OFFICE OF THE EXECUTIVE ENGINEER

SWABI IRRIGATION DIVISION-I SWABI


PHONE & FAX NO.0938-530484
No. /2/2-A (21-22) Dated Swabi the /12/2021
To

The Superintending Engineer,


Swabi Irrigation Circle,
Swabi.

Subject: ANTICIPATORY DEAMNDS/ADDITIONAL REQUIREMENTS OF


DEVELOPMENT FUNDS

It is intimated for your kind information that the funds under various ADPs were placed at the
disposal of this Division have fully been utilized. The site activities are in progress with full swing and the concerned
Govt; Contractors are constantly attending this office and stressing hard for making the payment and arranged of
balance funds on they apprehended that the payment will abnormally been delayed and they suspended their site
activities. The concerned MPAs are also taking keen interest for early completion of the on-going schemes to
facilitate general public. Details as under;-
S No & Name of ADP Approved Allocation Released Dg: Amount Additional Full justification of
# Scheme. Cost during 2021-22 Utilized fund the Additional
N 2021-22 along with Required demand
o Utilization
Certificate
1 2160/150775;- Construction 341.45 6.57 (M) 5.57 5.57 (M) 76.26 (M) The additional funds
of Canal Petrol Road & (M) are required for
flood protection works in clearance of
Tarakai, Dobian & liabilities and for
Adjoining area in District completion of
Swabi . schemes to achieve
perceived objectives.
2 2273/160597;- Improvement 200.00 23.830 (M) 23.830 (M) 23.830 (M) 12.99 (M) The additional funds
& Construction of Irrigation (M) are required for
facilities i/c FPW's, Tube completion of
Wells, Roads on canal and schemes.
drains in U/C Dagi, Tarakai, The Schemes was
Turlandi, Asota, Sheikh Jana, delayed due to non-
Karnal Sher Kalay, Shewa, receipt of funds.
Parmoli, Naranji, Yar
Hussain, Kalu Khan, Adina &
other Adjoining areas Distt:
Swabi, (PK-46 & 47)
3 2278/190474;- Improvement 300.00 40.00 (M) 40.00 (M) 40.00 (M) 250.00M) The additional funds
and Construction of Irrigation (M) are required for
facilities i.e FPWs, Canal completion of
Patrol Roads and drains in schemes.
U/C Chaknoda, Sheikh Jana,
KSK, Asota, Parmoli, Shewa,
Naranji, Kalu Khan, Adeena,
Turlandi and Tarakai Swabi
Forgoing in view, for accelerating the progress and early completion of the on-going ADP
Schemes, your goodself is requested to kindly approach the higher ups for arrangement of funds under the above
mentioned ADPs during 2021-22,so as to enable this Office to make the payments to the concerned Govt; Contractors
and to complete the schemes well in time, please.
Executive Engineer,
Swabi Irrigation Division-I,
Swabi
Copy forwarded to the:-
1. Account Officer, O/O the Secretary to Govt: of Khyber Pakhtunkhwa Irrigation Department
Peshawar for information & similar necessary action, please.
2. Accounts Officer O/O the Chief Engineer (North) Irrigation Department Peshawar for information and as
requested above, please.

Executive Engineer,
OFFICE OF THE EXECUTIVE ENGINEER
SWABI IRRIGATION DIVISION-I SWABI
PHONE & FAX NO.0938-530484
No. /2/2-A (21-22) Dated Swabi the /12/2021
To

The Superintending Engineer,


Swabi Irrigation Circle,
Swabi.

Subject: ANTICIPATORY DEAMNDS/ADDITIONAL REQUIREMENTS OF


DEVELOPMENT FUNDS

It is intimated for your kind information that the funds under the ADP were placed at the disposal of
this Division have fully been utilized. The site activities are in progress with full swing and the concerned Govt;
Contractors are constantly attending this office and stressing hard for making the payment and threaten that they will
be suspended the site activities on account of non-payment well in time. The concerned MPAs are also taking keen
interest for early completion of the on-going schemes.
S# No & Name of ADP Approved Allocation Released Amount Additional Full justification
No Scheme. Cost during Dg: 2021-22 Utilized fund of the Additional
2021-22 along with Required demand
Utilization
Certificate
1 2140/140540 Imprt: of 123.439 34.00 2.00 (M) 2.00 (M) 25.00 (M) The remaining
Roads along Canals & funds are
Drainage system in KPK. (M) (M) required for
completion of
schemes.
2 2349/160280 8.00 (M) 100.00( 2.50 (M) 2.50 (M) 4.00 (M) The remaining
Construction/Improvemen funds are
M) required for
t of Irrigation channels,
Bridges, Culverts, Small completion of
Storage Ponds and schemes.
Drainage system in
Khyber Pakhtunkhwa

Forgoing in view, for accelerating the progress and early completion of the on-going ADP
Schemes, your goodself is requested to kindly approach the higher ups for arrangement of funds under the above
mentioned ADP during 2021-22,so as to enable this Office to make the payments to the concerned Govt; Contractors
and to complete the schemes well in time, please.

Executive Engineer,
Swabi Irrigation Division-I,
Swabi
Copy forwarded to the:-
3. Account Officer, O/O the Secretary to Govt: of Khyber Pakhtunkhwa Irrigation Department
Peshawar for information & similar necessary action, please.
4. Accounts Officer O/O the Chief Engineer (North) Irrigation Department Peshawar for information and as
requested above, please.

Executive Engineer,
OFFICE OF THE EXECUTIVE ENGINEER
SWABI IRRIGATION DIVISION-I SWABI
PHONE & FAX NO.0938-530484
No. /2/2-A (21-22) Dated Swabi the /12/2021
To

The Superintending Engineer,


Swabi Irrigation Circle,
Swabi.

Subject: ANTICIPATORY DEAMNDS/ADDITIONAL REQUIREMENTS OF


DEVELOPMENT FUNDS

It is intimated for your kind information that the funds under various ADPs were placed at the
disposal of this Division have fully been utilized. The site activities are in progress with full swing and the concerned
Govt; Contractors are constantly attending this office and stressing hard for making the payment and threaten that
they will be suspended the site activities on account of non-payment well in time. The concerned MPAs are also
taking keen interest for early completion of the on-going schemes.
S# No & Name of ADP Approved Allocation Released Amount Additional Full justification
No Scheme. Cost during Dg: 2021-22 Utilized fund of the Additional
2021-22 along with Required demand
Utilization
Certificate
1 2160/150775 341.45 6.57 (M) 5.57 5.57 (M) 76.26 (M) Liabilities of the
Construction of Canal (M) contractors are
Petrol Road & flood pending for want
protection works in of additional
funds
Tarakai, Dobian &
Adjoining area in
District Swabi .
2 2273/160597 200.00 23.830 23.830 23.830 12.99 (M)
Improvement & (M) (M) (M) (M)
Construction of
Irrigation facilities i/c
FPW's, Tube Wells,
Roads on canal and
drains in U/C Dagi,
Tarakai, Turlandi,
Asota, Sheikh Jana,
Karnal Sher Kalay,
Shewa, Parmoli,
Naranji, Yar Hussain,
Kalu Khan, Adina &
other Adjoining areas
Distt: Swabi, (PK-46 &
47)
3 2278/190474 300.00 40.00 40.00 40.00 250.00M)
Improvement and (M) (M) (M) (M)
Construction of
Irrigation facilities i.e
FPWs, Canal Patrol
Roads and drains in
U/C Chaknoda, Sheikh
Jana, KSK, Asota,
Parmoli, Shewa,
Naranji, Kalu Khan,
Adeena, Turlandi and
Tarakai Swabi
S# No & Name of ADP Approved Allocation Released Amount Additional Full justification
No Scheme. Cost during Dg: 2021-22 Utilized fund of the Additional
2021-22 along with Required demand
Utilization
Certificate
5 8.00 (M) 2.50 (M) 2.50 (M) 4.00 (M)
2349/160280 100.00(
Construction/Improvem
ent of Irrigation
M)
channels, Bridges,
Culverts, Small Storage
Ponds and Drainage
system in Khyber
Pakhtunkhwa
6 2271/160291 39.25 (M) 22.42 1.942 1.942 7.12 (M)
Construction/Improvem (M) (M) (M)
ent of Irr: Infrastructure
i/c FPW, Channels,
Ponds, Roads, T/Ws &
Drainage system in
Tordher, Jalbai, Jalsai,
Lahor, Anbar & other
areas Distt: Swabi
7 2352/160513 10.926 (M) 52.67 0.154 0.154 4.89 (M)
Installation of Solar (M) (M) (M)
Augmentation /
Irrigation Tube Well in
Khyber Pakhtunkhwa
8 2338/140538 59.175 (M) 29.50 8.44 (M) 8.44 (M) 4.00(M)
Construction / (M)
Improvement of
Bridges on Canal &
Drainage System in
Khyber Pakhtunkhwa
9 2140/140540 Imprt: 123.439 34.00 2.00 (M) 2.00 (M) 25.00 (M)
of Roads along (M) (M)
Canals & Drainage
system in KPK.

10 2343/150436 Imprt: of 48.055 (M) 59.00 3.00 (M) 3.00(M) 5.00 (M)
Roads along Canals (M)
& Drainage system in
KPK.

11 2344/150437 Imprt: of 20.558 (M) 17.70 2.30 (M) 2.30 (M) 7.50 (M)
Roads along Canals (M)
& Drainage system in
KPK.

S# No & Name of ADP Approved Allocation Released Amount Additional Full justification
No Scheme. Cost during Dg: 2021-22 Utilized fund of the Additional
2021-22 along with Required demand
Utilization
Certificate
12 2371/200193 70.00 (M) 8.885 8.885 3.27 (M) 56.115
Construction and (M) (M) (M)
Rehabilitation of Canal
Patrol Old Road from
Kaddi Minor to Khattak
Salai, Gulo Derhi, District
Swab
13 2205/170597 23.55 50.00 3.30 (M) 3.30 (M) 15.00 (M)
Provision of Irrigation (M) (M)
Augmn; T/Wells & LIS at
required places in KPK.
14 2247/200233 50.00 (M) 11.80 5.90 (M) 5.505 27.25(M)
Construction/ Rehabilitaion (M) (M)
of Canal Roads/ Bridges/
Culverts/ Retaining Walls/
Flood Protection walls and
Installation of 06 Solar Tube
Wells at U/C Gumbat,
Ismailzai, Bala Ghari,
Kandar, Thoro Mayar,
Muhib Banda, Coat Dolatzai,
Baar Nullah Mehmood Abad
Mardan.
16 2146/140571 617.30 29.50 29.50 29.50 35.00(M)
Rehabilitation Of CPR along (M) (M) (M) (M)
Machai Br: & its sub
systems i.c installation of
vehicle weighting
arrangements Distt: Mardan

S# No & Name of ADP Approved Allocation Released Amount Additional Full justification
No Scheme. Cost during Dg: 2021-22 Utilized fund of the Additional
2021-22 along with Required demand
Utilization
Certificate
17 2235/190477 215.072 40.00 23.35 14.30 171.00
Construction of small (M) (M) (M) (M) (M)
bridges, Irrigation
channels, FPW & CPR in
U/C Machai
bazzar ,Rustam,
Charghuli , Palodheri
Kata khat Jamal Garhi ,
Sawaldher, Katlang-I&II
Construction of FPWin
Mathra kanda (pasand
kothy)in village Landi
District Mardan.

18 2240/190526 Reh;/ 123.85 (M) 30.00 30.00 8.706 88.85(M)


Improvement of Irrigation (M) (M) (M)
ficilities i/c Revamping of
Drainage system in U/Cs
Shahbaz Garhi baghicha
Dheri Garhi Daulat Zai ,
Kot Daulatzai, Kot
Ismailzai , Gujrat Buxali ,
Mardan
Forgoing in view, for accelerating the progress and early completion of the on-going ADP Schemes,
your goodself is requested to kindly approach the higher ups for arrangement of funds under the above mentioned
ADPs during 2021-22,so as to enable this Office to make the payments to the concerned Govt; Contractors and to
complete the schemes well in time, please.
OFFICE OF THE EXECUTIVE ENGINEER
SWABI IRRIGATION DIVISION-I SWABI
PHONE & FAX NO.0938-530484
No. /2/2-A (21-22) Dated Swabi the /01/2022
To

The Superintending Engineer,


Swabi Irrigation Circle,
Swabi.

Subject: ANTICIPATORY DEAMNDS/ADDITIONAL REQUIREMENTS OF


DEVELOPMENT FUNDS

It is intimated for your kind information that the funds under various ADPs were placed at the
disposal of this Division have fully been utilized. The site activities are in progress with full swing and the concerned
Govt; Contractors are constantly attending this office and stressing hard for making the payment and arranged of
balance funds on they apprehended that the payment will abnormally been delayed and they suspended their site
activities. The concerned MPAs are also taking keen interest for early completion of the on-going schemes to
facilitate general public. Details as under;-
S No & Name of ADP Approved Allocation Released Dg: Amount Additional Full justification of
# Scheme. Cost during 2021-22 Utilized fund the Additional
N 2021-22 along with Required demand
o Utilization
Certificate
1 2160/150775;- Construction 341.45 6.57 (M) 5.57 5.57 (M) 76.26 (M) The additional funds
of Canal Petrol Road & (M) are required for
flood protection works in clearance of
Tarakai, Dobian & liabilities and for
Adjoining area in District completion of
Swabi . schemes to achieve
perceived objectives.

2 2273/160597;- Improvement 200.00 23.830 (M) 23.830 (M) 23.830 (M) 12.99 (M) The additional funds
& Construction of Irrigation (M) are required for
facilities i/c FPW's, Tube completion of
Wells, Roads on canal and schemes.
drains in U/C Dagi, Tarakai, The Schemes was
Turlandi, Asota, Sheikh Jana, delayed due to non-
Karnal Sher Kalay, Shewa, receipt of funds.
Parmoli, Naranji, Yar
Hussain, Kalu Khan, Adina &
other Adjoining areas Distt:
Swabi, (PK-46 & 47)
3 2278/190474;- Improvement 300.00 40.00 (M) 40.00 (M) 40.00 (M) 250.00M) The additional funds
and Construction of Irrigation (M) are required for
facilities i.e FPWs, Canal completion of
Patrol Roads and drains in schemes.
U/C Chaknoda, Sheikh Jana,
KSK, Asota, Parmoli, Shewa,
Naranji, Kalu Khan, Adeena,
Turlandi and Tarakai Swabi

4 2146/140571 Rehabilitation 617.30 29.50 (M) 29.50 (M) 29.50 (M) 34.00 (M) The additional funds
Of CPR along Machai Br: & (M) are required for
its sub systems i.c installation completion of
of vehicle weighting schemes.
arrangements Distt: Mardan

5 2235/190477 Construction of 215.072 40.00 (M) 23.35 (M) 23.35 (M) 151.00 (M) The additional funds
small bridges, Irrigation (M) are required for
channels, FPW & CPR in U/C completion of
Machai bazzar ,Rustam, schemes.
Charghuli , Palodheri Kata
khat Jamal Garhi , Sawaldher,
Katlang-I&II Construction of
FPWin Mathra kanda (pasand
kothy)in village Landi District
Mardan.
S No & Name of ADP Approved Allocation Released Dg: Amount Additional Full justification of
# Scheme. Cost during 2021-22 Utilized fund the Additional
N 2021-22 along with Required demand
o Utilization
Certificate
6 2247/200233 Construction/ 50.00 (M) 11.80 (M) 5.90 (M) 5.90 (M) 27.00 (M) The additional funds
Rehabilitaion of Canal Roads/ are required for
Bridges/ Culverts/ Retaining completion of
Walls/ Flood Protection walls schemes.
and Installation of 06 Solar
Tube Wells at U/C Gumbat,
Ismailzai, Bala Ghari, Kandar,
Thoro Mayar, Muhib Banda,
Coat Dolatzai, Baar Nullah
Mehmood Abad Mardan.

Forgoing in view, for accelerating the progress and early completion of the on-going ADP
Schemes, your goodself is requested to kindly approach the higher ups for arrangement of funds under the above
mentioned ADPs during 2021-22,so as to enable this Office to make the payments to the concerned Govt; Contractors
and to complete the schemes well in time, please.

Executive Engineer,
Swabi Irrigation Division-I,
Swabi
Copy forwarded to the:-
1. Account Officer, O/O the Secretary to Govt: of Khyber Pakhtunkhwa Irrigation Department
Peshawar for information & similar necessary action, please.
2. Accounts Officer O/O the Chief Engineer (North) Irrigation Department Peshawar for information and as
requested above, please.

Executive Engineer,
OFFICE OF THE EXECUTIVE ENGINEER
SWABI IRRIGATION DIVISION-I SWABI
PHONE & FAX NO.0938-530484
No. /2/2-A (21-22) Dated Swabi the /01/2022
To

The Superintending Engineer,


Swabi Irrigation Circle,
Swabi.

Subject: ANTICIPATORY DEAMNDS/ADDITIONAL REQUIREMENTS OF


DEVELOPMENT FUNDS

It is intimated for your kind information that the funds under the ADP were placed at the disposal of
this Division have fully been utilized. The site activities are in progress with full swing and the concerned Govt;
Contractor are constantly attending this office and stressing hard for making the payment and arranged of balance
funds on they apprehended that the payment will abnormally been delayed and they suspended their site activities.
The concerned MPAs are also taking keen interest for early completion of the on-going scheme to facilitate general
public. Details as under;-

S No & Name of ADP Approved Allocation Released Dg: Amount Additional Full justification of
# Scheme. Cost during 2021-22 Utilized fund the Additional
N 2021-22 along with Required demand
o Utilization
Certificate
4 2148/140571;- 617.30 29.50 (M) 29.50 (M) 29.50 (M) 34.00 (M) The additional funds
Rehabilitation Of CPR (M) are required for
along Machai Br: & its sub completion of
systems i.c installation of scheme.
vehicle weighting
arrangements Distt:
Mardan

Forgoing in view, for accelerating the progress and early completion of the on-going ADP
Schemes, your goodself is requested to kindly approach the higher ups for arrangement of funds under the
above mentioned ADP during 2021-22,so as to enable this Office to make the payments to the concerned
Govt; Contractor and to complete the scheme well in time, please.

Executive Engineer,
Swabi Irrigation Division-I,
Swabi
Copy forwarded to the:-
1. Account Officer, O/O the Secretary to Govt: of Khyber Pakhtunkhwa Irrigation Department
Peshawar for information & similar necessary action, please.
2. Accounts Officer O/O the Chief Engineer (North) Irrigation Department Peshawar for information and as
requested above, please.

Executive Engineer,
OFFICE OF THE EXECUTIVE ENGINEER
SWABI IRRIGATION DIVISION-I SWABI
PHONE & FAX NO.0938-530484
No. /2/2-A (21-22) Dated Swabi the /02/2022
To

The Superintending Engineer,


Swabi Irrigation Circle,
Swabi.

Subject: ANTICIPATORY DEAMNDS/ADDITIONAL REQUIREMENTS OF


DEVELOPMENT FUNDS

It is intimated for your kind information that the funds under the ADP were placed at the disposal of
this Division have fully been utilized. The site activities are in progress with full swing and the concerned Govt;
Contractors are constantly attending this office and stressing hard for making the payment and arranged of balance
funds on they apprehended that the payment will abnormally been delayed and they suspended their site activities.
The concerned MPA are also taking keen interest for early completion of the on-going scheme to facilitate general
public. Details as under;-

S No & Name of ADP Approved Allocation Released Dg: Amount Additional Full justification of
# Scheme. Cost during 2021-22 Utilized fund the Additional
N 2021-22 along with Required demand
o Utilization
Certificate
2 2273/160597;- Improvement 200.00 23.830 (M) 23.830 (M) 23.830 (M) 12.99 (M) The additional funds
& Construction of Irrigation (M) are required for
facilities i/c FPW's, Tube completion of
Wells, Roads on canal and schemes.
drains in U/C Dagi, Tarakai, The Schemes was
Turlandi, Asota, Sheikh Jana, delayed due to non-
Karnal Sher Kalay, Shewa, receipt of funds.
Parmoli, Naranji, Yar
Hussain, Kalu Khan, Adina &
other Adjoining areas Distt:
Swabi, (PK-46 & 47)

Forgoing in view, for accelerating the progress and early completion of the on-going ADP
Schemes, your goodself is requested to kindly approach the higher ups for arrangement of funds under the
above mentioned ADP during 2021-22,so as to enable this Office to make the payments to the concerned
Govt; Contractors and to complete the scheme well in time, please.

Executive Engineer,
Swabi Irrigation Division-I,
Swabi
Copy forwarded to the:-
1. Account Officer, O/O the Secretary to Govt: of Khyber Pakhtunkhwa Irrigation Department
Peshawar for information & similar necessary action, please.
2. Accounts Officer O/O the Chief Engineer (North) Irrigation Department Peshawar for information and as
requested above, please.

Executive Engineer,
OFFICE OF THE EXECUTIVE ENGINEER
SWABI IRRIGATION DIVISION-I SWABI
PHONE & FAX NO.0938-530484
No. /2/2-A (21-22) Dated Swabi the /02/2022
To

The Superintending Engineer,


Swabi Irrigation Circle,
Swabi.

Subject: CUT OFF DATE FOR INTRA-SECTORAL RE-APPROPRIATION (KP ADP) 2021-22.