Description
Cost
Physical Progress
The land was
provided free of cost
by the owner.
Cost of Land
2.000
4.654
1.533
1.300
50% completed
2.270
31.592
Completed
Completed
Page 2 of 3
2. The pipes are connected using welding instead of joints and sockets. No test of welding has
been carried out yet. The department may be asked to conduct field testing of welds to ensure
that no leakage and thus contamination will happen in the designed period of project.
3. The pipes used were checked and found of specified thickness and from approved firm.
4. Two tube wells are functional while the remaining two are still awaited for energization by
WAPDA. The department may be asked to approach higher authorities of WAPDA for
expedition of energization of scheme.
Page 3 of 3