You are on page 1of 15

DHUKWAN SHP

Introduction
Govt of UP has entrusted implementation of 24 MW Dhukwan Small Hydro
Project to THDCIL. Project is located near village Sukhwan-Dhukwan in Tehsil
Babina, in Jhansi district of Uttar Pradesh on river Betwa. Implementation
agreement was signed between GOUP and THDCIL on 2nd Sep09.

Project is about 37 Km from Jhansi on Jhansi-Lalitpur road. The nearest rail


head is Jhansi. The project site falls in the survey of India toposheet No. 54
K/12/NW and is connected with all weather metalled road. The geographical
co-ordinates of the project site are latitude 25012 E and longitude 780 33 N.

The project as envisaged in DPR prepared by THDC India limited is of 24 MW


capacity, utilizing the storage of existing reservoir of Dhukwan masonry cum
Earthen Dam. The length of the Dam is 2972 m. The gross capacity of the
existing reservoir is 5780 MCum with top F.S.L. 273.7 m.

The construction to be under taken shall comprise of () 1433m long head race
channel, 4nos of RCC Intake barrels, Forebay, Penstock three numbers of 4.0 m
dia each, Surface Power house with three units of 8 MW capacity vertical
Kaplan turbine and a () 961m long Tail race Channel.. The estimated
generation from this project at 46.53% load factor is 97.82 Million units.

The project does not involve any R&R works. 39 Ha forest land is required for
Project works. Stage-I Forest clearance for the same has been accorded by
MoEF on 27.11.12. Final(2nd Stage) Forest diversion has been cleared by
Central Nodal Forest Officer, Lucknow and letter has been sent to Principal
Secretary (Forest), Govt of UP on 17th Sep-13for further necessary action. The
project can be implemented within a time period of approx. 30months.

Investment approval of the project has been accorded by THDCIL Board at an


estimated cost of ` 195.42 Cr including IDC of ` 12.89 Cr in Mar, 2011 at
April, 2010 PL. Equity portion i.e. 30% of the Project cost shall be funded by
the Corporation from its internal resources.
A VIEW OF DHUKWAN DAM

DHUKWAN DAM AND ITS RESERVOIR


ROAD TO VILLAGE BIRDHA AT THE DOWNSTREAM OF DAM

GATES OF DHUKWAN DAM


BACKGROUD OF DHUKWAN SHEP

Government of Uttar Pradesh allotted Dhukwan HEP on Betwa River to


THDCIL for DPR updation& implementation of this Project. An
Implementation Agreement was signed on 02 September 2009 between
GOUP & THDCIL.

The Dhukwan Hydro Power Scheme is proposed in the Down Stream of


already existing Dhukwan Reservoir on River Betwa.

Dhukwan reservoir was created in year 1907 by the Britishers by


constructing Dhukwan masonry cum earthen dam on River Betwa near
Babina in Jhansi District about 37 Km away from Jhansi .

Matatila Dam & Reservoir is located up stream of Dhukwan Reservoir


&Parichha Dam is located Downstream of Dhukwan Dam.

There is about 51 meter drop between Dhukwan&Parichha Dam in Betwa


River. Surplus water available in Dhukwan reservoir is released but this
drop is still unutilized.
SALIENT FEATURE OF DHUKWAN HEP

Dam & Reservoir (Existing)

Catchment Area : 21, 34, 160Ha

Gross Capacity : 5780 MCM

F.S.L. : 273.70m

Top Level : 277.00m

Length of Masonry : 1172m

Length of Earthen Dam : 1800m

Submergence Area : 1943m

Design Discharge of Spillway : 15,260 Cumecs

Dhukwan SHP at Down Stream of the Existing Dam

Approach Channel in Reservoir Area : 502.38 m Length,

Bed level : 264.50m

Concrete Barrels at Intake : 4 Nos.

4.5m(w) X 5.5 m (h)

Head Race Channel : 1451.46 m

Design Discharge : 180 Cumec

Shape : Trapezoidal

Bed Level : 265.50 m

F.S.L. : 273.50 m

Forebay : 145.40 X 39 m

Storage Capacity : 19200 Cum


Penstock : 3 Nos. 4m dia

Length : 63 m

Power House : 64 x 25 m

Gross Head : 20.60 m

No. Of Machines : 03

Type of machine : Kaplan

Capacity : 8 x 3 = 24 MW

Spill Channel : 383.83 m (L)

Shape : Trapezoidal

Tail Race Channel : 919.33 m

Shape : Trapezoidal

Cross Drainage Works : Nala Portions

Switchyard : 11/132 kV

No. of Bays : 3

Annual Energy Generation: 97.82 Million Units

(At 46.53% load factor)

Total Cost of the Project : 183.72 Crores (2010 PL)

(Including IDC & Subsidy)

Cost per MW : 7.65 Crores

Generation Cost Per KW: Rs. 3.63

Construction Period : 30 Month

Dhukwan SHEP (Civil Works)


Name of work: Civil works of Dhukwan Hydro Electric
Project (3X8 MW

Contractors Name: M/s SEW Infrastructure Limited, Hyderabad

Value of Work : INR 94.93 Cr

Schedule Date of Start:30.11.2014

Schedule Date of Completion:31st May2017 (30 Months)

Hydro Mechnical works

Name of Contractor- M/s Aarti Infra Projects Pvt. Ltd., Nagpur

Value of Work : INR 9.41 Cr (Supply) & INR 1.83 Cr(Services)

Schedule Date of Start: 13.09.2015

Schedule Date of Completion: 14.09.2017 ( 24 Months)

Electro Mechnical works

Name of Contractor- Joint Venture of M/s Hunan Allonward Hydro

Generating Equipment Co. Ltd, China(Lead


Partner)& M/s Shri Saravana Industries Pvt.
Ltd, Trichy .

Value of Work : On shore Supply Portion: INR 42.48 CR

Of shore supply portion: INR 6.54 Cr &

US $ 4293050 Services Portion: INR 4.67 Cr

Schedule Date of Start: Date of Signing of Agreement i.e 29.01.16

Schedule Date of Completion: 25 Months

Infrastructural works

8 Nos Type -II Residence Building


Name of Contractor- M/s Saini Square 2010, New Delhi

Value of Work : INR 84.70 Lacs (Agreement Value)

Schedule Date of Start: 31.03.2015

Schedule Date of Completion: 29.02.2016 ( 11 Months)

Plinth area of each building is 54 SqM.

Office Building

Name of Contractor- M/s Ashish Enterprises , Parichha Jhansi

Value of Work : INR 1.14 Cr (Agreement Value)


Schedule Date of Start: 31.03.2015

Schedule Date of Completion: 29.02.2016 ( 11 Months)

covered area of building is 350 SqM.

Field Hostel

Name of Contractor- M/s Ashish Enterprises , Parichha Jhansi

Value of Work : INR 2.07 Cr (Agreement Value)

Schedule Date of Start: 31.03.2015

Schedule Date of Completion: 29.02.2016 ( 11 Months)

covered area of building is 606 SqM.


COST ESTIMATE

15.1 GENERAL

Cost of the scheme is worked out in sufficient details so as to arrive at


realistic cost estimate. The details of cost abstract are given in part I of
this volume. The cost of civil works is worked out for installation of 3x8
MW. The estimates of quantities for civil works have been prepared and
given in part II of this volume. The basis of working out costs is as below:

a. The HRC will be constructed, partially with the excavated material and
balance from the borrowed material from the near by borrow area. The
quantities from excavation of different structures like, approach channel,
Penstock, Power House etc will be used for filling for HRC. Therefore, the
lead has been considered 2.00 Km for the item of common excavation of
these structures.

b. Rates for various components of civil structures have been adopted on the
basis of CWC guidelines and prevailing market price for the items which
are not included in the schedule. The worked out rates of civil works are
given in part III of this volume.

c. Provisions made for followings as per CWC / Central Electricity Authority


norms.

i. Establishment charges at the rate of 8% percent of the cost of


Civil works and 6.00% for Electromechanical works.

ii. Audit and accounts charges at the rate of 1 percent of the cost
of works.

iii. Losses on stock at the rate of 0.25 percent of the cost of civil
works.
d. Cost of electromechanical units including generator and control panels etc.
and cost of other equipments such as switchyard equipment, crane,
ventilation system equipment etc have been arrived at by escalating the
cost of equipment mentioned in Dhukwan DPR of May 2004 up to March
2010.
e. Duties, taxes, freight and insurance charges have been included in the
cost of electro-mechanical equipment. The estimates include inspection,
erection and commissioning charges, losses on stock and maintenance
during construction.

15.2 ABSTRACT OF COST

Abstract of item wise cost of civil and electromechanical works is worked


out and given on page 1 of this volume. The estimated hard cost of the
project at April 2010 price level comes out Rs. 182.53 Cr, IDC charges
Rs. 12.89 Cr. and total estimated cost including IDC comes out Rs.
195.42 Cr. A subsidy of Rs. 11.70 Cr. has also been considered, which
makes the net cost of the project as Rs. 183.72 Cr. Cost of installation
works out to Rs. 7.655 Cr. per MW. A detail of all cost analysis is given
in part I of this volume.
ABSTRACT OF COST ESTIMATE
Sl. No. DESCRIPTION AMOUNT Rs. LAKHS

DIRECT CHARGES P.L. APR 10

I WORKS

A. Preliminary 133.00
B. Land 81.39
C - Civil works 1003.13
J- Power Plant 8681.79
K. Buildings 547.14
M. Plantation 20.00
O. Miscellaneous 323.70
R. Communication 147.05
S-Power Plant 5110.60
Q. Special T&P 30.87
X. Environment & Ecology 523.24
P. Maintenance during construction 105.11
Y. Losses on stock 26.28

Total of I - Works 16733.29

ESTABLISHMENT

II (i) Civil 923.30

(ii) E & M 304.60

III TOOLS & PLANTS

(i) Civil (1.0 % of I works) 116.23

(ii) E & M 25.38

IV SUSPENSE 0.00

V RECEIPTS & RECOVERIES -20.52

TOTAL DIRECT CHARGES 18082.29

INDIRECT CHARGES

a Capitalisation of abatement of land revenue 4.07


b i) Audit & Account Charges(Civil) 116.23

ii) E&M 50.77

Total Indirect Charges 171.06

Total Hard Cost 18253.35

IDC 1289.00

TOTAL PROJECT COST 19542.35

Say Rs. (in Crore) 195.42


Financial Learnings at project

1 Working on Payroll
Payroll is the process by which employers pay an employee for the work they have
done. Any business with employees should have a payroll established. Although,
payroll seems like a mundane task, it involves many aspects including,

Determine the proper withholding amount for income tax

Withholding taxes from each paycheck and making sure accurate funds are paid to the
correct government agency

Deduct other required amounts from gross pay

Provident Fund

Voluntary Provident fund

GSLI

Interest on HBA

Payment of Medical Bills

Payment of Tour or Transfer Bills

Payment of Telephone Bills etc.

2 Creating Accounting Entries

3. Payments to the contractors

You might also like