Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

DEWATERING METHOD STATEMENT FOR

WASTE WATER NETWORK SYSTEM

Doc. Code KRWSS-MS-004

Doc.Revision Rev. 00

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
Page |1
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

Contents
1. INTRODUCTION................................................................................................................................2
1.1 Scope of Works.................................................................................................................................2
1.2 Purpose............................................................................................................................................3
1.3 Key Stakeholders..............................................................................................................................3
1.4 Project Schedule...............................................................................................................................3
1.5 Abbreviations...................................................................................................................................4
1.6 References........................................................................................................................................4
2. PREPARATION..................................................................................................................................5
2.1 Site Investigation..............................................................................................................................5
2.2 Site Mobilization...............................................................................................................................5
2.3 Responsibilities.................................................................................................................................5
2.4 Health and Safety Measures.............................................................................................................7
2.5 Permits and Licenses........................................................................................................................7
2.6 RESPONSIBILITIES.............................................................................................................................8
2.7 METHODOLOGY.........................................................................................................................10
3. INSPECTION.....................................................................................................................................12
4. Handover Procedures.........................................................................................................................13

1. INTRODUCTION

1.1 Scope of Works

UWSCG intends to apply part of the funds to payments under the contract for UWSCG-IPC-CW-
Lot 1: Upgrade of water supply and sewerage systems in Khashuri.
The works for construction activities of water distribution and sewerage network will mainly
include the following features:
Khashuri Water Supply and Sanitation Project
Method Statement for Water Network Crossings
Page |2
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

 Detailed shop-drawings design, supply, installation and testing of about 200 km of HDPE
pipes for a new water distribution network diameter ranging from 63mm to 450mm
including fittings, accessories, related manholes, 11 DMA’s chambers, 185 fire hydrants and
8,490 house connections in the cities of Khashuri, Osiauri and Tskhramukla.
Decommissioning of existing water supply pipelines.
 Detailed shop-drawings design, supply, installation and testing of about 44.5 km of
wastewater gravity collectors with diameters from 200mm to 800mm for the replacement of
a part of the wastewater network in Khashuri including manholes and house connections.
The overall Project area is located in Khashuri in the central part of the Georgia. The general
objective of the project is to improve the water supply services and the wastewater collection in this
town.

1.2 Purpose

The purpose of this document is to establish the procedure for the dewatering system in the ground
where the groundwater table/ water seepage area is above the excavation level, and to remove/
divert the same water until a dry working environment is obtained for completing the works.

1.3 Key Stakeholders

Employer - United Water Supply Company of Georgia


Engineer - EPTISA SERVICIOS de INGENIERIA, S.L.
Contractor - YDA & ARDEM JOINT VENTURE
Subcontractor – İNTAŞ Contracting Construction Industry Trade Inc.
Local Authotities – Khashuri Municipality and Its Subordinate Departments
Security Departments-Police Division
Service Providers-Telecom, Energy, Gas Providers, etc.

1.4 Project Schedule


Date of Signature of Works Contract - 7th of December 2022

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
Page |3
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

Commencement Date- 28th of April 2023


Duration of the work - 1200 days
Date of Completion – 9th of August 2026

1.5 Abbreviations
ITP Inspection and Test Plan

ESHS Environment, Social, Health and Safety

QA/QC Quality Assurance/Quality Control

QCP Quality Control Plan

MAF Material Approval Form

TBT Toolbox Talk

IFC Issued for Construction

IPC Interim Payment Certificate

1.6 References

No. Name of Reference Document Definition

1. Technical Specification Section_02100 Site Preparation

2. Technical Specification Section_02215 Trench Excavation

3. Technical Specification Section_14103 HDPE Pipes

4. Technical Specification Section_14110 Water Supply Connect

5. KHYDA-WSS-CP-P01 PLAN CROSSING

6. KHYDA-WSS-RC-STR-D01 №:1 - RAILWAY CROSSING

7. KRWSS-MS-003 Method Statement for Water Network

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
Page |4
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

Construction

2. PREPARATION

2.1 Site Investigation

Prior to the starting of the works, the Contractor has investigated the existing pipelines as well as
other underground facilities. The representatives of relevant departments of local utilities such as
water, gas electricity and telecommunication will be involved in investigation works. The special
attention will be paid to avoid damaging the existing fiber optic, energy, gas and other important
lines. The statement of construction method for the pipe laying work will be submitted to Police,
Road Department of the local Government and other authorities concerned prior to commencing the
work on public roads for getting their approval. Before excavation, photos of existing situations of
the coverings and surrounding structures will be taken. If there are any damages in the surrounding
areas, this will be documented and submitted for The Engineer's review.

2.2 Site Mobilization

Construction materials will be stocked in the Contractor’s warehouses. Currently Contractor holds 2
warehouses. One of them locates near the Contractor’s office area, another one locates in Surami
district. The location of water supply network construction activity is not permanent. Week by week
work will be done in different streets. Therefore, Contractor may arrange additional warehouses in
different locations to make easy the material transportation. This issue will be agreed with Engineer
and Local Authorities. Exact number of equipment and construction material will be delivered to
construction site to avoid road blockage or messy environment.

2.3 Responsibilities

Contractor management team is responsible for communicating and sharing all relevant
Project Procedures.

Construction Manager is responsible for;


Khashuri Water Supply and Sanitation Project
Method Statement for Water Network Crossings
Page |5
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

 Implementation of the ESHS plan


 Implementation of the Quality Plan
 Implementation of the Construction Plan
 Assessing resource levels to ensure the Construction Schedule is achieved

ESHS Manager is responsible for;

 Developing the ESHS Plan


 Ensuring the ESHS Plan is implemented across all construction activities
 Along with the Construction Manager producing Risk Assessment
 Carrying out Safety Audits
 Carrying out investigations
 Prepare Waste Management Plan and ensure working of plan at the workplace

QA/QC Manager is responsible for;

 Developing and submitting all Quality Assurance and Quality Control Plans (QCP)
 Ensuring all procured materials meet the project requirements with an approved
MAF
 Ensuring all works are done according to Project Requirements
 Make sure all inspections are conducted as per approved QCP
 Ensuring all NCR are punch points are closed out as per the project requirements

ESHS Supervisor is responsible for;


 Daily monitoring of all activities to ensure safety compliance
 Delivering/Attending daily TBT and Pre-start talks
 Ensuring compliance with the Method Statement and Risk Assessment
 Ensuring PPE compliance
 Ensuring housekeeping standards are maintained

Site Engineer is responsible for;

 Ensuring all works are carried out in accordance with the approval Risk Assessment
 Ensuring all works are done in accordance with the approved Method Statement
 Ensuring all works are conduct according to issue for construction documents
 Make sure all works are carried out based on project quality requirements
 Advising with Construction Manager of any slippage against the schedule
 Advising with Construction manager of any resource discrepancies
Khashuri Water Supply and Sanitation Project
Method Statement for Water Network Crossings
Page |6
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

 Working with the ESHS Supervisor to ensure the Health and Safety of the
workforce

Site Workforce is responsible for;

 Must be actively involved during pre-work TBT and Pre-start


 Must be able to fully understand the work to be done and use the right hand tools
 Should not do risky work, he should inform the site manager

2.4 Health and Safety Measures

Contractor will ensure suitable ESHS coverage during the execution of the work according to the
approved ESHS Plan and Local Regulations to ensure a high standard of Health and Safety is
onsite.
No works will be progressed without;
 An approved Method Statement
 An approved Risk Assessment
All operatives will be;
 Made aware the extent and location of the works
 Informed of any restricted areas
 Informed of any hazardous areas.
 Given daily prestart briefings including Risk Assessment for the works in progress
 Reported daily and other frequency indicated in QA/QC document with possible record
 Made aware of the minimum PPE requirements (boots, hi-vis, hard hat, LEP)
 Information and warning tables will be installed in the streets where construction activities
will take place. Information tables will include all required project information.
 Because construction activities will take place in the populated streets, without flagman no
any machinery can be used at the site.

2.5 Permits and Licenses

Before starting the construction activities, all required local authorities, services and utility
providers were officially asked regarding to existing underground utilities which could be damaged
while construction at site. Received letters, drawings, photos and technical conditions are obtained

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
Page |7
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

and investigated by Contractor. Before any manipulating to the existing services while construction,
Contractor will contact with responsible organization.

2.6 RESPONSIBILITIES

The responsibilities and authorities of Project personnel shall be assigned as per the project
requirements.

Project in Charge:

1. Ensure that the project works are carried out with the requirement of this Method Statement
and project document/specification as well as QCS 2010.
2. Ensure full compliance of the subcontractors with the company quality policies and the
Method Statement.
3. To ensure that all the required equipment to execute the works according to the
construction program are available, in good condition and provide any additional
equipment that might be required.
4. To co-ordinate with the Construction manager, Project Engineer, Safety Engineer, Foreman
and Surveyor for safe and proper execution of the works as per the Method Statement.
5. To guide specific attention to all safety measures in co-ordination with the safety
officer/engineer.

Construction Manager:

1. Ensure area is ready and sage to start the works.

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
Page |8
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

2. Ensure all the required approvals/NOC is obtained from the relevant authorities prior to the
commencement of works.
3. Set up required equipment and plant through discussion with the Project In Charge and
Project Engineer.
4. Ensure the works are carried out according to the specification, quality plan, approved shop
drawings and construction program.
5. Provide sufficient and safe access for operatives, trucks and pumps.
Site Engineer:

1. Set up the required equipment and allocate required manpower through discussion with the
Project In Charge and Construction Manager.
2. Ensure works are carried out according to the specification, quality plan, approved shop
drawings and the construction program.
3. Provide sufficient and safe access for operatives, trucks and pumps.

QA/QC Engineer:

1. Ensure that Consultant/Client inspection requests are implemented.


2. Compilation of all necessary quality control check lists.
3. The control of work performed at site by means of checking the work before consultant’s
inspection.
4. Issuing RFI’s and assisting consultant during the inspections.

HSE Engineer:

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
Page |9
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

1. To ensure implementation of all safety measures related to the nature of works being
carried out, and in accordance with the Project CEMP.
2. To ensure that all the persons involved in the works are aware of their responsibilities, and
that they have enough understanding of the safety procedures.
3. To provide and distribute risk assessment of the various activities
4. The safety officer in co-ordination with the Project In Charge shall ensure that all the
implemented safety measures are effective enough to maintain safe working on the site.
5. To maintain continuous inspections of the site activities and advise and train persons on a
daily basis to prevent accidents and personnel injury.
6. To give special concern to housekeeping and ensure that the site is maintained clean and
tidy.
7. To ensure all the relevant safety sign boards for different works are in place.
Surveyor:

1. To establish benchmarks from agreed reference points, provide required setting out and
level markings and follow up with regular checks.
2. Co-ordinate with the project engineer and ensure the approved shop drawing shall be
implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise
the project manager of any deviation from the drawings.

2.7 METHODOLOGY

DEEP WELL SUMP:


Determination excavations shall be made to determine the water level at the locations indicated in
the geotechnical report.
The dewatering pump will be placed at the location determined by the site authorities.
Dewatering will be carried out by two or any of the following methods as appropriate.

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
P a g e | 10
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri
METHOD STATEMENT FOR
DEWATERING

The area for installing deep sump well will be marked by surveyor and the area will be checked for
existing underground utilities.
The sump well will be installed into the ground using water jet. If the strata are hard to penetrate,
then suitable bore holes will be made for installing the deep well sump.
After the hole is drilled, an Ø300mm UPVC or CHDPE perforated pipe is installed into the drilled
hole surrounded with 3/8 3/16 aggregate filter materials to prevent the fines entering the system.
The submersible pump will be installed into the perforated pipe. The pump is connected to the
electrical power generator.
The outlet of these well pumps is connected to the vertical pipes, which is connected to the suction
hose.
The suction hose transfers the water to the sand settling tank. The silts settled in the tanks will be
removed and dumped in an approved location.
The pumps will be operated until the work is completed. On completion of all dewatering activities
the bore holes will be filled with suitable approved material.
Water levels will be checked and recorded regularly to derive the drawdown.

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
P a g e | 11
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri

METHOD STATEMENT FOR


DEWATERING

OPEN CUT SUBMERSİBLE PUMP SYSTEM:


At areas affected by low water seepage, an open cut submersible pumping system will be installed
to pump out the seeping water instead of the deep well system.
The size of the pump will depend on the amount of seepage occurring.
The pump will be placed at a low level area.
The water is pumped to the settling tank using a flat suction hose.
The water will be removed periodically from the settling tank to avoid spilling of water.
The silt will be removed and dumped at an approved location.

3. INSPECTION

Through daily schedule Engineer will be informed about Inspections. As per approved Quality
Control Plan documentations site activities will be inspected by Engineer and Contractor Quality
Control team. On the QCP documents and daily schedule the location and time of inspection will be
indicated.

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
P a g e | 12
Khashuri Water Supply and Sanitation Project

Project: Lot 1 - Upgrade of Water Supply and Sewerage


Systems in Khashuri

METHOD STATEMENT FOR


DEWATERING

4. Handover Procedures

As per Contract Documentations, after completion of works, it shall be hand overed to the Engineer
and Employer. Therefore, all site activities will be inspected and required Quality Control
documents, site check sheets, approval forms will be filled and signed. All of these documents and
as-built drawings will be part of Handover documents.

Khashuri Water Supply and Sanitation Project


Method Statement for Water Network Crossings
P a g e | 13