A field visit was made by Assistant Divisional Monitoring Officer (T) along with SDO and SubEngineer of Public Health Engineering Department on 20th May 2010 to monitor the physical and
financial progress of the subject scheme.
A. DESCRIPTION
To overcome the water shortage in Ayub Medical College, a scheme was approved at a cost of Rs.
39.968 million in PDWP meeting held on 15th April 2008.
Technical sanction amounting to Rs. 43.548 million has been accorded on 25 th September 2008. The
work was commenced on August 1st, 2008 with a tentative date of completion in June 2010.
B. SCOPE OF WORK AND PHYSICAL PROGRESS
The scope of work is as under: (Rs. in millions)
S.N
o

Description

Cost

Physical Progress
The land was
provided free of cost
by the owner.

Cost of Land

2.000

Tube Well (4 Nos.)

4.654

Pumping Chamber /Chowkidar Hut


External/Internal Electrification
(4 Nos.)

1.533
1.300

50% completed

Pumping Machinery (4 Nos.)

2.270

Purchased & Installed

Rising Main 8 dia

31.592

Completed

Completed

C. ANALYSIS AND RECOMMENDATIONS


1. The raising main is passed in the main sewer line on Mansehra Abbottabad Road. Any small
leakage in the pipe will cause contamination of water and may lead to epidemic as this water is
used in operation theaters and wards where patients are already porn to diseases. The
department may be asked to provide required treatment to the raising main to avoid any mishap.

Page 2 of 3

2. The pipes are connected using welding instead of joints and sockets. No test of welding has
been carried out yet. The department may be asked to conduct field testing of welds to ensure
that no leakage and thus contamination will happen in the designed period of project.

3. The pipes used were checked and found of specified thickness and from approved firm.

4. Two tube wells are functional while the remaining two are still awaited for energization by
WAPDA. The department may be asked to approach higher authorities of WAPDA for
expedition of energization of scheme.