Temporary Drainage
Temporary Drainage
Excavation for storm water path/channel. Excavation for storm water path/channel.
GENERAL NOTES/OBSERVATIONS
1. It was observed that the excavated path was not compacted, hence the soil on the drainage part
is loose.
2. The drainage ring along the path is blocked.
RECOMMENDATIONS
1. The surface of the excavated storm water drainage path should be compacted to prevent rainwater
pushing more sand into the channel.
2. The earth inside the blocked channel should be removed otherwise, it will be a wasted effort.
Yours sincerely,