipment etc have been arrived at by escalating the
cost of equipment mentioned in Dhukwan DPR of May 2004 up to March
2010.
e. Duties, taxes, freight and insurance charges have been included in the
cost of electro-mechanical equipment. The estimates include inspection,
erection and commissioning charges, losses on stock and maintenance
during construction.
I WORKS
A. Preliminary 133.00
B. Land 81.39
C - Civil works 1003.13
J- Power Plant 8681.79
K. Buildings 547.14
M. Plantation 20.00
O. Miscellaneous 323.70
R. Communication 147.05
S-Power Plant 5110.60
Q. Special T&P 30.87
X. Environment & Ecology 523.24
P. Maintenance during construction 105.11
Y. Losses on stock 26.28
ESTABLISHMENT
IV SUSPENSE 0.00
INDIRECT CHARGES
IDC 1289.00
1 Working on Payroll
Payroll is the process by which employers pay an employee for the work they have
done. Any business with employees should have a payroll established. Although,
payroll seems like a mundane task, it involves many aspects including,
Withholding taxes from each paycheck and making sure accurate funds are paid to the
correct government agency
Provident Fund
GSLI
Interest on HBA